Addendum No. 2-FINAL ADDENDUM NO 2 NH 019 2 076.pdf

PDF 11 MB Posted

Attached to
NH-019-2(076) HILO BAYFRONT HWY INTERSECTION IMPROVEMENTS
Solicitation number
B27000553
Issued by
Hawaii County, Hawaii

About this file

Addendum No. 2 Summary

This is an addendum to the Hilo Bayfront Highway Intersection Improvements solicitation (Federal-Aid Project No. NH-019-2(076)) issued by the Hawaii Department of Transportation on November 13, 2026. The addendum modifies the original solicitation by updating the table of contents; deleting and replacing special provisions sections including Section 411 (Portland Cement Concrete Pavement), Section 607 (Chain Link Fences and Gates), Section 629 (Pavement Markings), and Section 645 (Work Zone Traffic Control); updating federal wage rates effective October 15, 2026; revising the proposal schedule dated August 7, 2026 to pages P-8 through P-18; and providing responses to requests for information submitted by bidders. The project scope encompasses converting an existing intersection into a single-lane roundabout with central island, truck apron, circular travel path, and splitter islands, along with roadway stabilization, pavement reconstruction, landscaping improvements, electrical conduits and highway lighting, drainage improvements, ADA-compliant sidewalks and curb ramps, chain link fencing, signage and pavement marking, work zone traffic control, and utility adjustments and relocations. The proposal schedule identifies approximately 99 line items including excavation (5,570 cubic yards of roadway excavation), pavement work, concrete structures, drilled shafts (180 linear feet), drainage facilities, lighting systems, plantings, and numerous incidental construction items. Bidders were required to acknowledge receipt of this addendum by recording the date on page P-4 of the proposal prior to submission.

The addendum includes detailed responses to 21 bidder questions addressing technical clarifications on materials specifications, geotechnical requirements, utility responsibilities, construction sequencing, earthwork quantities, environmental permits, work hour restrictions, and equipment substitutions. Key clarifications indicate that the five construction phases shown in the plans are not mandatory; surplus excavated material must be disposed of offsite at the contractor's expense; Hawaiian Telcom will handle cable installation and connections while the contractor installs conduits and handholes; precast concrete light pole foundations and polymer pull boxes are not acceptable substitutes for the specified designs; and existing utilities must be verified by the contractor in the field. The addendum provides supplemental documents including environmental mitigation measures, pavement justification reports, geotechnical recommendations for retaining structures and drilled shaft foundations, noise permits and approvals, and stormwater pollution prevention plans. No contract value, contract term, incumbency status, set-asides, evaluation criteria, or award date is provided in the addendum documentation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS ADDENDUM NO. 2

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE NOVEMBER 13, 2026

DISTRICT OF HILO, ISLAND OF HAWAII PAGE 1 OF 2

FEDERAL-AID PROJECT NO. NH-019-2(076)

STATE OF HAWAII

DEPARTMENT OF TRANSPORTATION

HIGHWAYS

ADDENDUM NO. 2

FOR

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE

VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

NOVEMBER 13, 2026

This Addendum shall make the following amendment(s) to the Solicitation:

A. TABLE OF CONTENTS

1. Delete TABLE OF CONTENTS, dated r5/14/26, in its entirety and replace it with attached TABLE OF CONTENTS, dated r11/13/2026.

B. SPECIAL PROVISIONS

1. Delete SECTION 411 PORTLAND CEMENT CONCRETE PAVEMENT, dated 8/20/20, in its entirety.

2. Delete SECTION 607 CHAIN LINK FENCES AND GATES, dated 7/1/18, in its entirety and replace it with attached SECTION 607 CHAIN LINK FENCES AND GATES, dated r11/13/2026.

3. Delete SECTION 629 PAVEMENT MARKINGS, dated 6/6/22, in its entirety and replace it with attached SECTION 629 PAVEMENT MARKINGS, dated r11/13/2026.

4. Delete SECTION 645 WORK ZONE TRAFFIC CONTROL, dated 12/24/25, in its entirety and replace it with attached SECTION 645 WORK ZONE TRAFFIC CONTROL, dated r11/13/2026.

C. FEDERAL WAGE RATES

1. Delete FEDERAL WAGE RATES, dated 5/27/2026, in its entirety and replace it with the attached FEDERAL WAGE RATES, dated 10/15/2026.

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS ADDENDUM NO. 2

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE NOVEMBER 13, 2026

DISTRICT OF HILO, ISLAND OF HAWAII PAGE 2 OF 2

FEDERAL-AID PROJECT NO. NH-019-2(076)

D. PROPOSAL SCHEDULE

1. Delete PROPOSAL SCHEDULE, pages P-8 to P-18, dated 8/7/2026, and replace it with attached PROPOSAL SCHEDULE, pages P-8 to P-18, dated r11/13/2026.

The following is provided for information.

E. RESPONSES TO REQUEST FOR INFORMATION

1. The attached RESPONSE TO REQUEST FOR INFORMATION is provided for information.

F. SUPPLEMENTAL DOCUMENTS

1. The following SUPPLEMENTAL DOCUMENTS are attached for information.

a. Environmental Mitigation Measures Commitment Checklist

b. Pavement Justification Report Intersection Improvements at Bayfront Highway, dated September 16, 2022.

c. Recommendations for Retaining Structures for Intersection Improvements at

Bayfront Highway, dated June 5, 2026.

d. Drilled Shaft Foundation Recommendations for Intersection Improvements at

Bayfront Highway, dated June 16, 2026.

e. Noise Permit

f. National Pollutant Discharge Elimination System Notice of General Permit

Coverage

g. Storm Water Pollution Prevention Plan

h. Notice of Intent – Form C Submittal and Submittal Attachments

i. Noise Variance Approval Letter and Decision and Order

Please acknowledge receipt of this ADDENDUM NO. 2 by recording the date of its receipt in the space provided on PAGE P-4 of the Proposal.

HENRY KENNEDY

Engineering Program Manager

NH-019-2(076) ADDENDUM NO. 2

-1- r11/13/2026

TABLE OF CONTENTS

Instructions for Contractor’s Licensing

Civil Rights Compliance And Disadvantaged Business Enterprise Special Provisions

Required Federal-Aid Contract Provisions

Special Provisions Title Page

Special Provisions:

DIVISION 100 - GENERAL PROVISIONS

Section Description Pages

101 Terms, Abbreviations, and Definitions 101-1a – 101-13a

102 Bidding Requirements and Conditions 102-1a – 102-8a

103 Award And Execution of Contract 103-1a – 103-4a

104 Scope of Work 104-1a – 104-2a

105 Control of Work 105-1a – 105-3a

106 Material Restrictions and Requirements 106-1a – 106-4a

107 Legal Relations and Responsibility To Public 107-1a – 107-3a

108 Prosecution And Progress 108-1a – 108-25a

109 Measurement and Payment 109-1a – 109-2a

DIVISION 200 - EARTHWORK

Section Description Pages

201 Clearing and Grubbing 201-1a

202 Removal of Structures and Obstructions 202-1a – 202-2a

203 Excavation and Embankment 203-1a – 203-3a

Excavation and Backfill for Miscellaneous Facilities

204-1a

206 Excavation and Backfill for Drainage Facilities 206-1a

Temporary Water Pollution, Dust, and Erosion Control

209-1a – 209-28a

212 Archeological Monitoring 212-1a – 212-3a

-2- r11/13/2026

DIVISION 300 - BASES

Section Description Pages

301 Hot Mix Asphalt Base Course 301-1a – 301-2a

305 Aggregate Subbase Course 305-1a

Controlled Low Strength Material for Utilities and Structures

314-1a

DIVISION 400 - PAVEMENTS

401 Hot Mix Asphalt Pavement 401-1a – 401-36a

413 Stamped Textured Cement Concrete 413-1a – 413-4a

DIVISION 500 - STRUCTURES

503 Concrete Structures 503-1a

511 Drilled Shafts 511-01a – 511-13a

DIVISION 600 - INCIDENTAL CONSTRUCTION

601 Structural Concrete 601-1a – 601-15a

602 Reinforcing Steel 602-1a – 602-2a

603 Culverts and Storm Drains 603-1a

606 Guardrail 606-1a – 606-6a

607 Chain Link Fences and Gates 607-1a

610 Reinforced Concrete Driveways 610-1a

617 Planting Soil 617-1a – 617-5a

619 Planting 619-1a – 619-15a

621 Invasive Species Management 621-1a – 621-13a

622 Roadway and Sign Lighting System 622-1a – 622-12a

Manholes and Valve Boxes for Water and Sewer Systems

626-1a

627 Traffic Monitoring and Signal Control System 627-1a – 627-2a

-3- r11/13/2026

629 Pavement Markings 629-1a – 629-4a

630 Traffic Control Guide Sign 630-1a – 630-2a

Traffic Control Regulatory, Warning, and Miscellaneous Signs

631-1a – 631-2a

634 Portland Cement Concrete Sidewalks 634-1a

636 E-Construction 636-1a – 636-5a

638 Portland Cement Concrete Curb and Gutter 638-1a – 638-2a

641 Hydro-Mulch Seeding 641-1a – 641-8a

645 Traffic Control Work Zone 645-1a – 645-18a

647 Fiber Optic Cable 647-1a – 647-3a

650 Curb Ramps 650-1a

671 Protection of Endangered Species 671-1a – 671-10a

697 Project Web Page 697-1a – 697-2a

699 Mobilization 699-1a

DIVISION 700 - MATERIALS

702 Bituminous Materials 702-1a

703 Aggregates 703-1a

706 Concrete, Clay and Plastic Pipe 706-1a

Miscellaneous Frames, Grates, Covers and Ladder Rungs

712-1a

717 Cullet and Cullet-Made Materials 717-1a – 717-2a

Macro-Synthetic Fibers for Concrete Reinforcement

719-1a

750 Traffic Control Sign and Marker Materials 750-1a – 750-2a 755 Pavement Marking Materials 755-1a 760 Roadway and Sign Lighting Systems Materials 760-1a – 760-2a

Requirement of Chapter 104, HRS Wages and Hours of Employees on Public Works Law

Federal Wage Rates

Proposal Title Page

-4- r11/13/2026

Proposal .................................................................................................. P-1 – P-7 Proposal Schedule ................................................................................ P-8 – P-18

Surety Bid Bond

Sample Forms

Contract

Performance Bond (Surety)

Performance Bond

Labor and Material Payment Bond (Surety)

Labor and Material Payment Bond

Disclosure of Lobbying Activities Standard Form - LLL and LLL-A

Statement of Compliance Form WH-348

Chapter 104, HRS Compliance Certificate

END OF TABLE OF CONTENTS

607-1a r11/13/2026

SECTION 607 – CHAIN LINK FENCES AND GATES 1

Make the following amendment to said Section: 3

(I) Amend 607.04 - Measurement by replacing lines 105 to 106 to read: 5 “607.04 Measurement. The Engineer will measure 4-feet, Chain Link Fence by 7 the linear foot. Measurement will be along the top of the fence from outside to 8 outside of end post for each continuous run of fence. The Engineer will measure 9 Cattle Gate by each.” 10 (II) Amend 607.05 – Payment by revising lines 108 to 115 to read as follows: 13 “607.05 Payment. The Engineer will pay for the accepted quantities of 15 fence at the contract unit price per linear foot of the types and sizes specified in 16 the proposal, complete in place. 17 The Engineer will pay for following pay items when included in proposal 19 schedule: 20 Pay Item Pay Unit 22 4-feet, Chain Link Fence Linear Foot 24 Cattle Gate Each” 26

END OF SECTION 607 31

629-1a r11/13/2026

SECTION 629 - PAVEMENT MARKINGS 1

Make the following amendments to said Section: 3

(I) Amend Subsection 629.03(B) – Temporary Pavement Markings by 5 revising the third paragraph from line 62 to 63 to read: 6

“Maintain and replace temporary pavement markings, flexible 8 delineators, and barricades. ” 9

(II) Amend Table 629.03 – 1 – Temporary Pavement Markings to read as 11 follows: 12

“TABLE 629.03-1 TEMPORARY PAVEMENT MARKINGS

TYPE PAVEMENT MARKINGS

Passing Permitted - Both Sides

Single 4-inch yellow stripe 5 feet in length spaced 20 feet on center with Type D markers spaced 40 feet on center and located on center of 5-foot length of stripe.

Passing Prohibited - Both Sides

Double solid 4-inch yellow stripes with Type D markers placed 20 feet on center on one of 4-inch yellow stripes selected by the Engineer.

Passing Permitted - One Side Only

Single continuous 4-inch yellow stripe with Type D markers placed on stripe 20 feet on center on no-passing side and single 4-inch yellow stripes 5 feet in length spaced 20 feet on center on passing side.

Lane Lines - Lane Changing Permitted

Single 4-inch yellow or white stripe 5 feet in length spaced 20 feet on center with Type C or Type D markers spaced 40 feet on center.

Lane Lines - Lane Changing Prohibited

Double solid 4-inch white stripes with Type C markers placed 20 feet on center on one of the 4-inch white stripes selected by the Engineer.

Crosswalk Two 12-inch white transverse lines spaced 8 feet on center or as ordered by the Engineer.

Stop Line Single 12-inch white transverse line.

Note: Paint may be used for temporary markings in areas where final paving is not complete.”

(III) Amend 629.04 – Measurement by revising lines 292 to 294 to read as 16 follows: 17

629-2a r11/13/2026

“629.04 Measurement. 20

(A) The Engineer will measure thermoplastic and preformed pavement 22 marking tape per linear foot in accordance with the contract documents. 23 The longitudinal pavement markings will be measured per linear foot as 24 a single stripe for the width specified in the contract and in the proposal. 25 The Engineer will include the longitudinal gaps for skip striping, up to 26 thirty (30) feet long, in the measurement. 27

The Engineer will measure the transverse markings by per each 29 according to the contract. 30

The Engineer will not measure temporary pavement markings including 32 flexible delineator posts with reflector makers or Type I Barricades and 33 temporary signs installed for the longitudinal guidance of public traffic 34 over reconstructed areas, cold planed surfaces, newly paved surfaces 35 or other unmarked or scarified areas for payment. 36

The Contractor shall consider the work required for the removal of 38 pavement markings incidental to the various contract items, except as 39 provided in the proposal or elsewhere in the contract. 40

(B) The Engineer will measure the pavement markers per each for the types 42 shown in the proposal. 43

(C) The Engineer will measure the painted stripes that are twelve (12) 45 inches wide or less as a single stripe. The Engineer will measure the 46 painted stripes over twelve (12) inches wide as two (2) stripes. The 47 Engineer will measure the double stripes that are twelve (12) inches or 48 less in total width including the transverse space between the stripes as 49 a single stripe. 50 The Engineer will measure the longitudinal pavement markings by the 52 linear foot according to the contract. Longitudinal gaps for skip striping 53 that are 30 feet or less will be included in the measurement. 54 The Engineer will measure the transverse markings by per each 56 according to the contract.” 57

(IV) Amend 629.05 – Payment by revising lines 296 to 330 to read as follows: 60 “629.05 Payment. 62

(A) The Engineer will pay for thermoplastic and preformed pavement 64 marking tape at the contract price per linear foot according to the 65 contract, complete in place, including primers. 66

629-3a r11/13/2026

The Engineer will pay for double four (4) inch and double six (6) inch 68 striping with a four (4) inch space between stripes at the contract price 69 per linear foot according to the contract. 70 The Engineer will pay for crosswalk markings at the contract price per 72 each according to the contract. 73 The Engineer will pay for pavement arrows (single and multiple heads), 75 words, and white yield lines at the contract price per each according to 76 the contract. 77

The contract unit price paid shall be full compensation for furnishing 79 labors, materials, tools, equipment and incidentals and for doing the 80 work involved in furnishing and installing pavement markings complete 81 in place according to the contract. 82 The Engineer will not pay for the temporary pavement markings 84 including flexible delineator posts with reflector markers or Type I 85 Barricades and temporary signs installed for the longitudinal guidance 86 of public traffic over reconstructed areas, cold planed surfaces, newly 87 paved surfaces or other unmarked or scarified areas for payment if not 88 shown in the proposal separately. The Engineer will consider them 89 incidental to the various contract items. 90

(B) The Engineer will pay for the various types of pavement markers at the 92 contract price per each according to the contract, complete in place, 93 including adhesives. 94

(C) The Engineer will pay for painted pavement striping at the contract price 96 per linear foot according to the contract. 97

The Engineer will pay for quantities of crosswalk marking at the contract 99 price per each according to the contract. 100 The Engineer will pay for pavement arrows (single or multiple arrow 102 heads), words, and white yield lines at the contract price per each 103 according to the contract. 104 The Engineer will pay for the following pay items when included in the 106 proposal schedule: 107 Pay Item Pay Unit 109

4 - Inch Double Yellow Pavement Striping (Thermoplastic) Linear Foot 111 6 - Inch White Pavement Striping (Thermoplastic) Linear Foot 113

629-4a r11/13/2026

8 - Inch Yellow Pavement Striping (Thermoplastic) Linear Foot 114 6 - Inch Double Yellow Pavement Striping (Thermoplastic) Linear Foot 116 8 - Inch White Pavement Striping (Thermoplastic) Linear Foot 118 Crosswalk Marking (Thermoplastic) Each 120 White Yield Line (Thermoplastic) Each 122 Pavement Arrow (Thermoplastic) Each 124 Pavement Word (Thermoplastic) Each 126

Type C Pavement Marker Each 128 Type H Pavement Marker Each 130

Type F Pavement Marker Each” 132

END OF SECTION 629 134

D

C G x

E N D

R O A D

W

R O A D

W O R K

A H E A D

X X

R O A D

W O R K

F T

O N E

R 2

C W C x x

M.

P.

H

M.

P.

H.

C W A d

C W A x x

S E E

N O T E

1) C W X X A

C W X X A x x

T W O L А

A

O R K

C W O A x

S U P P L E M E N T A L

P L A T E x

C W x

C O N O N E L

R O A

D

D

F E E T

Π

T M I N

M I N

M I N

MI

N

R W O R K

A R E A

D

이

F E E T

LA

NE

J A D

F T

D x

C W D A x

S U P P L E M E N T A L

P L A T E

"x

N E

H I G H W A Y

N O T E S

E N D

R O A D

W O

1.

C W A d s i g n r e q u i r e d f o r p o s t e d s p e li mi t o f m p h o r r g r e a t e r

S e e

T A B L E fo r ad di ti on al d i m e n s i o n s

O N E

L A N E

R O A D

C W o n d

F L A G G E

A H E A D

C W s i g n s sh al l b e r e m o v e

. 기 o r c o v e r e d w h e n n o w o r k is b e i n g p e r f o r m e d o n d l o n e is n o t c l o s e d

T h e a d v i s o r y s p e e d x x s h a l l b e d e t b y t h e

E n g i n e e r

C o n e s o r d e l i n e a t o r s s t a l l b e in st al le o c m a x o n t o p e r s

O N E

L A N E

C L O

F I G U R E

T R A F F I C

C O N T R O L

P L A N

D

C W A x

C W X X A x

C W A d x

S E E

N O T E

R O A D

A N E

R O E D

W O R K

D

F T

W O R K

A H E A D

X X

X X

C W X X A

M.

F.

x

D D

C G A

O R K x e d

L E G E N D

E R e r m i n e d

P a t

S I G N

C O N E

O R

D E L I N E A T O R

D I R E C T I O N

O F

T R A F F I C

P O L I C E

O F F I C E R F L A G G E R

R

D

O A D

O R K

A H E A D

R O A D

W O R K

D

F T

X X

C W A d x

S E E

N O T

C W X X A x

N O T E S

C W A

D x

C W X X x

1.

C W A d si gn re qu ir ed f o

S e e

T A B f o r a d d i t i o n o

T h e a d v i s o r y s p e e d

(x x) s

M U L T I L A N E

U

C

Ω W O R K

A

F I G H T

LA

NE

G H T

L A R E

C L O S E D

C L O S E D

D

F T

X X

C W D R x

C W X X A x

X X

C W R A x

C W X X A x

L E C p o s t e d s p e e d li mi t o f m p h o r g r e a t e r d i m e n s i o n s ha il b e d e t e r m i n e d b y t h e

E n g i n e e r

I N D I V I D E D

H I G H W A Y

R I G H T

L A R

F I G U R E

T R A F F I C

C O N T R O L

P L A N

M I N

M I N

A R E A

E N D

R O A D

W O R K

C G A x

G E N D

S I G N

C O N E

O R

D E L I N E A T O R

D I R E C T I O N

O F

T R A F F I C

F L A S H I N G

A R R O W

S I G N A L

N E

C L O S E D

R

R O A D

W O R K

A H E A D

X X

R O A D

W O R K

D

FT

X X

ח

M Р

C W A d x

S E E

N O T E

1)

C W A D x

C W X X A

C C

C W X X A x x

M U L T I L A N E

U

F

R O E や

A( D) x

R O A D

W O R K

C F T

C W x

R O A D

W O R

F

E N D

A D

W O R K

A x

W O R K

A R E A

D

D D

LE

-T

L A N E

A E

C L O S E D

D

FT

X X

M P H

W D X L x

W X X A x

X X

A P L

C W L A

X

C W X X A x

Π

B W O R K

M I N

M I N

A R E A

N O T E S

1.

C W A d si gn re qu ir ed f o r s p e e d li mi t o f m p h o r

S e e

T A B L E f o r a d d i t i o n a l

P

T h e o d v i s o r y s o e e d x x s h o d e t e r m i n e d b y t h e

E n g i n e e r

N D I V I D E D

H I G H W A Y L E F T

L A N

G U R

R A F F I C

C O N T R O L

P L A N

A

C W A D x

B O A D

C W A d x

S E E

N O

1) C W K X X A x

W O R K

D

F T

R O A D

W O R K

A H E A D

X X

M P H

D D

E N D

C G A

R O A D

W O R K x

L E G E N D p o s t e d g r e a t e r i m e n s i o n s ll b e

S I G N

C O N E

O R

D E L I N E A T O R

D I R E C T I O N

O F

T R A F F I C

F L A S H I N G

A R R O W

S I G N A L

H E

C L O S E D

R

R O A D

W O R K

A H E A D

R O A D

W O R K

F x x

C W -0 A d x

S E E

N O

1)

O W A D x

C W X X

C W X X O A x x

C W

M U L

T I L A N E F I C

N E D I A N

D T

B

RI

GH

T L A N E

C L O S E D

C L O S E D

D

F T

C W D X R x

O R

LE

FT

L

AN

E C L O S E D

C W R A x

O R

1.N O T E S

C W A d si gn re qu ir ed f o s p e e d li mi t o f m p h o

S e e

T A B f r o d d i t i o n c

T h e od vi so ry s p e e d x x d e t e r m n e d b y t h e

E n g i n e e

F o r w o r k b e i n g p e r f o r m e d le ft l a n e l ef t l o n e c l o s u r e t a p e r s h a l b e su bs ti tu te d.

F

C W D L x

X X A x

C W L A x

X X C W X X A x

D I V I D E D

H I G H W A Y

O N E

L A N E

S U R E

T R A F F I C

C O N T R O L

P L A N

V O R K

A R E A

M I N

M I N o r p o s t e d g r e a t e r al d i m e n s i o n s th al l b e i n t h e s i g n s a n d

E N D

R O A D

W O R K

C G A x

L E G E N D

S I G N

C O N E

O R

D E L I N E A T O R

D I R E C T I O N

O F

T R A F F I C

F L A S H I N G

A R R O W

S I G N A L

C L O S E D

R

ADDENDUM NO. 2

NH-019-2(076)

r11/13/2026 P-8

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

201.0100 Removal of Existing Trees 54 EA $_________ $__________

201.0200 Clearing and Grubbing 16,590 S.F. $_________ $__________

202.0100 Removal of Existing Fence 710 L.F. $_________ $__________

202.0200 Removal of Existing Concrete Walkway 3,140 S.F. $_________ $__________

202.0300 Removal of Existing Concrete Curb 2,880 L.F. $_________ $__________

202.0400 Removal of Existing Wall 820 L.F. $_________ $__________

202.0500 Removal of Existing Traffic Sign 50 EA $_________ $__________

202.0600 Removal of Existing Drainage Structures 7 EA $_________ $__________

202.0700 Removal of Existing Drain Pipe 252 L.F. $_________ $__________

203.0100 Roadway Excavation 5,570 C.Y. $_________ $__________

204.0100 Excavation for Seawall Repair 415 C.Y. $_________ $__________

204.0200 Steel Plate for Seawall Repair 1,250 S.F. $_________ $__________

206.0100 Excavation and Backfill for Drainage Facilities 763 C.Y. $_________ $__________

209.0100 Installation, Maintenance, Monitoring, and Removal of BMP L.S. L.S. L.S. $__________ r11/13/2026 P-9

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

209.0200 Additional Water Pollution, Dust and Erosion Control F.A. F.A. F.A. $_ __290,000

212.0100 Archeological Monitoring F.A. F.A. F.A. $_ __ 50,000

301.0100 Hot Mix Asphalt Base Course 1,940 Ton $_________ $__________

305.0100 Aggregate Subbase 2,360 C.Y. $_________ $__________

314.0100 Controlled Low Strength Materials (CLSM) 460 C.Y. $_________ $__________

401.0100 Pavement Smoothness Incentive Allowance Allow Allow $_ __ 50,000

401.0200 4” PMA Pavement, Mix No. IV 1,850 Ton $_________ $__________

411.0100 10-Inch Concrete Pavement 180 C.Y. $_________ $__________

413.0100 10-Inch Stamped Textured Cement Concrete (Truck Apron)

690 S.Y. $_________ $__________

413.0200

4-Inch Stamped Textured Cement Concrete (Splitter Islands)

540 S.Y. $_________ $__________

503.1000 Concrete in Retaining Wall L.S L.S L.S $__________

511.0100 Unclassified Shaft Excavation (30-inch Diameter) 180 L.F. $_________ $__________

511.0200 Drill Shaft (30-inch Diameter) 180 L.F. $_________ $__________ r11/13/2026 P-10

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

603.0100 Bed Course Material for Culvert 159 C.Y. $_________ $__________

603.0200 24-inch Reinforced Concrete Pipe, Class III 801 L.F. $_________ $__________

604.0100 Type A Storm Drain Manhole, 5 feet to 10 feet 5 EA $_________ $__________

604.0200 Type 1A-9P Grated Drop Inlet, 0 feet to 5 feet 2 EA $_________ $__________

604.0300 Type 1A-9P Inlet, 5 feet to 10 feet 1 EA $_________ $__________

604.0400 Type D Catch Basin, 0 feet to 5 feet 7 EA $_________ $__________

604.0500 Type B Catch Basin, 5 feet to 10 feet 7 EA $_________ $__________

604.0600 Reconstructed Type 1211214P Catch Basin, 0 feet to 5 feet

1 EA $_________ $__________

604.0700 Adjusting Storm Drain Cast Iron Frame and Cover 4 EA $_________ $__________

604.0800 Adjusting Storm Drain Steel Frame and Grates 4 EA $_________ $__________

604.0900 Type 1211214P Steel Grates 1 EA $_________ $__________

606.0100 Guardrail Type Midwest Guardrail System (MSG) 220 L.F. $_________ $__________

606.0200 Terminal Section Type MSKT 1 EA $_________ $__________ r11/13/2026 P-11

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

606.0300 End Anchorage Type Trailing-End Anchorage System 1 EA $_________ $__________

607.0100 4-feet, Chain Link Fence 400 L.F. $_________ $__________

607.0200 Cattle Gate 1 EA $_________ $__________

610.0100 (6-Inch) Reinforced Concrete Driveway 38 S.Y. $_________ $__________

617.0100 Soil Preparation, 18" Depth 282 C.Y. $_________ $__________

617.0200 Imported Screened Topsoil, 4" Layer 282 C.Y. $_________ $__________

617.0300 Imported Compost, 2" Layer 22,800 S.F. $_________ $__________

617.0400 Soil Amendments 22,800 S.F. $_________ $__________

619.0100 Hau (Hibiscus tiliaceus, 25 Gal, 1.5”-2” Cal, 4’-6’ Brown Trunk Height)

9 EA $_________ $__________

619.0200 Ohia Lehua (Metrosideros polymorpha, 25 Gal, 1.5”-2” Cal, 4’-6’ Brown Trunk Height)

3 EA $_________ $__________

619.0300 Naupaka Kahakai (Scaevola taccada, 6” Pots @ 24” O.C.

Full and Bushy, 18” – 24” Height)

885 EA $_________ $__________

619.0400 Pohinahina (Vitex rotundifolia, 6” Pots @12” O.C., Triangular Spacing)

670 EA $_________ $__________

619.0500 Plastic Header 700 L.F. $_________ $__________

r11/13/2026 P-12

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

619.0600 Root Control Barrier 375 L.F. $_________ $__________

619.0700 Re-naturalized Lava 5,600 S.F. $_________ $__________

619.0800 Mortared Renaturalized Lava 6,200 S.F. $_________ $__________

621.0100 Inventory of Invasive Species before Construction L.S. L.S. L.S. $__________

621.0200

Invasive Species Removal Plan F.A. F.A. F.A. $ _____5,000

621.0300 Removal of Plants and Animals Established before

Physical Construction or Site Work, Post Removal Monitoring

F.A. F.A. F.A. $ _____30,000

621.0400 Monitoring of Invasive Species During and After

Construction

L.S. L.S. L.S. $__________

621.0500 Post-Construction Inventory Prior to Returning the Site to the State

L.S. L.S. L.S. $__________

622.1001 Removal of Existing Roadway Lighting System L.S. L.S. L.S. $__________

622.1002 Temporary Roadway Lighting System L.S. L.S. L.S. $__________

622.1003 Street Light System Cabinet and Foundation 1 EA $_________ $__________ r11/13/2026 P-13

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

622.1004 Street Light Luminaire, 85W, E2-HI50-ST-85W-7PD-SF

LED Luminaire, 30’ Aluminium Pole, Transformer Base, Dualhead, 8’ Bracket Arm, Concrete Base, and Appurtenances

4 EA $_________ $__________

622.1005 Street Light Luminaire, 85W, E2-HI50-ST-85W-7PD-SF

LED Luminaire, 30’ Aluminium Pole, Transformer Base, Single Head, 15’ Bracket Arm, Concrete Base, and Appurtenances

8 EA $_________ $__________

622.1006 Street Light Luminaire, 100W, E2-HI50-ST-100W-7PD-SF LED Luminaire, 30’ Aluminium Pole, Transformer Base, Single Head, 8’ Bracket Arm, Concrete Base, and Appurtenances

10 EA $_________ $__________

622.1007 Street Light, Type A Pullbox 18 EA $_________ $__________

622.1008 Street Light, Type C Pullbox 1 EA $_________ $__________

622.1009 Street Light Conductors, #4 RHW 20,000 L.F. $_________ $__________

622.1010 Ground Conductors, #6 RHW 10,000 L.F. $_________ $__________

622.1011 Street Light Conduit, 2” PVC Sch. 40 3,000 L.F. $_________ $__________

622.1012 Concrete Jacket, Lighting 75 C.Y. $_________ $__________

622.1013 Removal of Existing Traffic Signal System L.S. L.S. L.S. $__________ r11/13/2026 P-14

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

624.0100 Water Systems L.S. L.S. L.S. $__________

626.0100 Adjusting Sewer Manhole Frame and Cover 4 EA $_________ $__________

626.0200 Adjusting Water Standard Meter Box 3 EA $_________ $__________

626.0300 Adjusting Water Standard Valve Box 7 EA $_________ $__________

627.1001 CCTV Cabinet and Foundation, and Associated HELCO

Meter Box

1 EA. $_________ $__________

627.1002 CCTV Camera Pole with Mounting Bracket, 30’ Aluminum Pole, Concrete Base, and Appurtenances

2 EA $_________ $__________

627.1003 CCTV, Type A Pullbox 2 EA $_________ $__________

627.1004 CCTV Conduit, 2” PVC Sch. 40 350 L.F. $_________ $__________

627.1005 Concrete Jacket, CCTV 6 C.Y. $_________ $__________

629.0100 4-Inch Double Yellow Pavement Striping (Thermoplastic) 1,300 L.F. $_________ $__________

629.0200 6-Inch White Pavement Striping (Thermoplastic) 2,760 L.F. $_________ $__________

629.0300 8-Inch Yellow Pavement Striping (Thermoplastic) 1,500 L.F. $_________ $__________

629.0400 6-Inch Double Yellow Pavement Striping (Thermoplastic) 1,000 L.F. $_________ $__________

629.0500 8-Inch White Pavement Striping (Thermoplastic) 180 L.F. $_________ $__________ r11/13/2026 P-15

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

629.0600 Crosswalk Marking (Thermoplastic) 12 EA $_________ $__________

629.0700 White Yield Line (Thermoplastic) 5 EA $_________ $__________

629.0800 Pavement Arrow (Thermoplastic) 40 EA $_________ $__________

629.0900 Pavement Word (Thermoplastic) 2 EA $_________ $__________

629.1000 Type C Pavement Marker 76 EA $_________ $__________

629.1100 Type H Pavement Marker 72 EA $_________ $__________

629.1200 Type F Pavement Marker 2 EA $_________ $__________

630.0100 Panel for Destination Sign 24 S.F. $_________ $__________

630.0200 Type B Post and Arms for Destination Sign 2 EA $_________ $__________

630.0300 Type A Route Marker Assembly 1 EA $_________ $__________

631.0100 Regulatory Sign (10 Square Feet or Less) 16 EA $_________ $__________

631.0200 Regulatory Sign (More than 10 Square Feet) 7 EA $_________ $__________

631.0300 Warning Sign (10 Square Feet or Less) 12 EA $_________ $__________

631.0400 Warning Sign (More than 10 Square Feet) 11 EA $_________ $__________ r11/13/2026 P-16

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

631.0500 Relocation of Existing Sign 5 EA $_________ $__________

634.1000 Portland Cement Concrete Sidewalk 1,850 S.Y. $_________ $__________

636.0100 Additional E-Construction Programs, additional

licenses or additional equipment

F.A. F.A. F.A. $_ __ 50,000

638.0100 Curb, Type 2D 1,550 L.F. $_________ $__________

638.0200 Curb and Gutter, Type 2DG 2,590 L.F. $_________ $__________

638.0300 Curb and Gutter, Rolled Mountable 490 L.F. $_________ $__________

641.0100 Hydro-Mulch With Grass Sprig 19,415 S.F. $_________ $__________

641.0200 Additional Hydro-Mulch With Grass Sprig Applications F.A. F.A. F.A. $___116,490

645.0100 Work Zone Traffic Control L.S. L.S. L.S. $__________

645.0200 Additional Police Officers, Traffic Control Devices, and Advertisement

F.A. F.A. F.A. $_ __ 250,000

647.1001 Fiber Optic Cable, 3' x 5' Telecom Handhole, Traffic Rated 5 EA $_________ $__________

647.1002 Fiber Optic Cable Conduit, 4” PVC Sch. 40 2,500 L.F. $_________ $__________

647.1003 Concrete Jacket, Fiber Optic Cable Conduit 65 C.Y. $_________ $__________

647.1004 Hawaiian Telcom Manhole, 4' x 6'-6" x 6'-6", Traffic Rated 2 EA $_________ $__________ r11/13/2026 P-17

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

647.1005 Hawaiian Telcom Conduit, 5” PVC Sch. 40 1,000 L.F. $_________ $__________

647.1006 Concrete Jacket, Hawaiian Telcom Conduit 25 C.Y. $_________ $__________

648.0100 Field-Posted Drawings L.S. L.S. L.S. $__________

650.0100 Bicycle Ramp 2 E.A. $_________ $__________

650.0200 Curb Ramp, Type A 6 E.A. $_________ $__________

650.0300 Detectable Warning Mat 24 E.A. $_________ $__________

671.1000 Protection of Endangered Species F.A. F.A. F.A. $_ __ 50,000

696.0100 Field Office Trailer (Not to Exceed $32,000.00) L.S. L.S. L.S. $__________

696.0200 Project Site Laboratory Trailer (Not to Exceed $22,000.00) L.S. L.S. L.S. $__________

699.0100 Mobilization (Not to exceed 6 percent of the sum of all items excluding the bid price of this item)

L.S. L.S. L.S. $__________

Total Amount for Comparison of Bids…………………………………………………………………. $__________ r11/13/2026 P-18

PROPOSAL SCHEDULE

ITEM NO. ITEM

APPROX.

QUANTITY

UNIT UNIT PRICE AMOUNT

NOTE: Bidders must complete all unit prices and amounts. Failure to do so may be grounds for rejection of bid.

1. Bids shall include all Federal, State, County and other applicable taxes and fees.

2. The TOTAL AMOUNT FOR COMPARISON OF BIDS shall be used to determine the lowest responsible bidder.

3. Bidders shall complete all unit prices and amounts. Failure to do so shall be grounds for rejection of bid.

4. If a discrepancy occurs between unit bid price and the bid price, the unit bid price shall govern.

5. Bidders shall submit and upload the complete proposal to HIePRO prior to the bid opening date and time. Proposals received after said due date and time shall not be considered. Any additional support documents explicitly designated as confidential and/or proprietary shall be uploaded as a separate file to HIePRO. Bidders shall not include confidential and/or proprietary documents with the proposal. The record of each bidder and respective bid shall be open to public inspection. Original (wet ink, hard copy) proposal documents are not required to be submitted. Contract award shall be based on evaluation of proposals submitted and uploaded to HIePRO.

FAILURE TO UPLOAD THE COMPLETE PROPOSAL TO HIePRO SHALL BE GROUNDS FOR REJECTION OF THE BID.

If there is a conflict between the specification document and the HIePRO solicitation, the specifications shall govern and control, unless otherwise specified.

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs

NOVEMBER 13, 2026

Response to Request for Information (RFI’s/Questions)

HIePRO Questions for Solicitation B27000553

HILO BAYFRNT INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE

VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO

ISLAND OF HAWAII

FEDERAL-AID

PROJECT NO. NH-019-2(076)

As of October 23, 2026

1. In regards to the chain link fencing, section 607 refers to section 722 for materials, 4' height per HDOT would be 11ga wire. in order to meet AASHTO Type I, Class D, wire needs to be 9ga. it is not available in 11ga. please clarify wire gauge and coating.

RESPONSE: Materials shall comply with Section 722.

2. Please provide a geotechnical report for the project.

RESPONSE: See attached for three geotechnical reports:

1. Pavement Justification Report for Intersection Improvements at Bayfront Highway, September 16, 2022.

2. Recommendations for Retaining Structures for Intersection Improvements at Bayfront

Highway, June 5, 2026.

3. Drilled Shaft Foundation Recommendations for Intersection Improvements at Bayfront

Highway, June 16, 2026.

3. Can we substitute 24" HDPE pipe for the 24" concrete pipe for the drainlines?

RESPONSE: Storm drain pipe shall be RCP, Type III.

4. Are we allowed to close the intersection for multiple days? Does the roadway need to be open to traffic at the end of each working day?

RESPONSE: Waianuenue Ave could be closed for approximately 2 - 3 months with detour through Wailuku Drive and Shipman Street. See Sheet 22 & 58.

One-lane closure (Hilo bound) of Wailuku Bridge with southbound detour through Wainaku

Street is permitted. See Sheet 23, 59 & 60.

5. For pay item 630.0100 panel for destination sign - is this sign extruded aluminum or flat sheet aluminum?

RESPONSE: Sign shall be extruded aluminum.

6. Please provide a detail for graphic layout for 630.0100 panel for destination sign.

RESPONSE: Existing sign shall be used as an example.

7. Please provide a detail for Type B Post and Arms for Destination Sign? Are arms for lights required? Typically in recent projects, light are not required with new reflective sheeting on Destination signs.

RESPONSE: Arms for lights are not required.

8. Seawall Repair Details - Reference: Proposal Items 204.0100 and 204.0200; Section

204; Plans Sheets 25–26 Please provide additional details for the proposed seawall repairs, including the limits of work, steel plate dimensions and thickness, anchorage, and connection requirements. Additionally, please clarify whether temporary excavation support, dewatering, and restoration of existing improvements are included in the identified pay items.

RESPONSE: Limited of CLSM restoration may be estimated as about 380 feet long. This limits would likely be modified after the pre-construction probing test program to be conducted by the Contractor. The probing test program is to verify the subsurface profile and existing tieback anchor locations within the limits of CLSM restoration. The 8’x10’ steep plates may be used to contain the CLSM from leaking into the ocean. They would be left in-place. Provided the CLSM to be placed/tremied from bottom up, dewatering will not be required. The contractor should determine the method and equipment to be used for trench excavation, subject to practical limits and safety considerations. The excavations should comply with the applicable local safety requirements. Trench shoring design and installation should be the responsibility of the contractor.

9. Drilled Shaft Quantities and Payment - Reference: Proposal Items 511.0100 and

511.0200; Section 511 Both drilled shaft pay items identify quantities of 180 LF.

Please confirm these items represent separate payment components for the same 180

LF of drilled shafts, rather than separate installations. Additionally, please clarify how differing subsurface conditions, including rock or obstructions, will be measured and compensated.

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs

NOVEMBER 13, 2026

RESPONSE: Confirming the items represent payment components for the same 180 LF of drilled shafts. The contractor should anticipate differing subsurface conditions, including rock or obstructions, and shall be considered incidental to bid item 511.0100.

10. Utility Relocations and Responsibilities - Reference: Plans Sheets 7 and 47–50;

Utility Notes Please confirm which utility relocations and modifications will be performed by the Contractor and which, if any, will be completed by the respective utility owners. Additionally, are there anticipated restrictions on utility shutdowns or service interruptions that should be considered when developing the construction schedule?

RESPONSE: Storm drain, water, fire hydrant and sanitary sewer modifications will be done by the Contractor.

Relocation of HELCO and Spectrum overhead cables and poles will be done by the utility owners.

Hawaiian Telcom scope, division of responsibilities:

• Demolition:

o Hawaiian Telcom:

Remove existing cabling in existing underground ducts.

o Contractor (after cable removal by HT):

Remove 1 existing hand hole.

Remove existing underground ducts to extent shown on plans.

• New Work:

o Contractor:

Install 2 new handholes.

Install new underground ducts.

Provide pull chord for HTEL to use.

o Hawaiian Telcom:

Install new cables in new underground ducts.

Splice new cables to existing cables in new handholes.

Utility shutdowns and service interruptions must be scheduled and approved by each respective utility, HDOT, and County of Hawai'i.

11. Existing Utility Information - Reference: Plans Sheets 3–8 and 47–50 Have subsurface utility investigations or test pits been performed to verify the locations and elevations of existing utilities within the project limits? If so, please provide the

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs available information, particularly at proposed drainage crossings, waterline connections, and retaining wall excavations.

RESPONSE: None have been completed. Contractor responsibility to confirm locations and elevations of existing utilities within project limits.

12. Existing Drainage Connections - Reference: Plans Sheets 47–50; Sections 603 and

604 Please confirm whether the existing drainage lines and outfalls designated for connection or reuse have been inspected and verified for condition, size, and invert elevations. If existing facilities are found unsuitable for connection, will additional repairs or replacement be addressed as extra work?

RESPONSE: Existing storm drain inspections have not been completed. Unsuitable conditions will be addressed if found in the field.

13. Construction Sequencing and Temporary Pavement - Reference: Plans Sheets 19–24 and 56–60; Section 645 Please confirm whether the five construction phases shown in the plans are mandatory or if alternate sequencing may be proposed by the

Contractor for approval. Additionally, please clarify whether temporary pavement, roadway widening, or other improvements will be required to maintain traffic during construction beyond those specifically shown in the plans. If required, how will this work be measured and paid?

RESPONSE: The phases are not mandatory. Any work required to support the phasing or sequencing shall be considered incidental to Work Zone Traffic Control.

14. Earthwork Quantities and Material Disposal - Reference: Plans Sheets 41–42; Item

203.0100 Please confirm whether the 5,570 CY of roadway excavation includes all proposed roadway grading, roundabout islands, and associated earthwork. Has an earthwork balance been developed for the project? If available, please provide the anticipated quantities of material to be reused onsite, imported, or exported.

Additionally, please clarify whether surplus excavated material is to be disposed of offsite at the Contractor's expense.

RESPONSE: See revised Proposal Schedule. Surplus excavated material shall disposed of offsite at the Contractor's expense.

15. Existing 36-Inch Culvert at Retaining Wall - Reference: Plans Sheets 43 and 68

Please clarify the required treatment of the existing 36-inch culvert adjacent to the proposed retaining wall. Is the culvert to remain in service during construction? Are temporary support, diversion, or modifications to the existing pipe anticipated? If so, please provide the applicable details.

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs

RESPONSE: Culvert should remain in service during construction.

16. Hawaiian Telcom Scope and Responsibilities - Reference: Utility/Communications

Plans; Associated Proposal Items Please clarify the division of responsibilities between the Contractor and Hawaiian Telcom for the proposed communications improvements. Specifically, is the Contractor responsible for installation of conduits and manholes only, or will cable installation, transfer of existing facilities, connections, and testing also be required? Additionally, are there any utility-owner inspection or approval requirements that could affect the construction schedule?

RESPONSE: Cable installation, transfer of existing facilities and connections will be done by

HT. HT inspectors will require the Contractor to test the new conduits with mandrels prior to acceptance.

Utility-owner inspections and approvals will be required for new manholes and conduits provided by the Contractor for HTel’s system.

Hawaiian Telcom scope, division of responsibilities:

• Demolition:

o Hawaiian Telcom:

Remove existing cabling in existing underground ducts.

o Contractor (after cable removal by HT):

Remove 1 existing hand hole.

Remove existing underground ducts to extent shown on plans.

• New Work:

o Contractor:

Install 2 new handholes.

Install new underground ducts.

Provide pull chord for HTEL to use.

o Hawaiian Telcom:

Install new cables in new underground ducts.

Splice new cables to existing cables in new handholes.

17. Environmental Permits and Restrictions - Reference: Plans Sheets 9–11; Sections

209, 621, and 671 Please provide copies of the environmental permits and approvals applicable to the project, including any project-specific conditions or restrictions.

Please clarify which permits have already been obtained by HDOT and which will be the responsibility of the Contractor. Additionally, are there any seasonal work restrictions, prohibited construction periods, or special monitoring requirements that should be considered when developing the construction schedule?

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs

RESPONSE: See attachment Environmental Mitigation Measures Commitment Checklist.

18. Work Hours and Lane Closure Restrictions - Reference: Plans Sheets 19–24 and 56–

60; Section 645 – Work Zone Traffic Control Please clarify the allowable construction work hours and lane closure windows for the project. Specifically, are there restrictions on daytime, nighttime, weekend, or holiday work? Additionally, please identify any restrictions on the duration and timing of lane closures, full roadway closures, and temporary detours, including peak-hour limitations. Are there any activities that will be required to take place outside normal working hours?

RESPONSE: See revised Section 645.

19. Proposed Substitutions for Street Light Foundations and Pull Boxes Reference:

Sheets 71 and 92; State Highways Standard Plan TE-47 1. Street Light Pole

Foundations Sheet 71 specifies a 2'-6" diameter drilled shaft concrete foundation with a minimum depth of 20'-0" for typical street light poles. State Highway

Standard Plan TE-47 specifies a minimum 2'-0" diameter foundation with a depth of 8'-6" in sand and gravel conditions, with shorter depths permitted in rock or stiff clay. We have also recently installed numerous 30" x 30" x 6'-0" precast concrete light pole foundations on County and State projects. Please confirm if 30" x 30" x

6'-0" precast concrete foundations can be used in lieu of the specified 2'-6" diameter x 20'-0" deep drilled shaft foundations.

RESPONSE: 30" x 30" x 6'-0" precast concrete foundations in lieu of the specified 2'-6" diameter x 20'-0" deep drilled shaft foundations will not be accepted.

20. Proposed Substitutions for Street Light Foundations and Pull Boxes Reference:

Sheets 71 and 92; State Highways Standard Plan TE-47 2. Cast-in-Place Foundation

Requirements If cast-in-place concrete street light foundations are required, please confirm if the entire foundation must be poured monolithically or if multiple concrete pours are acceptable.

RESPONSE: The entire foundation shall be poured monolithically.

21. Proposed Substitutions for Street Light Foundations and Pull Boxes Reference:

Sheets 71 and 92; State Highways Standard Plan TE-47 Street Lighting Pull Box

Substitution Sheet 92 specifies Type A, B, and C concrete pull boxes for the street lighting system. The County and State have been using polymer pull boxes on recent projects in lieu of traditional concrete pull boxes. Please confirm if polymer pull boxes can be substituted for the specified concrete pull boxes.

RESPONSE: Street Lighting Pull Boxes shall be per State Highways Standard Plan TE-47.

HILO BAYFRONT HIGHWAY INTERSECTION IMPROVEMENTS

AT WAIANUENUE AVENUE, VICINITY OF KAMEHAMEHA AVENUE

DISTRICT OF HILO, ISLAND OF HAWAII

FEDERAL-AID PROJECT NO. NH-019-2(076)

ADDENDUM NO. 2

RESPONSES TO RFIs

File details come from the government source that posted it. Updated .