SECTION 02 41 00

DEMOLITION AND DECONSTRUCTION

Section 02 41 00 – Page 1

1.1 GENERAL

This guide specification covers the requirements for demolition, deconstruction, dismantling, and disposal of existing material as a part of new construction work.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)

AASHTO M 145

AASHTO T 180

(1991; R 2004) Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes

(2001; R 2004) Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and an 457-mm (18-in) Drop

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2003) Safety -- Safety and Health Requirements

U.S. DEFENSE LOGISTICS AGENCY (DLA)

DLA 4145.25 (June 2000) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 4000.25-1-M (2006; Notice 1) Requisitioning and Issue Procedures

MIL-STD-129 (Rev P; Notice 3) Military Marking for Shipment and Storage

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (Rev K; Change 1) Obstruction Marking and

1.3 GENERAL REQUIREMENTS

Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes salvage and recycling of materials. Remove rubbish and debris from the project site; do not allow accumulations on the airfield pavements. The work includes demolition, salvage of identified items and

Section 02 41 00 – Page 2 materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily and include sweeping the area to remove foreign object damage potential to aircraft. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 and other applicable Sections.

1.4 SUBMITTALS

The procedures proposed for the accomplishment of demolition work shall be submitted for approval. The procedures shall provide for safe conduct of the work, careful removal and disposition of materials specified to be demolished protection of property which is to remain undisturbed and coordinated with other work in progress and timely disconnection of utility services. The procedures shall include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations.

1.5 REGULATORY AND SAFETY REQUIREMENTS

Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6.

1.6 DUST AND DEBRIS CONTROL

Prevent the spread of dust and debris to occupied portions of the building on airfield pavements and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.

1.7 PROTECTION

1.7.1 Traffic Control Signs

Where pedestrian, driver and aircraft safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind, jet or prop blast. Notify the Contracting Officer prior to beginning such work.

Contractor must provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet 30 meter above ground level. Light construction and installation must comply with FAA AC 70/7460-1. Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.

1.7.3 Items to Remain in Place

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload pavements to

Section 02 41 00 – Page 3 remain. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.7.4 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Before beginning any cutting or demolition work, the contractor shall carefully survey the existing work and examine the drawings and specifications to determine the extent of the work.

The contractor shall take all necessary precautions to insure against damage to existing work to remain in place, to be reused, or to remain the property of the government, and any damage to such work shall be repaired or replaced as approved by the Contracting Officer at no additional cost to the government. The contractor shall carefully coordinate the work of this section with all other work.

1.7.9 Protection of Personnel

Before, during and after the demolition work the Contractor shall continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site.

1.8 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.9 FOREIGN OBJECT DAMAGE (FOD)

Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations.

If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade must include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts. Remove barricade when no longer required.

1.10 RELOCATIONS

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Items to be relocated which are damaged by the Contractor shall be repaired or replaced with new undamaged items as approved by the Contracting Officer.

1.11 ENVIRONMENTAL PROTECTION

All work and contractor's operations shall comply with the requirements of

SECTION 01 35 35: ENVIRONMENTAL PROTECTION.

Comply with the Environmental Protection Agency requirements specified.

1.12 USE OF EXPLOSIVES

Section 02 41 00 – Page 4

Use of explosives will not be permitted.

1.13 AVAILABILITY OF WORK AREAS

Areas in which demolition work is to be accomplished will be available to the contractor

1.14 METHOD OF MEASUREMENT

Measurement will be in cubic yard of concrete slab removed in accordance with these specifications.

1.15 BASIS OF PAYMENT

The quantity of cubic yards of concrete curb removed measure as hereinbefore specified and accepted by the Contracting Officer, or his representative will be paid for at the contract unit price, which payment shall constitute full compensation for all materials, labor, equipment and tools, including all operations necessary to complete the specified work.

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

3.1.1 Utilities and Related Equipment

3.1.1.1 General Requirements

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated.

3.1.1.2 Disconnecting Existing Utilities

Remove existing utilities, as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered that is not indicated on the drawings, the Contracting Officer shall be notified prior to further work in that area. Remove meters and related equipment and deliver to a location on the station in accordance with instructions of the Contracting Officer.

3.1.2 Paving and Slabs

The concrete slabs to be replaced shall be removed full depth completely.

Existing airfield pavements indicated shall be removed to grade, and to permit construction of the new airfield pavements. All slabs replaced shall be constructed to follow the existing slopes of the adjacent slabs and shall meet existing slab grades. Removal of full thickness of existing concrete slabs, and new concrete slabs shall be phased, sequenced and constructed in such a manner that to accommodate Base Operations. In the event of rain, the contractor shall construct barrier berm to intercept the surface runoff

Section 02 41 00 – Page 5 from entering into the excavated area. The contractor shall dewater the excavated area and maintain it dry at all times.

3.1.3 Patching

Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be per Section 32 01 28 Patching of Rigid Pavements

3.2 CONCURRENT EARTH-MOVING OPERATIONS

Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

All materials and equipment removed shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.

3.4 CLEANUP

Remove debris and rubbish from the excavations. Remove and transport the in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

Debris and rubbish shall be removed from the area where airfield pavement removal occurs and reference 3.1.4, Paving and Slabs.

3.5.2 Burning on Government Property

Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.

3.5.3 Removal from Government Property

Section 02 41 00 – Page 6

Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal.

Dispose of waste soil as directed.

-- End of Section --

1.14 METHOD OF MEASUREMENT
1.15 basis of payment

File details come from the government source that posted it. Updated .