WORK_DIRECTIVE_CHANGE.pdf

PDF 48 KB Posted

Attached to
106th and Westfield Water Main Extension
Solicitation number
IFB-2026-006
Issued by
Hamilton County, Indiana

About this file

This is a Work Directive Change form issued by the City of Carmel, Indiana, Board of Public Works and Safety, designed to authorize modifications to an existing contract for the 106th and Westfield Water Main Extension project. The form provides a template for documenting changes to project scope, including specification and drawing references, a detailed description of the modified work, and the reason for the directive change. The form accommodates adjustments to the project completion date, noting whether changes add days, deduct days, or leave the timeline unchanged. The directive change requires approval from the City of Carmel Board of Public Works and Safety, with signatures required from the Presiding Officer (Laura Campbell), board members (James Barlow and Alan Potasnik), the City Engineer (Brad Pease), and the City Clerk (Jacob Quinn).

The Work Directive Change authorizes work to be completed as outlined and indicates that a formal Contract Change Order will be issued to cover associated costs, with a blank field provided for the dollar amount of the change. The document is a standard administrative tool used to manage changes during the execution of the water main extension project, which consists of approximately 800 feet of water main installation using either open cut or directional drilling methods. This form facilitates the tracking and authorization of project modifications while maintaining proper municipal governance and oversight through required Board approvals.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF CARMEL

TO: WORK DIRECTIVE CHANGE NO.______________

DATE: ______________________________________

PROJECT NAME:_____________________________

PROJECT NO.: _______________________________

Specification Reference

Drawing Reference:

DESCRIPTION OF WORK COVERED BY THIS DIRECTIVE CHANGE:

REASON FOR THIS ORDER:

AUTHORIZATION:

THIS WORK DIRECTIVE CHANGE AUTHORIZES THE WORK TO BE COMPLETED AS

OUTLINED. A Contract Change Order in the amount of $______________ will be issued to you in the near future to cover this Work Directive Change.

PROJECT COMPLETION DATE: ADD/DEDUCT/UNCHANGED ___________ DAYS.

By:_______________________________ Approved By:

Owner’s Representative

CITY OF CARMEL

BOARD OF PUBLIC

WORKS AND SAFETY

By:__________________________

Laura Campbell, Presiding Officer

By:__________________________ James Barlow, Member

By:__________________________ Alan Potasnik, Member

By:__________________________ Brad Pease, PE, City Engineer

DATE:_______________________

ATTEST:

DATE:_______________________

Jacob Quinn, Clerk