This is Addendum No. 3 to the sealed bid procurement issued by the Virginia Community College System for the replacement of the roof at Bedford Hall, Central Virginia Community College (Project Code #260-B0260-042/MR20023) in Lynchburg, Virginia. The addendum, dated March 30, 2026, modifies the original bidding documents dated February 13, 2026, and clarifies specifications and adjusts the bid timeline. The project scope encompasses removal of the existing EPDM membrane and built-up asphalt roofing system and installation of approximately 13,880 square feet of new fully adhered EPDM roofing membrane with polyisocyanurate insulation, new roof drains and accessories, asbestos-containing materials removal and disposal, roof hatch replacement, and incidental mechanical and electrical work. A pre-bid conference was held on March 12, 2026, at 11:30 A.M. at Central Virginia Community College (attendance was optional but recommended). The revised bid due date is April 7, 2026, with public bid opening scheduled for April 8, 2026 (originally April 1 and April 2, 2026). Substantial Completion is required within 90 consecutive calendar days from Notice to Proceed, with Final Completion within 30 days thereafter. The contractor must provide a 20-year manufacturer's warranty on roofing materials and a 2-year workmanship warranty.
The addendum clarifies that the existing steel deck is believed to be 1-inch narrow rib with unknown gauge, requiring field verification by bidders of the actual flute pattern, size, and gauge. Section 075323 specifies that EPDM products meeting all technical, single source, and warranty requirements will be acceptable, with bidders responsible for verification of compliance. A Standard Commonwealth Bid Bond (Form CO-10.2) and contract security are required for all bids regardless of amount. Bidders must be registered vendors in eVA, comply with prevailing wage requirements per Virginia Code 2.2-4321.3, and hold appropriate Virginia contractor licensing (Class A or Class B based on contract value). All pay applications and invoices must be processed through the Owner's e-Builder web-based project management software at no cost to the contractor. The contract will be awarded to the lowest responsive and responsible bidder on a lump sum basis, and no specific budget range or award value is disclosed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CVCC – REPLACE ROOF BEDFORD HALL
PC: CVCC 260-B0260-042 MR20023
SFCS – 20301.03
ADDENDUM NO. 3 1
ADDENDUM NO. 3 – MARCH 30, 2026
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated February 13, 2026.
Acknowledge receipt of this Addendum in the space provided on the BID FORM. Failure to do so may subject the Bidder to disqualification.
This Addendum consists of 2 page narrative.
The following items clarify, modify, change, delete from or add to the Contract Documents. When any paragraph, subparagraph, or sub-subparagraph thereof is modified or deleted by this Addendum, the unaltered provisions of that paragraph, subparagraph, sub-subparagraph shall remain in effect.
SPECIFICATIONS:
1. SECTION 070150.19 – PREPARATION FOR REROOFING:
Response:
Existing steel deck is believed to be 1 ½” narrow rib, from existing drawings. Gauge is unknown.
Actual flute pattern, size and gauge of deck shall be field verified by bidders.
2. SECTION 075323 – ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM) ROOFING:
Air Tech Solutions Inc., Alejandra Espinal
CVCC – REPLACE ROOF BEDFORD HALL
PC: CVCC 260-B0260-042 MR20023
SFCS – 20301.03
ADDENDUM NO. 3 2
Response:
Section 075323 is a performance specification. EPDM products that meet all technical, single source and warranty requirements as specified will be acceptable. Verification of compliance with requirements is the responsibility of the bidder.
3. Bid due date has been changed to April 7, 2026, with opening the following day. All other bidding information, including time and location remains unchanged.
END OF ADDENDUM NO. 3