D.1.a. Environmental Mitigation Measures Commitment Checklist.pdf

PDF 287 KB Posted

Attached to
NH-019-2(076) HILO BAYFRONT HWY INTERSECTION IMPROVEMENTS
Solicitation number
B27000553
Issued by
Hawaii County, Hawaii

About this file

Environmental Mitigation Measures Commitment Checklist

This is an Environmental Mitigation Measures/Commitment Checklist prepared by the Hawaii Department of Transportation (HDOT) in coordination with the Federal Highway Administration (FHWA) for the Hilo Bayfront Highway Intersection Improvements project (Federal-Aid Project No. NH-019-2(076)) located in Hilo District on the Island of Hawaii. The document comprehensively identifies and incorporates environmental conservation and mitigation measures across multiple regulatory frameworks, including the National Historic Preservation Act Section 106, Hawaii Revised Statutes Chapter 6E, Endangered Species Act Section 7, Essential Fish Habitat consultation requirements, Clean Water Act provisions, and Hawaii Environmental Policy Act requirements. The checklist identifies specific responsibilities for the contractor, HDOT, and FHWA; references applicable regulatory documents and determinations; describes detailed mitigation commitments; specifies where measures are incorporated into construction plans (sheets 3-100); and establishes follow-up requirements. Construction is estimated to occur from February 2027 to February 2029, with normal working hours from 7:00 a.m. to 3:00 p.m., Monday to Friday, excluding holidays, and nighttime work restricted between 3:00 p.m. and 7:00 a.m. the following day, with no nightwork between September 15 and December 15 due to seabird fledging season restrictions.

The mitigation measures address historical and cultural resources requiring documentation and rehabilitation of lava rock curbs in adherence to the Secretary's Standards for the Treatment of Historic Properties; terrestrial biological resources protection for Hawaiian hoary bats, Hawaiian geese, waterbirds, seabirds, and sea turtles through seasonal restrictions, nesting surveys, buffer zones, and biological monitoring; aquatic and marine resource protection through Best Management Practices for erosion and sediment control, stormwater pollution prevention, and equipment management; and compliance with noise regulations through noise variance approval, equipment muffling, and community complaint procedures. The contractor is responsible for finalizing a Storm Water Pollution Prevention Plan (SWPPP) prior to construction commencement and implementing comprehensive pollution prevention measures including waste management, hazardous material handling, concrete washout procedures, and fugitive dust control. Additional requirements include obtaining Notice of General Permit Coverage under NPDES regulations; conducting archaeological surveys and halting work if historic properties or human remains are encountered; submitting required notifications to the Department of Health; and maintaining compliance with Hawaii County Code chapters addressing erosion and sedimentation control and floodplain management. All environmental commitments have been incorporated into the construction plans or bid package documents.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Environmental Mitigation Measures/Commitment Checklist

Project Title: Hilo Bayfront Highway Intersection Improvements at Waianuenue Avenue

Federal-Aid Project No. NH-019-2(076)

Hilo District, Island of Hawaii

INCORPORATE ANY ENVIRONMENTAL CONSERVATION/MITIGATION MEASURES OR ENVIRONMENTAL COMMITMENTS BELOW.

SHOULD A PROJECT REQUIRE A MEMORANDUM OF AGREEMENT (SUCH AS THAT FROM SECTION 106), USE SEPARATE SHEET.

Historical and Cultural Resources (NHPA Section 106 and HRS 6E) Responsible

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

HWY-DD 2.2051

NHPA Section

106 Initiation

Letter

7/18/2023

(Page 21)

The project will include rehabilitation of the lava rock curbs.

Any lava rock or basalt curbs identified within the project area will be surveyed and documented prior to work starting and will be rehabilitated as part of the project.

Note: See “NHPA Section 106 Effect Determination Letter from

FHWA to SHPO, 11/18/2024, (Page 7)” below.

Rehabilitation of Lava

Rock Curbs provided on

Sheets 99-100 of

Construction Plans.

Removal of CRM wall provided on Sheet 25 of

Construction Plans.

Yes, HDOT will repurpose the lava rock curbs.

Contractor, HDOT, FHWA

HWY-DD 2.2051

NHPA Section

106 Initiation

Letter

7/18/2023

(Page 21)

The project will include removal of a historic (50+ year old)

CRM wall which is not NRHP or HRHP eligible. This wall will be surveyed and documented prior to work starting.

Rehabilitation of Lava

Rock Curbs provided on

Sheets 99-100 of

Removal of CRM wall provided on Sheet 25 of

Construction Plans.

Yes. Survey and document wall prior to work starting.

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

NHPA Section

106 Effect

Determination

Letter from

FHWA to SHPO

11/18/2024

(Page 7)

The lava rock curbs were surveyed and inventoried as part of the project efforts to identify historic properties in the APE.

They are recognized as having historic value and are a distinctive element of the historic streetscape of downtown

Hilo. During the October 1, 2024, HDOT/SHPD monthly meeting, the treatment of the lava rock curbs in the APE was discussed. HDOT will repurpose the lava rock curbs to preserve them by rehabilitating the curbs in adherence to the Secretary’s

Standards for the Treatment of Historic Properties (36 CFR Part

68). The lava rock curbs will either be used whole and in-place or placed in a new location within the existing APE, used for a similar purpose, such as curbing in parking areas, edging for walkways, or as decorative features in the roundabout. The rehabilitated curb placement will be prioritized in the storefront area near the historic buildings, and on the mauka side of the roundabout. The draft design will be reviewed by

SOI qualified personnel to ensure consistency with the

Secretary’s Standards for the Treatment of Historic Properties

(36 CFR Part 68). Once complete, the final designs that include the rehabilitated lava rock curbs will be uploaded into HICRIS. A letter from the SOI qualified reviewer, including documentation of their qualifications and applicable guidelines, will also be uploaded into the project HICRIS file.

Yes, HDOT will repurpose the lava rock curbs.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

SHPO Project

No.:

2022PR00759,

Doc No.:

2412SH01,

NHPA Section

106 Review -

Continued

Consultation and Request for

Concurrence with the Effect

Determination

12/12/2024

(Page 3)

Any deviations from the scope of work or the APE requires the

Section 106 consultation process reopened prior to the project moving forward, to consider the potential for effects to historic properties resulting in project scope or APE revisions.

Archaeological Notes provided on Sheet 4 of

Construction Plans.

Yes, if deviations from the SOW or APE are needed, reinitiate consultation.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

SHPO Project

No.:

2022PR00759,

Doc No.:

2412SH01,

NHPA Section

106 Review -

Continued

Consultation and Request for

Concurrence with the Effect

Determination

12/12/2024

(Page 3)

Should any potential historic properties be encountered, immediately halt work in the vicinity of the find, secure the find from further disturbance, and follow the stipulations set forth in 36 CFR 800.13.

Should any potential human remains be encountered, immediately halt work in the vicinity of the find, secure the find from further disturbance, and contact SHPD prior to work in the area continuing.

Archaeological Notes provided on Sheet 4 of

Yes, if historic properties are encountered

Contractor, HDOT, FHWA

HWY-DD-

2.20111, HRS 6E-8,

Request for

Concurrence on

Effect

Determination

2/19/2025

(Page 3)

The FHWA has committed to HDOT to repurpose the lava rock curbs to preserve curbs to preserve them by rehabilitating the curbs in adherence to the Secretary’s Standards for the

Treatment of Historic Properties, 36 Code of Federal

Regulations (CFR), Part 68. The lava rock curbs will be used whole and in-place or placed in a new location within the existing APE, used for a similar purpose, such as curbing in parking areas, edging for walkways, or as decorative features in the roundabout. The rehabilitated curb placement will be prioritized in the storefront area near the historic buildings, and on the mauka side of the roundabout. The draft design will be reviewed by a Secretary of Interior Qualified personnel to ensure consistency with the Secretary’s Standards for the

Treatment of Historic Properties (36 CFR Part 68).

Rehabilitation of Lava

Rock Curbs provided on

Sheets 99-100 of

Construction Plans.

Yes, HDOT to repurpose the lava rock curbs.

Terrestrial Biological Resources (ESA Section 7)

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

Project Code:

2023-0038168

Section 7

Informal

Consultation

Letter

1/26/2023

(Page 5)

Woody plants greater than 15 feet in height shall not be disturbed, removed, or trimmed during bat birthing and pup rearing season

(June 1 through September 15). No barbed wire for fencing shall be used.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 1.

No.

Contractor, HDOT, FHWA

Project Code:

2023-0038168

Section 7

Informal

Consultation

Letter

1/26/2023

(Page 5)

All outdoor lighting shall be shielded so the bulb can only be seen from below. Night construction shall be avoided during the seabird fledging season, September 15 through December 15. For night construction occurring during other times of the year, all lighting shall be fully shielded and directed towards the ground. All outdoor lighting, with the exception of streetlights, will have automatic motion sensor switches and controls. Powerline and other existing above ground cables will be relocated within the roadway right-of-way within five feet of the height of the existing cables. If any new fencing or temporary construction fencing is required and extends above vegetation, three strands of polytape

(or similar measure) will be integrated into the fence to increase visibility.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 3, 7, 8 & 9.

No.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Section 7

Informal

Consultation

Letter

1/26/2023

(Page 5)

In areas where waterbirds are known to be present, reduced speed limits will be posted and enforced. In addition, project personnel and contractors will be informed about the presence of endangered species on-site. A biological monitor that is familiar with the species’ biology will conduct Hawaiian waterbird nest surveys, where appropriate habitat occurs within the vicinity of the proposed project site, prior to project initiation. These surveys will be repeated within 3 days of project initiation and after any subsequent delay of work of 3 or more days (during which the birds may attempt to nest). If a nest or active brood is found:

o The USFWS will be contacted within 48 hours for further guidance.

o A 100-foot buffer will be established and maintained around all active nests and/or broods until the chicks/ducklings have fledged. No potentially disruptive activities or habitat alterations will occur within the buffer.

o A biological monitor familiar with the species’ biology will be on-site during all construction or earth moving activities to ensure Hawaiian waterbirds and nests are not adversely impacted until the chicks/ducklings fledge.

Biological Resource

Notes added to Sheet 5 of Construction Plan.

See Note 2.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Section 7

Informal

Consultation

Letter

1/26/2023

(Page 6)

Nene will not be approached, fed, or disturbed. If nene are observed loafing or foraging within the project area during the breeding season (September through April), a biologist familiar with nene nesting behavior will survey for nests in and around the project area prior to the resumption of work. Surveys will be repeated after any subsequent delay of work of 3 or more days

(during which the birds may attempt to nest). If a nene nest is discovered within 150 feet of the work area all work will cease and the USFWS will be contacted for further guidance. If nene are observed in or near the project area the project personnel and contractor will be informed about the presence of nene at the site.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 4.

No.

2023-0038168-

S7-001, Informal

Consultation letter (From

USFWS to

FHWA)

8/8/2023

(Page 3)

Hawaiian Hoary Bats: Avoid disturbing, removing, or trimming woody plants greater than 15-ft tall during the bat birthing and pup rearing season (June 1 through September 15). Avoid use of barbed wire.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 1.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 3)

Hawaiian Goose: Project personnel will not approach, feed, or disturb Hawaiian geese. If Hawaiian geese are observed loafing or foraging within the project area during the breeding season

(September through April), a biologist familiar with Hawaiian goose nesting behavior will survey for nests in and around the project area prior to the resumption of any work. A biologist will repeat surveys after any subsequent delay of work of 3 or more days (during which the birds may attempt to nest). If a nest is discovered within a radius of 150 ft of proposed project, or a previously undiscovered nest is found within the 150-ft radius after work begins the work will cease immediately, and project proponents will contact the Service for further guidance. In areas where Hawaiian geese are known to be present, reduced speed limits will be posted and enforced, and project personnel and contractors will be informed of the presence of federally listed species on-site.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 5.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 4)

Hawaiian Waterbirds: In areas where waterbirds are known to be present, the project will post and implement reduced speed limits, and inform project personnel and contractors about the presence of endangered species on site. If water resources are located within or adjacent to the project site, the project will incorporate applicable best management practices for work in aquatic environments into the project design (enclosed). A biological monitor that is familiar with the species’ biology will conduct

Hawaiian waterbird nest surveys where appropriate habitat occurs within the vicinity of the proposed project site prior to project initiation. The monitor will repeat surveys again within 3 days of project initiation and after any subsequent delay of work of 3 or more days (during which the birds may attempt to nest). If a nest or active brood is found, the project will: Contact the Service within 48 hours for further guidance; Establish and maintain a

100-ft buffer around all active nests and/or broods until the chicks have fledged where potentially disruptive activities or habitat alteration would be avoided within this buffer; A biological monitor that is familiar with the species’ biology will be present on the project site during all construction or earth-moving activities until the chicks fledge to ensure that Hawaiian waterbirds and nests are not adversely affected (i.e., mortality of young, or parents kept from the nest).

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 2.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 5)

Hawaiian Seabirds: Fully shield all outdoor lights so lighting can only be seen from below (year round). Install automatic motion sensor switches and controls on all outdoor lights or turn off lights when human activity is not occurring in the lighted area (except streetlights). Avoid nighttime construction during the seabird fledging period (Sept 15 - Dec 15). New or temporary construction fencing extending above vegetation will be constructed of three strands of polytape, or similar material, to increase visibility.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 3, 7 & 9.

No.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 6)

Hawaiian Sea Turtles: Modification of and vehicle use on beaches or dune environments shall not occur. No removal of native dune vegetation shall occur. Applicable BMPs for work in and around the aquatic environments shall be incorporated into the project

(see enclosure). The contractor (in lieu of a biologist) shall conduct a visual survey of the project site to ensure no basking sea turtles are present. If a basking sea turtles occur within the project area, all mechanical or construction activities shall cease within 100 feet of the sea turtle until it voluntarily leaves the area. All project-related debris, trash, or equipment shall be removed from the beach/dune. No project-related materials will be stockpiled in the intertidal zone, reef flats, sandy beach and adjacent vegetated areas, or stream channels.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 6.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 6)

Reinitiation of consultation is required and shall be requested: If new information reveals effects of the action that may affect listed species or critical habitat in a manner or to an extent not previously considered; If the identified action is subsequently modified in a manner that causes an effect to the listed species or critical habitat that was not considered in the written concurrence; or, If a new species is listed or critical habitat designated that may be affected by the identified actions.

No.

Informal

Consultation letter (From

USFWS to

FHWA)

(Page 7)

USFWS Standard BMPs shown here:

https://www.fws.gov/sites/default/files/documents/Best%20Man agement%20Practices%20For%20Work%20In%20or%20Around%2

0Aquatic%20Environment-April%202022.pdf

Aquatic/Marine Natural Resources (ESA Section 7, Essential Fish Habitat, HRS Ch. 195D)

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Essential Fish

Habitat, Conservation

Recommendati ons Response

May 18, 2023

The FHWA and HDOT will require the contractor to develop and implement a contingency plan for management of equipment, materials, and the job site in the event of an approaching sever storm event, including a tropical storm, hurricane, or predicted rain event anticipated to exceed a 2-year, 24- hour event. This will include removing or securing construction equipment and material at the site, stabilization of stockpiles and un-stabilized areas, and identification of and mitigation of other potential sources of pollution. The plan will also include photographic documentation of pre- and post-storm conditions at the site and inspection and maintenance and repair of BMPs following the storm, as needed.

Yes, contractor to develop contingency plan

Contractor, HDOT, FHWA

Essential Fish

Habitat, Consultation

Letter

May 9, 2023

(Page 3)

A construction site’s primary potential sources of nutrient loading and sediment runoff are ground disturbance and the storage and use of construction equipment and materials.

Extensive BMPs to prevent erosion and sedimentation have been included in the required project specification to contractors.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Essential Fish

Habitat

Consultation

Letter

May 9, 2023

(Page 3)

Storm water BMPs would be installed to isolate the work areas where ground disturbance is required to ensure that debris and runoff does not reach the Wailuku River, Hilo Bay, or any drainage features connected to those waters.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Construction Plans.

No.

Consultation

Letter

May 9, 2023

(Page 3)

Contaminant runoff can also be generated from storage and use of construction equipment that is leaking fuel or oil, and/or improperly stored construction materials being exposed to storm water runoff. Storm water BMPs include maintaining equipment in good working order, storing equipment and materials away from surface waters with strategic placement of absorbent material, such as fiber rolls, as a buffer between equipment and the river or shoreline. Drip pans will also be maintained beneath construction equipment.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Construction Plans.

No.

Consultation

Letter

May 9, 2023

(Page 3)

Waste Management – Concrete wastes, solid wastes, and any sanitary/septic wastes will be located away from surface waters and managed to assure no contamination.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Consultation

Letter

May 9, 2023

(Page 3)

Vehicle and Equipment Management – All vehicle and equipment cleaning, maintenance, and refueling will be located away from surface waters and managed to assure no contamination to EFH.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Construction Plans.

No.

Consultation

Letter

May 9, 2023

(Page 4)

No work will be done in the water, and no permanent structures or temporary fill will be placed in the water.

Biological Resource

Notes added to Sheet 5 of Construction Plans.

See Note 10.

No.

Consultation

Letter

May 9, 2023

(Page 4)

Stockpiling, storage, and equipment staging will utilize appropriate BMPs to prevent potential surface runoff from entering Wailuku River or Hilo Bay. No stockpiling, storage, or heavy equipment will be placed in Wailuku River or Hilo Bay.

Water Pollution and

Erosion Control Notes provided on Sheets 9-11 on Construction Plans.

Erosion Control Plan and Details provided on

Sheets 27-28 on

Native Plants

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

None. The entire project area is within previously developed, modified, and maintained roadway right-of-way. Therefore, Native Hawaiian plant species are not anticipated to be present in the project area.

Not Applicable No.

Noxious and Invasive Species

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

None. Not Applicable No.

Land Use (SMA Use Permit)

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

PL-SAA-2024-

000213, SMA Use Permit

Assessment

Application

3/14/2024

(Page 4)

Please note that any substantive changes to the proposed improvements, as well as any subsequent phases or activities may require further review by this office and possibly the submittal of another SMA Use Permit Assessment Application.

HDOT, FHWA

PL-SAA-2024-

000213, SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

The Applicant shall secure all necessary approvals and permits from other affected federal, state, and county agencies as necessary to comply with all applicable laws and regulations.

Construction Notes are provided on Sheets 3-11 of Construction Plans.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

If required, the Applicant shall secure building permits for the proposed project within five (5) years from the date of this determination. If building permits have not been secured within that five (5) year period, this determination is automatically null and void, and a new Special Management

Area Assessment Application must be submitted for review and approval.

Building Permit is not required.

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

All earthwork and grading activity shall conform to Chapter 10, Erosion and Sedimentation Control of the Hawai‘i County Code.

Work within County

ROW notes provided on

Sheet 6 of Construction

Plans.

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

All construction and maintenance activities on the subject parcel shall comply with Chapter 27, Floodplain Management, of the Hawai‘i County Code.

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

The Applicant shall adhere to all Best Management Practices, monitoring, and mitigation as outlined in the submitted application.

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor, HDOT, FHWA

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

In the event that surface or subsurface historic resources, including human skeletal remains, structural remains (e.g., rock walls, terraces, platforms, etc.), cultural deposits, marine shell concentrations, sand deposits, or sink holes are identified during the demolition and/or construction work, the Applicant shall cease work in the immediate vicinity of the find, protect the find from additional disturbance and contact the State

Historic Preservation Division at (808) 933-7651. Subsequent work shall proceed upon an archaeological clearance from

DLNR-SHPD when it finds that sufficient mitigation measures have been taken.

Archaeological Notes provided on Sheet 4 of

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

Artificial light from exterior lighting fixtures, including, but not necessarily limited to floodlights, up-lights or spotlights used for decorative or aesthetic purposes shall be prohibited if the light directly illuminates, or is directed to project across property boundaries toward, the shoreline and ocean waters, except as may otherwise be permitted pursuant to Section

205A-71(b), Hawai‘i Revised Statutes.

Biological Resource

Protection Notes provided on Sheet 5 of

Construction Plans.

No.

Contractor, HDOT, FHWA

PL-SAA-2024-

000213

SMA Use Permit

Assessment

Application

3/14/2024

(Page 5)

Any further development, including but not limited to, the construction of structures or improvements not included in this determination shall require further review and approval as provided under Chapter 205A, HRS, and Rule 9, Planning

Commission Rules of Practice and Procedure.

Clean Water Act Section 401 Water Quality Certification Important: A 404 permit must always be accompanied by the appropriate 401 Water Quality Certification.

Responsible

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

None.

Clean Water Act Section 404 (ACOE) permit

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

None.

Clean Water Act Section 402 (NPDES Permit)

Party(ies)

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(SWPPP)

(The contractor shall finalize the SWPPP and submit to HDOT for approval following contract award and before the start of construction. The SWPPP will be implemented and revised throughout the project lifespan as construction progresses and on-site conditions changes.)

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract award and before the start of construction

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(SWPPP)

(Page 19)

Construction debris, green waste, general litter:

• Separate contaminated clean up materials from construction and demolition (C&D) wastes.

• Provide waste containers (e.g., dumpster or trash receptacle) of sufficient size and number to contain construction and domestic wastes.

• Inspect construction waste and recycling areas regularly.

· Schedule solid waste collection regularly.

• Schedule recycling activities based on construction/demolition phases.

• Empty waste containers weekly or when they are two-thirds full, whichever is sooner.

• Do not allow containers to overflow. Clean up immediately if they do.

• On work days, clean up and dispose of waste in designated waste containers.

• See Solid Waste Management Section SM-6 for additional requirements.

• Provide Storm Drain Inlet Protection and/or Perimeter

Sediment Controls as applicable.

• Collect and dispose of all waste materials in trash dumpsters. Place dumpsters, with secure watertight lids, away from storm water conveyances and drains, in a covered materials storage area.

• Dispose of construction and non- construction solid waste in accordance with State DOH regs.

• Load removed non- recyclable vegetation directly onto trucks; cover and transport to a licensed facility.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 20)

Materials associated with the operation and maintenance of equipment, such as oil, fuel, and hydraulic fluid leakage:

• Use off-site wash racks, repair and maintenance facilities, and fueling sites when practical.

• Designate bermed wash area if cleaning on site is necessary.

• Place drip pans or drop cloths under vehicles and equipment to absorb spills or leaks.

• Provide an ample supply of readily available spill cleanup materials.

• Clean up spills immediately, using dry clean-up methods where possible, and dispose of used materials properly.

• Do not clean surfaces or spills by hosing the area down.

• Eliminate the source of the spill to prevent a discharge or a continuation of an ongoing discharge.

• Inspect on-site vehicles and equipment regularly and immediately repair leaks.

• Regularly inspect fueling areas and storage tanks.

• Train employees on proper maintenance and spill practices and procedures and fueling and cleanup procedures.

• Store diesel fuel, oil, hydraulic fluid, or other petroleum products or other chemicals in water-tight containers and provide cover or secondary containment.

• Do not remove original product labels and comply with manufacturer’s labels for proper disposal.

• Dispose of containers only after all the product has been used.

• Dispose of or recycle oil or oily wastes according to

Federal, State, and Local requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

• Store soaps, detergents, or solvents under cover or other means to prevent contact with rainwater.

• See Vehicle and Equipment Cleaning, Maintenance, and

Refueling, Sections SM-11, SM-12, and SM-13 and

Material Storage and Handling SM-2 for additional requirements.

Contractor Draft Storm

Water Pollution

Prevention Plan

(SWPPP)

(Page 22)

Soil erosion from the disturbed areas:

• Provide Soil Stabilization, Slope Protection, Perimeter

Controls and Sediment Barriers, , Level Spreader EC-6, Paving Operations SM-20, Construction Roads and

Parking Area SC-10, Controlling Storm Water Flowing

Onto and Through the Project, Post-Construction BMPs, and Non-Structural BMPs (Construction BMP Training

SM-1, Scheduling SM-14, Location of Potential Sources of Sediment SM-15, Preservation of Existing Vegetation

SM-17) .

• Delineate, and clearly mark off, with flags, tape, or other similar marking device all natural buffer areas defined in the SWPPP.

• Preserve native topsoil where practicable. · In areas where vegetative stabilization will occur, restrict vehicle/equipment use in areas to avoid soil compaction or condition soil to promote vegetative growth.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 23)

Sediment from soil stockpiles:

• Locate stockpiles a minimum of 50 feet or as far as practicable from concentrated runoff or outside of any natural buffers identified on the SWPPP.

• Place bagged materials on pallets and under cover.

• Provide physical diversion to protect stockpiles from concentrated runoff.

• Cover stockpiles with plastic or comparable material when practicable.

• Place silt fence, fiber filtration tubes, or straw wattles around stockpiles.

• Do not hose down or sweep soil or sediment accumulated on pavement or other impervious surfaces into any storm water conveyance (unless connected to a sediment basin, sediment trap, or similarly effective control), storm drain inlet, or state water.

• Unless infeasible, contain and securely protect stockpiles from the wind.

• Provide Perimeter Sediment Controls as applicable.

• See Stockpile Management Section SM-3 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 25)

Emulsified asphalt or prime/tack coat:

• Provide training for employees and contractors on proper material delivery and storage practices and procedures.

• Restrict paving operations during wet weather to prevent paving materials from being discharged.

• Use asphalt emulsions such as prime coat when possible.

• Protect manholes during application of tack coat, seal coat, slurry seal, and fog seal.

• Keep ample supplies of drip pans and absorbent materials on site.

• See Material Storage and Handling Section SM-2 and

Paving Operations Section SM-20 for additional requirements.

• Provide Perimeter Sediment Controls as applicable.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Prevention Plan

(Page 25)

Materials associated with painting, such as paint and paint wash solvent:

• Hazardous chemicals shall be well-labeled and stored in original containers.

• Keep ample supply of cleanup materials on site.

• Dispose container only after all of the product has been used.

• Rinse from water-based paints shall be discharged into the sanitary sewer system where possible. If not, direct all washwater into a leak-proof container or leak-proof pit. The container or pit must be designed so that no overflows can occur due to inadequate sizing or precipitation.

• Locate on-site wash area a minimum of 50 feet away or as far as practicable from water bodies.

• Filter and re-use solvents and thinners.

• Dispose of oil-based paints and residue as a hazardous waste.

• Ensure collection, removal, and disposal of hazardous waste complies with regulations.

• Immediately clean up spills and leaks.

• Properly store paints, solvents, and epoxy compounds.

• Properly store and dispose waste materials generated from painting and structure repair and construction activities.

• Mix paints in a covered and contained area when possible to minimize adverse impacts from spills.

• Do not apply traffic paint or thermoplastic if rain is forecasted.

• See Material Storage and Handling SM-2, Waste

Management, Hazardous Materials and Waste

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Management Section SM-9, Waste Management, Spill

Prevention and Control Section SM-10, and Structure

Construction and Painting Section SM-21 for additional requirements.

• Provide Perimeter Sediment Controls as applicable.

Prevention Plan

(Page 27)

Industrial chemicals, fertilizers, and/or pesticides:

• Hazardous chemicals shall be well-labeled and stored in original containers.

• Keep ample supply of cleanup materials on site.

• Clean up spills immediately, using dry clean-up methods where possible, and dispose of used materials properly.

• Do not clean surfaces or spills by hosing the area down.

• Eliminate the source of the spill to prevent a discharge or a furtherance of an ongoing discharge.

• Dispose container only after all of the product has been used.

• Retain a complete set of safety data sheets (formerly

MSDS) on site.

• Store industrial chemicals in water-tight containers and provide either cover or secondary containment.

• Provide cover when storing fertilizers or pesticides to prevent these chemicals from coming into contact with rainwater.

• Restrict amount of pesticide prepared to quantity necessary for the current application.

• Do not apply fertilizers or pesticides during or just before a rain event.

• Do not apply to stormwater conveyance channels with flowing water.

• Comply with fertilizer and pesticide manufacturer’s recommended usage and disposal instructions.

Document departures from manufacturer’s specifications in Attachment J.

• Apply fertilizers at the appropriate time of year for the location, and preferably timed to coincide as closely as

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

possible to the period of maximum vegetation uptake and growth.

• Follow federal, state, and local laws regarding fertilizer application.

• Do not dispose of toxic liquid wastes (solvents, used oils, and paints) or chemicals (additives, acids, and curing compounds) in dumpsters allocated for construction debris.

• Ensure collection, removal, and disposal of hazardous waste complies with regulations. Hazardous waste that cannot be reused or recycled shall be disposed of by a licensed hazardous waste hauler.

• See Material Delivery, Storage, and Material Use SM-2, and Waste Management, Hazardous Waste

Management Section SM-9 for additional requirements.

Prevention Plan

(Page 28)

Hazardous waste (batteries, solvents, treated lumber, etc.):

• Do not dispose of toxic materials in dumpsters allocated for construction debris.

• Ensure collection, removal, and disposal of hazardous waste complies with regulations.

• Hazardous waste that cannot be reused or recycled shall be disposed of by a licensed hazardous waste hauler.

• Segregate and recycle wastes from vehicle/equipment maintenance activities such as used oil or oil filters, greases, cleaning solutions, antifreeze, automotive batteries, and hydraulic and transmission fluids.

• Store waste in sealed containers, which are constructed of suitable materials to prevent leakage and corrosion, and which are labeled in accordance with applicable

Resource Conservation and Recovery Act (RCRA) requirements and all other applicable federal, state, and local requirements.

• All containers stored outside shall be kept away from surface waters and within appropriately-sized secondary containment (e.g., spill berms, decks, spill containment pallets). Provide cover if possible.

• Clean up spills immediately, using dry clean-up methods where possible, and dispose of used materials properly.

• Do not clean surfaces or spills by hosing the area down.

• Eliminate the source of the spill to prevent a discharge or a continuation of an ongoing discharge.

• Ensure collection, removal, and disposal of hazardous waste complies with manufacturer’s recommendations and is in compliance with federal, state, and local requirements.

• See Hazardous Materials and Waste Management

Section SM-9 and Vehicle and Equipment Management, Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Vehicle and Equipment Maintenance SM-12 for additional requirements.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 30)

Metals and building materials:

• Inspect construction waste and recycling areas regularly.

• Schedule solid waste collection regularly.

• If metals are stored on site (such as rebar or galvanized poles) store under cover under tarps or in containers.

• Minimize the amount of material stored on site.

• Do not stockpile uncovered metals in close proximity to discharge points.

• See Solid Waste Management Section SM-6 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract award and before the start of construction

Contractor Draft Storm

Water Pollution

Prevention Plan

Contaminated soil

• See Waste Management, Contaminated Soil

Management Section SM-8 and/or Hazardous Materials and Waste Management Section SM-9 for additional requirements.

• At minimum contain contaminated material soil by surrounding with impermeable lined berms or cover exposed contaminated material with plastic sheets.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

Fugitive dust control and dust control water:

• Do not over spray water for dust control purposes which will result in runoff from the area.

• Apply water as conditions require.

• Washing down of debris or dirt into drainage, sewage systems, or State waters is not allowed.

• Minimize exposed areas through the schedule of construction activities.

• Utilize vegetation, mulching, sprinkling, and stone/gravel layering to quickly stabilize exposed soil.

• Direct construction vehicle traffic to stabilized roadways.

• Cover dump trucks hauling material from the site with a tarpaulin.

• See Dust Control Section SM-19 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 32)

Concrete truck wash water:

• Disposal of concrete truck wash water via percolation is prohibited.

• Wash concrete-coated vehicles or equipment off-site or in the designated wash area.

• Locate on-site wash area a minimum of 50 feet away or as far as practicable from storm drain inlets, open drainage facilities, or water bodies.

• Runoff from the on-site concrete wash area shall be contained in a temporary pit or level bermed area where the concrete can set.

• Design the area so that no overflow can occur due to inadequate wash area sizing or precipitation.

• The temporary pit shall be lined with plastic to prevent seepage of wash water into the ground.

• Allow wash water to evaporate or collect wash water and all concrete debris in a concrete washout system bin.

• Do not dump liquid wastes into storm drainage system.

• Dispose of liquid and solid concrete wastes in compliance with federal, state, and local standards.

• See Waste Management, Concrete Wash and Waste

Management Section SM-4 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 33)

Sediment track-out:

• A sediment trapping device is required if a wash rack is used in conjunction with the stabilized construction entrance/exit.

• The pavement shall not be cleaned by washing down the street.

• If sweeping is ineffective or it is necessary to wash the streets, wash water must be contained either by construction of a sump, diverting the water to an acceptable disposal area, or vacuuming the wash water.

• Use BMPs for adjacent drainage structures.

• Remove sediment tracked onto the street by the end of the day in which the track-out occurs.

• Restrict vehicle use to properly designated exit points.

• Include additional BMPs that remove sediment prior to exit when minimum dimensions can not be met.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best and submit to HDOT for approval following contract award and before the start of construction

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 33)

Saw-cutting slurry:

• Saw cut slurry shall be removed from the site by vacuuming.

• Provide Perimeter Sediment Controls as applicable.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 34)

Concrete curing water:

• Avoid overspraying of curing compounds.

• Apply an amount of compound that covers the surface, but does not allow any runoff of the compound.

• See California Stormwater BMP Handbook NS-12

Concrete Curing included in SWPPP Attachment A for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract award and before the start of construction

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 34)

Plaster waste water:

• Direct all washwater into a leak-proof container or leak-proof pit. The container or pit must be designed so that no overflows can occur due to inadequate sizing or precipitation.

• Locate on-site wash area a minimum of 50 feet away or as far as practicable from storm drain inlets, open drainage facilities, or water bodies.

• Any significant residual materials remaining on the ground after the completion of construction shall be removed and properly disposed. If the residual materials contaminate the soil, then the contaminated soil shall also be removed and properly disposed of.

• Plaster waste water shall not be allowed to flow into drainage structures or State waters.

• See Material Storage and Handling, SM-2, Stockpile

Management SM-3 and Hazardous Materials and Waste

Management Section SM-9 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract

Reference(s) (Letter #/ Doc. and page #)

Mitigation Measure(s)/Commitment(s) Incorporated Into Bid

Package?

(Where? If not, why?)

Follow-Up Required?

(Expiration/renewal)

Explain.

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 35)

Water-jet wash water:

• For Water-Jet Wash Water used to clean vehicles, use off site wash racks or commercial washing facilities when practical.

• See Vehicle and Equipment Cleaning Section SM-11 for additional information.

• For Water-Jet Wash Water used to clean impervious surfaces, the runoff shall not be allowed to flow into drainage structures or State Waters.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT for approval following contract award and before the start of construction

Contractor Draft Storm

Water Pollution

Prevention Plan

(Page 35)

Sanitary/septic waste:

• Locate Sanitary facilities in a convenient place away from drainage facilities.

• Position sanitary facilities so they are secure and will not be tipped over or knocked down.

• Wastewater shall not be discharged to the ground or buried.

• A licensed service provider shall maintain sanitary/septic facilities in good working order.

• Schedule regular waste collection by a licensed transporter.

• See Sanitary/Septic Waste Section SM-7 for additional requirements.

Water Pollution and

Erosion Control Notes are provided on Sheets

9-11 of Construction

Plans. Contractor directed to comply with

HDOT Highways, Construction Best

Management Practices

Field Manual.

The contractor shall finalize the SWPPP and submit to HDOT…