D.1.b. Pavement Justification Report Intersection Improvements at Bayfront Highway.pdf
PDF 8 MB Posted
- Solicitation number
- B27000553
- Issued by
- Hawaii County, Hawaii
About this file
This is a Pavement Justification Report prepared by Geolabs, Inc. for AECOM on behalf of the Hawaii Department of Transportation (HDOT) and Hawaii County for the Intersection Improvements at Bayfront Highway project in Hilo, Hawaii. The report presents geotechnical engineering analyses and pavement design recommendations for converting an existing intersection into a single-lane roundabout with associated roadway reconstruction. The analysis is based on field exploration consisting of ten borings drilled to depths of 15.5 to 41.5 feet below the existing pavement surface, laboratory testing of soil samples, and economic analysis of pavement design options. The report recommends flexible asphaltic concrete pavement sections consisting of 4.0 inches of asphaltic concrete over 6.0 inches of aggregate base course and 7.0 inches of aggregate subbase for Bayfront Highway, and 4.0 inches of asphaltic concrete over 8.0 inches of aggregate base course and 12.0 inches of aggregate subbase for Kamehameha Avenue, with a 10.0-inch Portland Cement Concrete pavement section for the truck apron. The report was prepared as of September 16, 2022, with soil and rock samples retained for two months from the report date.
The report provides technical specifications for pavement subgrade preparation, requiring scarification to 8 inches depth with recompaction to 95 percent relative compaction above optimum moisture content. Critical construction recommendations include proof-rolling operations using a minimum 10-ton vibratory drum roller with eight passes to detect and collapse near-surface cavities and voids, placement of non-woven geotextile filter fabric on the recompacted subgrade, and proper surface drainage maintenance to prevent pumping and premature pavement failure. The report notes that groundwater was encountered at depths varying from 5.2 to 15 feet below the existing pavement surface and identifies the presence of severely corroded sheetpile and tieback anchors along Bayfront Highway that may contribute to pavement distress. Geolabs recommends retaining geotechnical engineering services during construction for monitoring subgrade preparation, fill placement, and compaction testing, with provisions for design modifications if actual site conditions differ from those assumed in the analysis.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAVEMENT JUSTIFICATION REPORT
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
HILO, ISLAND OF HAWAII
W.O. 8467-00 SEPTEMBER 16, 2022
Prepared for
AECOM
GEOLABS, INC.
Geotechnical Engineering and Drilling Services
PAVEMENT JUSTIFICATION REPORT
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
Prepared for
THIS WORK WAS PREPARED BY
ME OR UNDER MY SUPERVISION.
4-30-24
SIGNATURE EXPIRATION DATE
OF THE LICENSE
94-429 Koaki Street, Suite 200 • Waipahu, HI 96797
Hawaii • California
94-429 Koaki Street, Suite 200 • Waipahu, Hawaii 96797
Telephone: (808) 841-5064 • E-mail: hawaii@geolabs.net
September 16, 2022 W.O. 8467-00
Ms. Catherine Crawford
1001 Bishop Street, Suite 1600 Honolulu, HI 96813
Dear Ms. Crawford:
Geolabs, Inc. is pleased to submit our report entitled "Pavement Justification Report, Intersection Improvements at Bayfront Highway, Hilo, Island of Hawaii," prepared for the design of the roadway reconstruction project.
Our work was performed in general accordance with the scope of services outlined in our revised fee proposal, dated March 25, 2022.
Please note that the soil and rock samples recovered during our field exploration (remaining after testing) will be stored for a period of two months from the date of this report. The samples will be discarded after that date unless arrangements are made for a longer sample storage period. Please contact our office for alternative sample storage requirements, if appropriate.
Detailed discussion and specific design recommendations are contained in the body of this report. If there is any point that is not clear, please contact our office.
Very truly yours, John Y.L. Chen, P.E.
Vice President
JC:TO:lf mailto:hawaii@geolabs.net
W.O. 8467-00 GEOLABS, INC. Page i
PAVEMENT JUSTIFICATION REPORT
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
TABLE OF CONTENTS
Page
SUMMARY OF FINDINGS AND RECOMMENDATIONS .............................................. iii
1. GENERAL
1.1 Introduction
1.2 Project Considerations
1.3 Purpose and Scope
2. SITE CHARACTERIZATION
2.1 Regional Geology
2.2 Subsurface Conditions
3. DISCUSSION AND RECOMMENDATIONS
3.1 Methodology of Pavement Design
3.2 Design Traffic Loading Conditions/Traffic Index
3.3 Design Subgrade Conditions
3.4 Design Pavement Sections
3.5 Surface Drainage
3.6 Design Review
3.7 Construction Monitoring
4. LIMITATIONS
CLOSURE
PLATES
Project Location Map .................................................................................. Plate 1 Site Plan ..................................................................................................... Plate 2
APPENDIX A
Field Exploration ....................................................................... Pages A-1 and A-2 Soil Log Legend ..................................................................................... Plate A-0.1 Soil Classification Log Key .................................................................... Plate A-0.2 Rock Log Legend .................................................................................. Plate A-0.3 Logs of Borings .................................................................... Plates A-1.1 thru A-10
APPENDIX B
Laboratory Tests ...................................................................................... Page B-1 Laboratory Test Data .............................................................. Plates B-1 thru B-18
TABLE OF CONTENTS
Page
W.O. 8467-00 GEOLABS, INC. Page ii
APPENDIX C
Pavement Design ····················································· Plates C-1.1 thru C-4.2 Pavement Design Economical Analysis ························· Plates C-5.1 thru C-6.4
APPENDIX D
Photographs of Core Samples ·········································· Plates D-1 thru D-8
W.O. 8467-00 GEOLABS, INC. Page iii
PAVEMENT JUSTIFICATION REPORT
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
SUMMARY OF FINDINGS AND RECOMMENDATIONS
Our field exploration along Bayfront Highway is generally very loose to very dense fill overlying beach deposits and basalt formation extending to the maximum depth explored of approximately 41.5 feet below the existing pavement surface. The borings along Kamehameha Avenue generally encountered fill materials overlying volcanic ash material extending to the maximum depth explored of approximately 16.5 feet below the existing pavement surface. Groundwater was encountered at depths varying from about
5.2 to 15 feet below the existing pavement surface at the time of exploration.
Based on our field exploration program, we envision that the new pavements will be constructed over the recompacted in-situ sandy/gravelly fills overlying basalt formation and/or volcanic ash material. Based on the anticipated subgrade conditions, the traffic data provided for our pavement analyses, the economic analysis performed, and construction considerations, it is our opinion that new pavements for the roadway reconstruction project may consist of asphaltic concrete over aggregate base course and aggregate subbase material. It should be noted that CBR tests and/or field observations should be performed on the actual subgrade soils during construction to confirm that the above pavement design section is adequate.
Cavities and voids were encountered in some of the borings drilled at shallow depths. We envision that the cavity/void encountered may be caused due to extremely to severely corroded sheetpile sections along the Bayfront Highway, as interpreted by the geophysical surveying exploration. To reduce the risk of future pavement distress due to subgrade material migration, we recommend implementing proof-rolling operation at the pavement subgrade. The proof-rolling operation may be conducted by a large vibratory drum roller (minimum 10 tons static weight) with a minimum of eight passes to help detect and collapse near-surface cavities and/or voids. The vibratory drum roller should be operated at a speed of about 300 feet per minute.
One of the primary distress mechanisms in pavement structures is pumping due to saturation of the base, subbase, and/or subgrade soils. Therefore, the pavement surface should be sloped, and drainage gradients should be maintained to carry surface water off the pavement to appropriate drainage structures.
The text of this report should be referred to for detailed discussions and specific pavement design recommendations.
END OF SUMMARY OF FINDINGS AND RECOMMENDATIONS
W.O. 8467-00 GEOLABS, INC. Page 1
SECTION 1. GENERAL
1.1 Introduction
This pavement justification report presents the results of our geotechnical engineering analyses performed for the Intersection Improvements at Bayfront Highway project in Hilo on the Island of Hawaii. The project location and general vicinity are shown on the Project Location Map, Plate 1.
This report summarizes the findings from our field exploration and laboratory testing and presents our geotechnical recommendations derived from our analyses for the design of new pavements only. The findings and recommendations presented herein are subject to the limitations noted at the end of this report.
1.2 Project Considerations
Based on the information provided, we understand that the State of Hawaii
Department of Transportation (HDOT) – Highway Division is evaluating intersection improvements at Bayfront Highway and Waianuenue Road. It is proposed to construct a roundabout intersection to address the highway operational issues, as well as provide pedestrian accessibility and safety improvements. The approximate limits of the roadway reconstruction project are shown on the Site Plan, Plate 2.
The Bayfront Highway is under the HDOT’s jurisdiction, while Kamehameha
Avenue is under the County’s jurisdiction. As part of the project, geophysical surveying exploration was conducted to estimate the limits/depths of sheetpile along the Bayfront
Highway with locations of the tieback anchors. The geophysical surveying exploration was performed by Global Geophysics. The results of the geophysical surveying exploration are contained in a separate report entitled “Report for Sheet Pile and Tie
Back Location at Bayfront Highway, Hilo, Hawaii,” dated June 16, 2022.
1.3 Purpose and Scope
The purpose of our exploration was to obtain an overview of the surface and subsurface conditions to develop an idealized soil and/or rock data set to formulate geotechnical engineering recommendations for the design of the project. The work was
SECTION 1. GENERAL
W.O. 8467-00 GEOLABS, INC. Page 2 performed in general accordance with our revised fee proposal dated March 25, 2022.
The scope of work for this exploration included the following tasks and work efforts:
1. Research and review available in-house soil data and geologic information in the project vicinity.
2. Obtain the excavation permits from the HDOT-HWY and the County of Hawaii with one-call underground utility clearance with various utility companies for toning of the boring locations.
3. Prepare an accident prevention plan with activity hazard analyses in support of field exploration activities.
4. Mobilization and demobilization of a truck-mounted drill rig presently on the Island of Hawaii and two operators from Honolulu to the project site and back.
5. Drilling and sampling ten boreholes extending to depths of approximately
15.5 and 41.5 feet below the existing ground surface with the provision of traffic control and safety devices during our field exploration program.
6. Coordinate the field exploration and logging of the borings by our field engineer.
7. Laboratory testing on selected soil samples obtained from the field exploration as an aid in classifying the materials and evaluating their engineering properties.
8. Analyze the field and laboratory data to formulate geotechnical engineering recommendations for the proposed roundabout intersection improvement project.
9. Coordinate our overall work by our engineer.
10. Prepare a pavement justification report summarizing our work and presenting our findings and recommendations.
11. Quality assurance and client/design team consultation by our principal engineer.
12. Miscellaneous work efforts such as drafting, word processing, clerical support, and reproductions.
SECTION 1. GENERAL
W.O. 8467-00 GEOLABS, INC. Page 3
Detailed descriptions of our field exploration methodology and the Logs of
Borings are presented in Appendix A. Results of the laboratory tests performed on selected soil samples are presented in Appendix B. Detailed calculations and analyses of the pavement design are presented in Appendix C. Photographs of the core samples retrieved during our field exploration are presented in Appendix D.
END OF GENERAL
W.O. 8467-00 GEOLABS, INC. Page 4
SECTION 2. SITE CHARACTERIZATION
2.1 Regional Geology
The Island of Hawaii is the largest in the Hawaiian Archipelago and covers an area of approximately 4,000 square miles. The island was formed by the activity of five shield volcanoes, which include the following: Kohala (long extinct); Mauna Kea
(activity during recent geologic time); Hualalai (erupted in 1801), and Mauna Loa and
Kilauea (both still active).
The project site is on the northeastern flank of the Mauna Loa Shield Volcano, which had been built up by the successive accumulation of basaltic lava flows and pyroclastic materials. The lava formation encountered at the site appears to consist of both a'a and pahoehoe type flows, which spread and ponded as they approached the ocean. A’a lava is typically characterized by a porous, rough, and irregular flow surface resembling a jagged accumulation of rock fragments, including cobbles and boulders.
Pahoehoe is characterized by a smooth, rope-like, or billowy surface and an internal structure of vesicular (porous) rock.
Cavities are commonly encountered in basaltic lavas, especially pahoehoe type lava. Cavities form when the lava is still in a molten state, and they represent both lava tubes (intra-flow cavities) and blisters and pockets (inter-flow cavities). Lava tubes form when molten lava drains from the cooling flow, leaving a hollow tube-like structure, which may extend for a large longitudinal distance along the flow. Blisters and pockets are generally smaller in horizontal extent.
2.2 Subsurface Conditions
The existing Bayfront Highway within the project limits is generally a three-lane divided roadway. The existing Kamehameha Avenue within the project limits is generally a four-lane divided roadway. The approximate project limits of the roadways are shown on the Site Plan, Plate 2.
Our field exploration program consisted of drilling and sampling ten borings, designated as Boring Nos. 1 through 10, at selected locations along the Bayfront
Highway and Kamehameha Avenue, extending to depths of about 15.5 to 41.5 feet
SECTION 2. SITE CHARACTERIZATION
W.O. 8467-00 GEOLABS, INC. Page 5 below the existing pavement surface. In addition, four bulk samples of the subgrade soils, designated as Bulk-1 through Bulk-4, were obtained to evaluate the pavement support characteristics of the near-surface soils. The approximate borings and bulk sample locations are shown on the Site Plan, Plate 2.
In general, our borings drilled along Bayfront Highway encountered a pavement section consisting of approximately 1 to 3 inches of asphaltic concrete (AC) and/or 5 to
7 inches of concrete over about 3 to 15 feet of fill materials consisting of very loose to very dense sands and gravels and very dense cobbly boulders. It should be noted that multiple voids ranging from about 6 to 12 inches were encountered within the cobbly boulder fill material. Below the existing pavement section and the fill layer, the borings generally encountered beach deposits consisting of medium dense sandy gravel and gravelly sand overlying medium hard to very hard basalt formation extending to the maximum depth explored of approximately 41.5 feet below the existing pavement surface.
The borings drilled along Kamehameha Avenue generally encountered a pavement section consisting of approximately 3 inches of AC and/or 5 to 7 inches of concrete overlying 3 to 4 feet of fill materials consisting of medium dense to very dense sands and medium stiff to stiff clays. Below the existing pavement section and fill layer, the borings generally encountered volcanic ash material consisting of soft to stiff clayey silts and beach deposits consisting of medium dense to very dense sands extending to the maximum depth explored of approximately 16.5 feet below the existing pavement surface.
Groundwater was encountered at depths varying from about 5.2 to 15 feet below the existing pavement surface at the time of exploration. It should be noted that the water level may vary due to tidal fluctuations and the nearby canal, as well as rainfall, seasonal precipitation, surface water runoff, and other factors at the project site.
Detailed descriptions of the materials encountered in the borings are presented on the Logs of Borings in Appendix A.
SECTION 2. SITE CHARACTERIZATION
W.O. 8467-00 GEOLABS, INC. Page 6
As mentioned previously, a geophysical surveying exploration was conducted using ground penetration radar (GPR) and electromagnetic (EM61) traversing along the
Bayfront Highway on the pavement surface and the gradient magnetometer method through the six boreholes. Intents of the geophysical surveying exploration are to estimate the limits and depths of the existing sheetpile installed along the makai side of the Bayfront Highway and detect the locations of the existing tieback anchors connected to the sheetpile. The geophysical surveying exploration was performed by Global
Geophysics.
Results of the geophysical survey exploration suggest that the existing sheetpile with tieback anchors may be located within about 400 feet of the highway section. The tieback anchors were detected at depths of approximately 3 to 7 feet below the ground surface with a horizontal spacing of about 10 feet. It also suggests that many tieback anchors may be severely corroded. Relatively weaker responses (suggesting moderately corroded condition) were detected from the steel sheetpile within about
100 feet of the sheetpile alignment with the bottom of the sheetpile at about 15 to 20 feet below the ground surface, while the remaining sheetpile alignment section may be extremely to severely corroded.
The results of the geophysical surveying exploration are contained in a separate report entitled “Report for Sheet Pile and Tie Back Location at Bayfront Highway, Hilo, Hawaii,” dated June 16, 2022.
END OF SITE CHARACTERIZATION
W.O. 8467-00 GEOLABS, INC. Page 7
SECTION 3. DISCUSSION AND RECOMMENDATIONS
Based on the current design concept and guidelines, we envision that new pavements will be constructed as part of the roundabout improvements, including
Bayfront Highway and Kamehameha Avenue within the specified limits as illustrated in
Site Plan, Plate 2.
Based on the traffic data provided, the R-value of the subgrade (converted from
California Bearing Ration [CBR] value), and the economic analyses, we recommend
4.0 inches of AC on 6.0 inches of Aggregate Base (AB) Course over 7.0 inches of
Aggregate Subbase (ASB) course for the Bayfront Highway, including the new roundabout. Due to the relatively lower R-value encountered at the subgrade level along
Kamehameha Avenue, we recommend 4.0 inches of AC on 8.0 inches of AB over 12.0 inches of ASB.
For the truck apron pavement planned, we recommend using 10 inches of
Portland Cement Concrete (PCC) over 6 inches of ASB. We recommend that the subgrade of the new pavements be scarified to a depth of 8 inches and recompacted to at least 95 percent relative compaction with moisture-conditioned above the optimum moisture content.
The following sections provide a discussion on the areas necessary for pavement analyses and design.
• Methodology of Pavement Design
• Design Traffic Loading Conditions/Traffic Index
• Design Subgrade Conditions
• Design Pavement Sections
• Subgrade Preparation Below Pavement Sections
• Compaction Requirements
• Pavement Drainage
3.1 Methodology of Pavement Design
The pavement structural section presented herein was generally determined based on the methodology described in Chapter 3 of the Pavement Design Manual dated March 2002. The Pavement Design Manual was prepared by the HDOT, W.O. 8467-00 GEOLABS, INC. Page 8
Highways Division, Materials Testing and Research Branch. The pavement design methodology is based on the Hveem Stabilometer method developed and used by the
California Department of Transportation (Caltrans). The design procedures for rigid pavements are based on the design procedures of the Portland Cement Association, “Thickness Design for Concrete Highway and Street Pavements.”
The design procedures for the rigid pavement section are generally based on the design procedures described in the Portland Cement Association “Thickness Design for
Concrete Highway and Street Pavements.”
3.2 Design Traffic Loading Conditions/Traffic Index
Design traffic loading conditions for the Average Daily Traffic (ADT) and 24-Hour
Truck Traffic (T24) along the Bayfront Highway were based on the information provided by the Highway Division Planning Branch of the HDOT, dated July 26, 2022. A copy of the design traffic parameters used in our analyses is presented in Plate C-1.1 of
Appendix C.
Design traffic data along Kamehameha Avenue was based on the information retrieved from the HDOT Highway Program Status website, dated August 19, 2022. A copy of the design traffic parameters used in our analyses is presented in Plate C-1.2 of
Appendix C.
Based on the traffic data provided for the Year 2022, the proposed roadway reconstruction project should be categorized as “High Volume Urban” with a design life of 20 years. Detailed design traffic parameters are summarized in the table below.
LOCATION
TRAFFIC VOLUME
(Average Daily Traffic)
Year 2022 Year 2042
Bayfront Highway – Route 19 18,600 23,200
Kamehameha Avenue 6,500 8,200
W.O. 8467-00 GEOLABS, INC. Page 9
Based on the typical traffic design distribution, the design daily traffic per direction is further calculated as follows.
LOCATION
TRAFFIC VOLUME
(ADT per Direction)
Design Distribution
Year 2022 Year 2042
Bayfront Highway – Route 19 55/45 10,230 12,760
Kamehameha Avenue 55/45 3,575 4,510
Based on the design period, traffic volume, and truck traffic distribution information provided, a Traffic Index (TI) has been determined for the proposed roadway reconstruction project. Results of the Traffic Index Determination are summarized in the following table. Detailed analyses on the Traffic Index Determination are presented on Plates C-2.1 and C-2.2.
TRAFFIC INDEX DETERMINATION
Location Traffic Index (TI)
Bayfront Highway – Route 19 11.5
Kamehameha Avenue 9.5
DESIGN TRAFFIC PARAMETERS
Location Bayfront Highway – Route 19 Kamehameha Avenue
24-Hour Truck Traffic
5.0% 6.9%
Type of Axle Truck Traffic Distribution
2-axle 48.7% 70.0%
3-axle 14.4% 15.0%
4-axle 6.7% 9.0%
5-axle 26.8% 5.0%
6-axle 1.8% 1.0%
7-axle 1.6% 0.0%
DESIGN TRAFFIC PARAMETERS
Location Bayfront Highway – Route 19 Kamehameha Avenue
24-Hour Truck Traffic
5.0% 6.9%
Type of Axle Truck Traffic Distribution
2-axle 48.7% 70.0%
3-axle 14.4% 15.0%
4-axle 6.7% 9.0%
5-axle 26.8% 5.0%
6-axle 1.8% 1.0%
7-axle 1.6% 0.0%
W.O. 8467-00 GEOLABS, INC. Page 10
3.3 Design Subgrade Conditions
We envision that the new roadway pavement will be constructed near the existing grades in a cut condition. Based on our field exploration, we anticipate that the majority of the pavement subgrade soils will generally consist of medium dense sandy/gravelly soils and medium stiff silty ash materials along Bayfront Highway and
Kamehameha Avenue, respectively.
We have performed our pavement designs assuming that the pavement subgrade soils will generally consist of the near-surface sandy/gravelly soils and silty ash materials encountered in the borings drilled with laboratory CBR values of 25 and
10 along Bayfront Highway and Kamehameha Avenue, respectively, as summarized in the table below. Therefore, the design Resistance (R) values of 55 and 25 are adopted accordingly, as also summarized in the table below.
LABORATORY CBR VALUES
Location CBR Values R-Values
Bayfront Highway – Route 19 25 55
Kamehameha Avenue 10 25
If site grading exposes soils other than those assumed, additional tests should be performed to confirm and/or revise the recommended pavement section for actual field conditions.
For the PCC pavement design along the truck apron planned, the pavement subgrade modulus of about 290 pounds per square inch per inch of deflection (pci) was adopted with adjusted 6 inches of ASB with a minimum flexural strength of 650 pounds per square inch (psi) at 28 days.
3.4 Design Pavement Sections
Based on the assumptions presented above, the flexible AC pavements and the rigid PCC pavement for the roundabout improvements may be designed using one of the following pavement structural sections. Detailed analyses and calculations of the two flexible AC pavement design options are presented on Plates C-3.1 and C-3.2
W.O. 8467-00 GEOLABS, INC. Page 11
(Option A) and Plates C-4.1 and C-4.2 (Option B) of Appendix C. Detailed analyses and calculations of the rigid PCC pavement are presented on Plates 5.1 and 5.2 of
Appendix C.
Option A: Flexible Asphaltic Concrete Pavement
Bayfront Highway – Route 19 (including roundabout)
4.0 Inches Asphaltic Concrete
6.0 Inches Aggregate Base Course (95 Percent Relative Compaction)
7.0 Inches Aggregate Subbase (95 Percent Relative Compaction)
17.0 Inches Total Pavement Thickness on Compacted Subgrade
Kamehameha Avenue
4.0 Inches Asphaltic Concrete
8.0 Inches Aggregate Base Course (95 Percent Relative Compaction)
12.0 Inches Aggregate Subbase (95 Percent Relative Compaction)
24.0 Inches Total Pavement Thickness on Compacted Subgrade
Option B: Flexible Asphaltic Concrete Pavement
Bayfront Highway – Route 19 (including roundabout)
4.0 Inches Asphaltic Concrete
4.0 Inches Asphalt Concrete Base (92 Percent Relative Specific Gravity)
6.0 Inches Aggregate Subbase (95 Percent Relative Compaction)
14.0 Inches Total Pavement Thickness on Compacted Subgrade
Kamehameha Avenue
4.0 Inches Asphaltic Concrete
5.0 Inches Asphalt Concrete Base (92 Percent Relative Specific Gravity)
10.0 Inches Aggregate Subbase (95 Percent Relative Compaction)
19.0 Inches Total Pavement Thickness on Compacted Subgrade
Rigid Portland Cement Concrete Pavement (Truck Apron)
10.0-Inch Portland Cement Concrete 6.0-Inch Aggregate Subbase Course (95 Percent Relative Compaction) 16.0-Inch Total Pavement Thickness on Moist Compacted Subgrade
As mentioned previously, cavities and/or voids were encountered in some of the borings drilled. The interpretations of the geophysical survey results suggested that pavement subgrade soils may have been migrated due to adjacent extremely to severely corroded steel sheetpile along the makai side of Bayfront Highway. To reduce
W.O. 8467-00 GEOLABS, INC. Page 12 the risk of the new pavement subbase course material from being compromised, we recommend placing a layer of the non-woven geotextile filter fabric, such as Mirafi 180N or equivalent, on top of the recompacted subgrade prior to placement of the aggregate subbase course.
An economic analysis was performed on the two flexible AC pavement design options for the Bayfront Highway and Kamehameha Avenue pavement design presented above to evaluate the initial construction cost and life cycle cost of the pavement structural sections. Based on our cost comparison of the AC pavement design options, it appears that a pavement structural section consisting of aggregate base course over aggregate subbase course (Option A) would result in the most economical pavement design. The economic analysis results are presented on Plates
C-6.1 through C-6.4 of Appendix C.
3.5 Subgrade Preparation Below Pavement Section
In general, the area within the contract grading limits should be thoroughly cleared and grubbed at the on-set of earthwork. Vegetation, debris, deleterious material, and other unsuitable materials should be removed and disposed of properly off-site or disposed of in a designated area to reduce the potential for contamination of the excavated materials. Soft and yielding areas encountered during clearing and grubbing below areas designated to receive fill or future improvements should be over-excavated to expose stiff and/or dense materials. The resulting excavation should be backfilled with aggregate subbase materials. The excavated soft and/or organic soils should be properly disposed of off-site.
After clearing and grubbing, the future pavement areas should be excavated, where necessary, to the pavement subgrade level, i.e., bottom of the aggregate subbase course layer. The pavement subgrade soils should be scarified to a depth of at least 8 inches, moisture-conditioned to above the optimum moisture content, and compacted to no less than 95 percent relative compaction. Relative compaction refers to the in-place dry density of soil expressed as a percentage of the maximum dry density of the same soil determined in accordance with AASHTO Test Method T180 or
W.O. 8467-00 GEOLABS, INC. Page 13
ASTM D1557. Optimum moisture is the water content (percentage by dry weight) corresponding to the maximum dry density.
As mentioned previously, cavities and/or voids were encountered near the ground surface during our field exploration. We recommend that the exposed pavement subgrade materials should be proof-rolled with a large vibratory drum roller (minimum
10 tons static weight) with a minimum of eight passes to help detect and collapse near-surface cavities and/or voids. The vibratory drum roller should be operated at a speed of about 300 feet per minute.
If the subgrade soils are pumping during subgrade preparation, the pumping subgrade may be stabilized by cement treatment to reduce the potential for pumping subgrade conditions. As a guide, stabilization by cement treatment may consist of one sack of cement for approximately 25 square feet of subgrade area. Geolabs should be contacted to evaluate the pumping subgrade conditions and whether the pavement sections need to be revised and/or modified based on the exposed subgrade conditions.
Where shrinkage cracks are noted after compaction of the subgrade, we recommend that the soils be scarified and re-prepared as recommended above.
Saturation and subsequent yielding of the exposed subgrade due to inclement weather and poor drainage may require over-excavation of the soft areas and replacement with well-compacted fill. Contract documents should include additive and deductive unit prices for over-excavation and compacted fill placement to account for variations in the over-excavation quantities.
A Geolabs representative should monitor the pavement subgrade preparation to observe whether undesirable materials are encountered during the excavation and scarification process and to confirm whether the exposed soil/rock conditions are similar to those encountered in our field exploration.
3.6 Compaction Requirements
In general, fill and backfill materials should be moisture-conditioned to above the optimum moisture content, placed in level lifts not exceeding 8 inches in loose thickness, and compacted to a minimum of 95 percent relative compaction. Aggregate
W.O. 8467-00 GEOLABS, INC. Page 14 subbase materials required for the new pavements should conform to the requirements stipulated in Subsection 703.16 of the State of Hawaii, Standard Specifications for Road and Bridge Construction (2005) (HSS). The aggregate subbase should be moisture-conditioned to above the optimum moisture content, placed in 8-inch level loose lifts, and compacted to not less than 95 percent of the maximum density according to Section 106.09, Special Test Methods of the HSS.
Aggregate base course materials required for the project should consist of crushed basaltic aggregates with a 1.5-inch maximum nominal size and should conform to Subsection 703.06 of the State of Hawaii, Standard Specifications for Road and
Bridge Construction (2005). Aggregate base material should be moisture-conditioned to above the optimum moisture content and compacted to a minimum of 95 percent relative compaction. Relative compaction refers to the in-place dry density of soil expressed as a percentage of the maximum dry density of the same soil established in accordance with AASHTO T-180 or ASTM D1557. Optimum moisture is the water content (percentage by dry weight) corresponding to the maximum dry density.
Asphalt concrete base (ACB) material should consist of asphalt-treated basalt aggregate and compacted to no less than 92 percent of the maximum theoretical specific gravity determined in accordance with AASHTO T-209 or ASTM D2041.
Asphaltic concrete (AC) material should be constructed in accordance with
Section 401 Asphalt Concrete Pavement of the State of Hawaii, Standard Specifications for Road and Bridge Construction (2005) and subsequent amendments.
3.7 Pavement Drainage
One of the primary distress mechanisms in pavement structures is pumping due to saturation of the base, subbase, and/or subgrade soils. It should be noted that the clayey subgrade soils are susceptible to softening and loss of strength upon saturation.
Therefore, special attention should be given to the surface drainage of the pavements.
As a minimum, the pavement surface should be sloped, and drainage gradients should be maintained to carry surface water off the pavement to appropriate drainage structures. Surface water ponding should not be allowed on the site during or after construction.
W.O. 8467-00 GEOLABS, INC. Page 15
The development of good shoulder drainage along with a program to prevent obstructions in the drainage structures is strongly recommended to reduce the potential for pavement deterioration or premature failure of the pavements.
3.8 Design Review
Preliminary and final drawings and specifications for the proposed project should be forwarded to Geolabs for review and written comments prior to advertisement for bids. This review is necessary to evaluate the general conformance of the plans and specifications with the intent of the pavement design recommendations provided herein.
If this review is not made, Geolabs cannot be responsible for misinterpretation of the recommendations presented.
3.9 Construction Monitoring
Geolabs should be retained to provide geotechnical engineering services during the construction of pavements for the project. The critical items of construction monitoring include observation of the subgrade preparation and observation of the placement and compaction testing of the fill and base materials. A Geolabs representative should also monitor other aspects of earthwork construction to observe compliance with the intent of the design concepts, specifications, or recommendations and to expedite suggestions for design changes that may be required in the event that subsurface conditions differ from those anticipated at the time this report was prepared.
The recommendations provided herein are contingent upon such observations.
If the actual soil conditions encountered during construction are different from those assumed or considered in this report, then appropriate design modifications should be made.
END OF DISCUSSION AND RECOMMENDATIONS
W.O. 8467-00 GEOLABS, INC. Page 16
SECTION 4. LIMITATIONS
The analyses and recommendations submitted herein are based, in part, upon information obtained from the borings, bulk samples, and laboratory test data.
Variations of conditions between and beyond the field data points may occur, and the nature and extent of these variations may not become evident until construction is underway. If variations then appear evident, it will be necessary to re-evaluate the recommendations presented herein.
The boring and bulk sample locations are approximate, having been estimated by using a hand-held Global Positioning System (GPS) device shown on the Google
Earth Pro software. Elevations of the field borings were estimated by interpolation from the spot elevations shown on Google Earth Pro. The physical locations and elevations of the borings should be considered accurate only to the degree implied by the methods used.
The stratification breaks shown on the graphic representations of the borings depict the approximate boundaries between soil/rock types and, as such, may denote a gradual transition. Water level data from the borings were measured at the times shown on the graphic representations and/or presented in the text of this report. These data have been reviewed and interpretations made to formulate this report. However, it must be noted that fluctuation may occur due to variations in rainfall, temperature, and other factors.
This report has been prepared for the exclusive use of AECOM for the specific application to the Intersection Improvements at Bayfront Highway project in accordance with generally accepted geotechnical engineering principles and practices. No warranty is expressed or implied.
This report has been prepared solely for the purpose of assisting the design engineer in the preparation of design drawings related to the pavements for the proposed project only. Therefore, this report may not contain sufficient data or the proper information for use to form the basis for the preparation of construction cost estimates or for contract bidding. A contractor wishing to bid on this project should
SECTION 4. LIMITATIONS
W.O. 8467-00 GEOLABS, INC. Page 17 retain a competent geotechnical engineer to assist in the interpretation of this report and/or in the performance of site-specific exploration for bid estimating purposes.
The owner/client should be aware that unanticipated subsurface conditions are commonly encountered in the field during construction. Unforeseen subsurface conditions, such as perched groundwater, soft deposits, hard layers, or cavities, may occur in localized areas and may require additional probing or corrections in the field
(which may result in construction delays) to attain a properly constructed project.
Therefore, a sufficient contingency fund is recommended to accommodate these possible extra costs.
This geotechnical engineering exploration conducted at the project site was not intended to investigate the potential presence of hazardous materials existing at the project site. It should be noted that the equipment, techniques, and personnel used to conduct a geo-environmental exploration differ substantially from those applied in geotechnical engineering.
END OF LIMITATIONS
W.O. 8467-00 GEOLABS, INC. Page 18
CLOSURE
The following plates and appendices are attached and complete this report:
Project Location Map .............................................................................................. Plate 1
Site Plan ................................................................................................................. Plate 2
Field Exploration ............................................................................................. Appendix A
Laboratory Tests ............................................................................................. Appendix B
Pavement Design ............................................................................................ Appendix C
Photographs of Core Samples ........................................................................ Appendix D
Respectfully submitted, By John Y.L. Chen, P.E.
Vice President
JC:TO:lf h:\8400 Series\8467-00.to1
PLATES
GRAPHIC SCALE
10002000 20000 FT.
PROJECT LOCATION
GENERAL PROJECT LOCATION
PROJECT LOCATION MAP
JULY 2022
1" = 2,000'
Geotechnical Engineering
GEOLABS, INC.
HILO, ISLAND OF HAWAII
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
N
DATE
SCALE
8467-00
DRAWN BY
HYC
W.O.
PLATE
N
HONAUNAU
KAILUA-KONA
KALAOA
KONA
HOLUALOA
CAPTAIN
COOK
KA'U
MAUNA LOA
PAHALA
VOLCANO
PUNA
MOUNTAIN
VIEW
HILO
HILO
MAUNA KEA
KAWAIHAE
KOHALA
HAWI
HONOKAA
WAIMEA
HONOMU
PAPAIKOU
NAALEHU
ISLAND MAP
NO SCALE
PACIFIC OCEAN
C A
D
U s e r
H
E N
R Y
F i l e
L a s t
U p d a t e d
J u l y p m
P o t
D a t
J u l y p m
F i l e
A
D r a f t i n g D r a f t i n g W o r k i n g
I n t e r s e c t i o n
I m p r o v e m e n t s a t
B a y f r o n t
H i g h w a y
H i l o
P
L M d w g
P l o t t e r
D
W G
T o
P
D F
G
E O p c o t s t y l e
G
E O
N o D i t h e r i n g B l u e B o r i n g c t b
REFERENCE: MAP CREATED WITH TOPO!® ©2010 NATIONAL
GEOGRAPHIC; ©2007 TELE ATLAS, REL. 1/2007.
APPROXIMATE BORING LOCATION
LEGEND:
N
APPROXIMATE BULK SAMPLE LOCATION
INTERSECTION IMPROVEMENTS AT BAYFRONT HIGHWAY
HILO, ISLAND OF HAWAII
GEOLABS, INC.
Geotechnical Engineering
8467-00
DRAWN BY
HYC
1" = 150'
JULY 2022
SCALE
DATE
W.O.
SITE PLAN
PLATE
GRAPHIC SCALE
0 750 150 300 450 FT.
C A
D
U s e r
H
E N
F i
L s t
U p d a t e d
J u l y m o t
D a t u l y p m
F i l e
A
D r a f t i n g D r a f t i n g W o r k i n g
I n t e r s e c t i o n
I m p r o v e m e n t s a t
B a y f r o n t
H i g h w a y
H i l o
S i t e
P l a n d w g
P l o t t e r
D
W o
P
D F
G
E O p c o t s t y l e
G
E O
N o D i t h e r i n g B l u e B o r i n g c t b
REFERENCE: ©2022 GOOGLE EARTH PRO. IMAGERY DATED JULY 12, 2019.
B-1
B-7
B-2
B-3 / BULK-2
B-8 / BULK-1
B-9 / BULK-4
B-4
B-5 / BULK-3
B-6
B-10
APPENDIX A
W.O. 8467-00 GEOLABS, INC. SEPTEMBER 2022 Page A-1
A P P E N D I X A
Field Exploration
We explored the subsurface conditions along the roadway by drilling and sampling ten borings, designated as Boring Nos. 1 through 10, extending to maximum depths of about 15.5 to 41.5 feet below the existing pavement surface. The approximate boring locations are shown on the Site Plan, Plate 2. The borings were drilled using a truck-mounted drill rig equipped with continuous flight augers and coring tools.
Our geologists classified the materials encountered in the borings by visual and textural examination in the field in general accordance with ASTM D2488, Standard Practice for Description and Identification of Soils, and monitored the drilling operations on a near-continuous (full-time) basis. These classifications were further reviewed visually and by testing in the laboratory. Soils were classified in general accordance with ASTM D2487, Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System), as shown on the Soil Log Legend, Plate A-0.1.
Deviations made to the soil classification in accordance with ASTM D2487 are described on the Soil Classification Log Key, Plate A-0.2. Graphic representations of the materials encountered are presented on the Logs of Borings, Plates A-1 through A-10.
Relatively “undisturbed” soil samples were obtained in general accordance with ASTM D3550, Ring-Lined Barrel Sampling of Soils, by driving a 3-inch OD Modified California sampler with a 140-pound hammer falling 30 inches. In addition, some samples were obtained from the drilled borings in general accordance with ASTM D1586, Penetration Test and Split-Barrel Sampling of Soils, by driving a 2-inch OD standard penetration sampler using the same hammer and drop. The blow counts needed to drive the sampler the second and third 6 inches of an 18-inch drive are shown as the “Penetration Resistance” on the Logs of Borings at the appropriate sample depths. The penetration resistance shown on the Logs of Borings indicates the number of blows required for the specific sampler type used. The blow counts may need to be factored to obtain the Standard Penetration Test (SPT) blow counts.
Core samples of the rock materials encountered at the project site were obtained by using diamond core drilling techniques in general accordance with ASTM D2113, Diamond Core Drilling for Site Investigation. Core drilling is a rotary drilling method that uses a hollow bit to cut into the rock formation. The rock material left in the hollow core of the bit is mechanically recovered for examination and description. Rock cores were described in general accordance with the Rock Description System, as shown on the Rock Log Legend, Plate A-0.3. The Rock Description System is based on the publication “Suggested Methods for the Quantitative Description of Discontinuities in Rock Masses” by the International Society for Rock Mechanics (March 1977).
Recovery (REC) may be used as a subjective guide to the interpretation of the relative quality of rock masses, where appropriate. Recovery is defined as the actual length of material recovered from a coring attempt versus the length of the core attempt.
Appendix A (continued)
W.O. 8467-00 GEOLABS, INC. SEPTEMBER 2022 Page A-2
For example, if 3.7 feet of material is recovered from a 5.0-foot core run, the recovery would be 74 percent and would be shown on the Logs of Borings as REC = 74%.
The Rock Quality Designation (RQD) is also a subjective guide to the relative quality of rock masses. RQD is defined as the percentage of the core run in rock that is sound material in excess of 4 inches in length without any discontinuities, discounting any drilling, mechanical, and handling induced fractures or breaks. If 2.5 feet of sound material is recovered from a 5.0-foot core run in rock, the RQD would be 50 percent and would be shown on the Logs of Borings as RQD = 50%. Generally, the following is used to describe the relative quality of the rock based on the "Practical Handbook of Physical Properties of Rocks and Minerals” by Robert S. Carmichael (1989).
Rock Quality
RQD
Very Poor 0 – 25
Poor 25 – 50
Fair 50 – 75
Good 75 – 90
Excellent 90 – 100
The excavation characteristic of a rock mass is a function of the relative hardness of the rock, its relative quality, brittleness, and fissile characteristics. A dense rock formation with a high RQD value would be very difficult to excavate and probably would require more arduous methods of excavation.
A-0.1
UNCONSOLIDATED UNDRAINED TRIAXIAL
COMPRESSION (ksf)
MORE THAN 50%
OF COARSE
FRACTION
RETAINED ON
NO. 4 SIEVE
50% OR MORE OF
COARSE FRACTION
PASSING
THROUGH NO. 4
SIEVE
MORE THAN 50%
OF MATERIAL
RETAINED ON NO.
200 SIEVE
50% OR MORE OF
MATERIAL PASSING
THROUGH NO. 200
SIEVE
TORVANE SHEAR (tsf)
(2-INCH) O.D. STANDARD PENETRATION TEST
(3-INCH) O.D. MODIFIED CALIFORNIA SAMPLE
INORGANIC SILTS AND VERY FINE SANDS,
ROCK FLOUR, SILTY OR CLAYEY FINE SANDS
OR CLAYEY SILTS WITH SLIGHT PLASTICITY
POORLY-GRADED GRAVELS, GRAVEL-SAND
MIXTURES, LITTLE OR NO FINES
CLAYEY GRAVELS, GRAVEL-SAND-CLAY
MIXTURES
WELL-GRADED SANDS, GRAVELLY SANDS,
LITTLE OR NO FINES
POORLY-GRADED SANDS, GRAVELLY
SANDS, LITTLE OR NO FINES
SILTY SANDS, SAND-SILT MIXTURES
CLAYEY SANDS, SAND-CLAY MIXTURES
LIQUID LIMIT
50 OR MORE CH
NOTE: DUAL SYMBOLS ARE USED TO INDICATE BORDERLINE SOIL CLASSIFICATIONS
MH
SILTS
AND
CLAYS
SILTS
AND
CLAYS
LIQUID LIMIT
LESS THAN 50
USCS
TYPICAL
DESCRIPTIONS
GW
MORE THAN 12%
FINES
WATER LEVEL OBSERVED IN BORING OVERNIGHT
HIGHLY ORGANIC SOILS
SILTY GRAVELS, GRAVEL-SAND-SILT
MIXTURES
OL
PEAT, HUMUS, SWAMP SOILS WITH HIGH
ORGANIC CONTENTS
INORGANIC CLAYS OF LOW TO MEDIUM
PLASTICITY, GRAVELLY CLAYS, SANDY
CLAYS, SILTY CLAYS, LEAN CLAYS
Soil Log Legend
ORGANIC CLAYS OF MEDIUM TO HIGH
PLASTICITY, ORGANIC SILTS
SC
Plate
GM
FINE-
GRAINED
SOILS
COARSE-
GRAINED
SOILS
CLEAN SANDS
SANDS WITH
FINES
SP
SANDS
GRAVELS
WELL-GRADED GRAVELS, GRAVEL-SAND
MIXTURES, LITTLE OR NO FINES
ML
CL
OH
LESS THAN 5%
FINES
GRAVELS WITH
FINES
CLEAN
GRAVELS
GRAB SAMPLE
PLASTICITY INDEX (NP=NON-PLASTIC)
TV
LEGEND
WATER LEVEL OBSERVED IN BORING AT TIME OF
DRILLING
WATER LEVEL OBSERVED IN BORING AFTER DRILLING
SM
MAJOR DIVISIONS
GP
MORE THAN 12%
FINES
PT
LESS THAN 5%
FINES
UNIFIED SOIL CLASSIFICATION SYSTEM (USCS)
ORGANIC SILTS AND ORGANIC SILTY
CLAYS OF LOW PLASTICITY
SW
GC
INORGANIC SILT, MICACEOUS OR
DIATOMACEOUS FINE SAND OR SILTY
SOILS
INORGANIC CLAYS OF HIGH PLASTICITY
PI
LL
TXUU
UNCONFINED COMPRESSION
OR UNIAXIAL COMPRESSIVE STRENGTH
CORE SAMPLE
SHELBY TUBE SAMPLE
LIQUID LIMIT (NP=NON-PLASTIC)
UC
GEOLABS, INC.
Geotechnical Engineering
L O
G L
E G
E N
D F
O R
S O
IL
-0
.G
E
O L
A B
S .G
D
/2
A-0.2
7 - 18
18 - 55
55 - 91
> 91
Medium Dense
Coarse Sand
(with deviations from ASTM D2488)
Soil Classification Log Key
*Soil descriptions are based on ASTM D2488-09a, Visual-Manual Procedure, with the above modifications by Geolabs, Inc. to the Unified Soil Classification System (USCS).
accessory descriptions compose of the following:
with some: >12% with a little: 5 - 12% with traces of: <5% accessory descriptions are lower cased and follow the Primary and Secondary Constituents (i.e., SILTY GRAVEL with a little sand)
Dry: Absence of moisture, dry to the touch
Moist: Damp but no visible water
Wet: Visible free water
Medium Sand
Fine Sand
#4 to #200 (4.75-mm to 0.075-mm)
#4 to #10 (4.75-mm to 2-mm)
> 12 inches (305-mm)
3-inch to #4 (75-mm to 4.75-mm)
Sieve Number and / or Size
Gravel
#10 to #40 (2-mm to 0.425-mm)
#40 to #200 (0.425-mm to 0.075-mm)
3 to 12 inches (75-mm to 305-mm)
Description
PP Readings (tsf)
2.0 - 4.0
> 4.0
N-Value (Blows/Foot)
MCS
0 - 4
RELATIVE DENSITY / CONSISTENCY
GRAIN SIZE DEFINITION
ABBREVIATIONS
N-Value (Blows/Foot)
0 - 7
WOH: Weight of Hammer
WOR: Weight of Drill Rods
SPT: Standard Penetration Test Split-Spoon Sampler
MCS: Modified California Sampler
PP: Pocket Penetrometer
4 - 7
7 - 15
15 - 27
27 - 55
SPT
0 - 2
> 55> 30
4 - 8
15 - 30
MOISTURE CONTENT DEFINITIONS
SPT
0 - 4
4 - 10
10 - 30
30 - 50
> 50
MCS
Loose
EXAMPLE: Soil Containing 60% Gravel, 25% Sand, 15% Fines. Described as: SILTY GRAVEL with some sand
Plate
GRANULAR SOIL (- #200 <50%)
2 - 4
8 - 15
Relative Density
Very Loose
Dense
Very Dense
COHESIVE SOIL (- #200 50%)
PRIMARY constituents are composed of the largest percent of the soil mass. Primary constituents are capitalized and bold (i.e., GRAVEL, SAND)
PRIMARY constituents are based on plasticity. Primary constituents are capitalized and bold (i.e., CLAY, SILT)
SECONDARY constituents are composed of a percentage less than the primary constituent. If the soil mass consists of 12 percent or more fines content, a cohesive constituent is used (SILTY or CLAYEY);
otherwise, a granular constituent is used (GRAVELLY or SANDY) provided that the secondary constituent consists of 20 percent or more of the soil mass.
Secondary constituents are capitalized and bold (i.e., SANDY GRAVEL, CLAYEY SAND) and precede the primary constituent.
SECONDARY constituents are composed of a percentage less than the primary constituent, but more than 20 percent of the soil mass. Secondary constituents are capitalized and bold (i.e., SANDY CLAY, SILTY CLAY, CLAYEY SILT) and precede the primary constituent.
Sand
Boulders
Cobbles
Coarse Gravel 3-inch to 3/4-inch (75-mm to 19-mm)
Fine Gravel 3/4-inch to #4 (19-mm to 4.75-mm)
GEOLABS, INC. CLASSIFICATION*
Granular Soils Cohesive Soils
Consistency accessory descriptions compose of the following:
with some: >12% with a little: 5 - 12% with traces of: <5% accessory descriptions are lower cased and follow the Primary and Secondary Constituents (i.e., SILTY CLAY with some sand)
Very Soft
Soft
Medium Stiff
Stiff
Very Stiff
Hard
< 0.5
0.5 - 1.0
1.0 - 2.0
S O
IL
C L
A S
S
L O
G
K
-0
.G
O L
A B
S .G
/2
Geotechnical Engineering
A-0.3
ROCK DESCRIPTIONS
Plate
BRECCIA
CLINKER
COBBLES
CORAL
BASALT
ROCK DESCRIPTION SYSTEM
Greater than 24 inches apart
12 to 24 inches apart
6 to 12 inches apart
3 to 6 inches apart
Less than 3 inches apart
Rock shows no sign of discoloration or loss of strength.
Slight discoloration inwards from open fractures.
Discoloration throughout and noticeably weakened though not able to break by hand.
Most minerals decomposed with some corestones present in residual soil mass. Can be broken by hand.
Saprolite. Mineral residue completely decomposed to soil but fabric and structure preserved.
The following terms describe general fracture spacing of a rock:
The following terms describe the chemical weathering of a rock:
ROCK FRACTURE CHARACTERISTICS
DEGREE OF WEATHERING
HARDNESS
BOULDERS
VOID/CAVITY
TUFF
SILTSTONE
LIMESTONE
Unweathered:
Slightly Weathered:
Moderately Weathered:
Highly Weathered:
Extremely Weathered:
Very Hard:
Hard:
Medium Hard:
Soft:
Very Soft:
SANDSTONE
Massive:
Slightly Fractured:
Moderately Fractured:
Closely Fractured:
Severely Fractured:
Rock Log Legend
The following terms describe the resistance of a rock to indentation or scratching:
Specimen breaks with difficulty after several "pinging" hammer blows.
Example: Dense, fine grain volcanic rock
Specimen breaks with some difficulty after several hammer blows.
Example: Vesicular, vugular, coarse-grained rock
Specimen can be broked by one hammer blow. Cannot be scraped by knife. SPT may penetrate by ~25 blows per inch with bounce.
Example: Porous rock such as clinker, cinder, and coral reef
Can be indented by one hammer blow.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .