CONTRACT_CHANGE_REQUEST.pdf
PDF 32 KB Posted
- Attached to
- 106th and Westfield Water Main Extension
- Solicitation number
- IFB-2026-006
- Issued by
- Hamilton County, Indiana
About this file
This is a Contract Change Request form from the City of Carmel's Board of Public Works and Safety for the 106th and Westfield Water Main Extension project. The form serves as a template for requesting modifications to the construction contract involving the installation of approximately 800 linear feet of 12-inch water main using either open cut or horizontal directional drilling methods. The document provides structured fields for documenting the scope of work changes, reasons for modifications, cost impacts, timeline adjustments, and personnel requirements. The mandatory pre-bid conference is scheduled for Wednesday, April 8, 2026, at 9:00 a.m. at City Hall, with sealed bids due by 9:00 a.m. on Wednesday, April 15, 2026. The project work is expected to commence in May 2026 with substantial completion required by June 30, 2026, pending a Notice to Proceed issued on or before April 15, 2026.
The contract change request form requires identification of cost adjustments to the contract price, determination of whether additional contract time is necessary to complete the work, and specification of any additional personnel needs by trade and duration. The form includes sections for engineer review and recommendations, attachment identification, and sign-off by preparers and reviewers. All work must comply with Indiana Department of Transportation Standard Drawings and Specifications, INDOT Supplemental Specifications, and City of Carmel Standards for Construction and Utility Standard Specifications and Details (2023). The project is funded by the City of Carmel with no specific budget disclosure in procurement documents; however, all bids must be reasonable and not exceed available City funds. Contractors must maintain comprehensive general liability insurance with minimum limits of $6,000,000 general aggregate and $5,000,000 per occurrence, provide performance and payment bonds equal to 100 percent of the contract value, and submit E-Verify compliance documentation at bid submission.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
TO: CONTRACT CHANGE REQUEST NO.:
DATE:
PROJECT NAME:
FROM:
IT IS REQUESTED THAT A CONTRACT CHANGE BE MADE TO THE ABOVE
REFERENCED CONTRACT.
1. SCOPE OF WORK (USE ADDITIONAL PAGES IF REQUIRED. ALSO LIST OTHER
CONTRACTS INVOLVED.)
2. REASON FOR CHANGE:
3. APPROXIMATE COST CHANGE TO CONTRACT PRICE: _____________________
4. WILL THE CONTRACT NEED ADDITIONAL CONTRACT TIME TO COMPLETE
THE CHANGE IN WORK SCOPE? _____ -YES _____ -NO _____ -(CALENDAR
DAYS)
5. WILL THE CONTRACTOR NEED ADDITIONAL PERSONNEL TO COMPLETE
THE CHANGE IN WORK SCOPE? _____ -YES _____ -NO
IF NO, TRADE(S): _____________________________________
NO. OF PERSONNEL: _________________________________
DURATION: ______________________________________
6. IDENTIFICATION OF ATTACHMENTS:
DATE: _______________________ DATE: ________________________
PREPARED
REVIEWED BY:____________ REVIEWED BY:____________________________
ENGINEER
Comments and Recommendation: