DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
This guide specification covers the requirements for general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents, called for in other sections of the specifications.
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals are to be the same as those used in the contract drawings. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals; G
Submittals which are required prior to start of construction (work) issuance of contract notice to proceed, or commencing work on site, or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance Surety bonds List of proposed Subcontractors List of proposed products Construction Schedule Submittal register Health and safety plan Work plan Quality Control (QC) plan Environmental protection plan
SD-02 Shop Drawings; G
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated
SD-03 Product Data; G
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work
Samples of warranty language when the contract requires extended product warranties
SD-04 Samples; G
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged, (if necessary)
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project, (if necessary)
SD-05 Design Data; G
Design calculations, (if necessary) Mix Designs Analyses or other data pertaining to a part of work
SD-06 Test Reports; G
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.) Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates; G
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-08 Manufacturer's Instructions; G
Preprinted material describing installation of a product, system or material, including special notices and (MSDS) concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports; G
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports
SD-10 Operation and Maintenance Data; G
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item. This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals; G
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism. Special requirements necessary to properly close out a construction contract.
For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract
Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD- 01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS (as required by the Contract)
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved; G
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
1.5 PREPARATION
1.5.1 Transmittal Form
Transmit submittals with transmittal form, AF3000, for project. On the transmittal form identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled, "Identifying Submittals," of this section. Submittals maybe sent electronically via email, preferred in a PDF format, if approved by the Contracting Officer.
1.5.2 Identifying Submittals
When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval. Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other subcontractor associated with the submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.
h. Product identification and location in project.
1.5.3 Format for SD-02 Shop Drawings
Shop drawings are not to be less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless other form is required. Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled, "Identifying Submittals," of this section. Number the drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.5.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
Present product data submittals for each section as a complete, bound volume (maybe sent electronically). Include table of contents, listing page and catalog item numbers for product data. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.
Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates. Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM
International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will be accepted for expedition of construction effort. Submit manufacturer's instructions prior to installation.
1.5.5 Format of SD-04 Samples
Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
1.5.6 Format of SD-05 Design Data and SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inches paper. Provide a bound volume for submittals containing numerous pages (maybe send electronically).
1.5.7 Format of SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Provide reports on 8 1/2 by 11 inches paper in a complete bound volume (maybe send electronically). Indicate by prominent notation, each report in the submittal. Indicate specification number and paragraph number to which it pertains.
1.5.8 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in pertinent specification for Operation and Maintenance data for O&M Data format.
1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply Contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
Submit 2 hard copies and an electronic copy of submittals of shop drawings requiring review and approval only by QC organization and two hard copies and an electronic copy of shop drawings requiring review and approval by
1.6.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.6.3 Number of Samples SD-04 Samples
a. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit Two copies of O&M Data to the Contracting Officer for review and approval, where directed.
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals.
Unless otherwise specified, submit two sets of administrative submittals.
1.7 INFORMATION ONLY SUBMITTALS
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe. For design-build construction the Government will retain 1 copy of information only submittals.
1.8 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.8.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP). Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.8.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Is Modified
The normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.9 SUBMITTAL REGISTER
Create the submittal register from the project specification files. Prepare and maintain submittal register, as the work progresses. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required.
1.10 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
e. Period of review for each re-submittal is the same as for initial submittal.
1.11 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received from QC Manager.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
1.11.1 Review Notations
Contracting Officer review will be completed within 10 working days after date of submission. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, re-submittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes.
No work shall proceed for this item until re-submittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.12 DISAPPROVED SUBMITTALS
Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer.
Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense. If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.13 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work. After submittals have been approved or accepted by the Contracting Officer, no re-submittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved. Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested. Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service. Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals, Contractor to replace such materials or equipment to meet contract requirements. Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.
1.15 PROGRESS SCHEDULE
1.15.1 Bar Chart
a. Submit the progress chart, for approval by the Contracting Officer, at the Preconstruction Conference in an electronic copy and 2 hard copies.
b. Prepare the progress chart in the form of a bar chart utilizing form "Construction Progress Chart" or comparable format acceptable to the
c. Include no less than the following information on the progress chart:
(1) Break out by major headings for primary work activity.
(2) A line item break-out under each major heading sufficient to track the progress of the work.
(3) A line item showing contract finalization task which includes punch list, clean-up and demolition, and final construction drawings.
(4) A materials bar and a separate labor bar for each line item. Both bars will show the scheduled percentage complete for any given date within the contract performance period. Labor bar will also show the number of men (man-load) expected to be working on any given date within the contract performance period.
(5) The estimated cost and percentage weight of total contract cost for each materials and labor bar on the chart.
(6) Separate line items for mobilization and drawing submittal and approval. (These items are to show no associated costs.)
d. Update the progress schedule on the electronic copy and two copies every 30 calendar days throughout the contract performance period.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
--End of Section --