This is a Request for Proposal Change form issued by the City of Carmel, Indiana for the 106th and Westfield Water Main Extension project. The document serves as a formal request for contractors to submit proposals regarding proposed modifications to an existing contract. Contractors are required to submit their proposals within fifteen (15) calendar days of the request date and must include four (4) copies of detailed breakdowns showing quantities, costs of materials, equipment, labor, overhead, and profit, as well as the basis for any requested additional time. The proposal must address the effect of the proposed change on both Substantial Completion and Final Completion dates. The underlying project involves the installation of approximately 800 feet of water main utilizing either open cut or directional drilling methods, with sealed bids originally due by 9:00 am on Wednesday, April 15, 2026, through the City's e-Procurement Portal.
The change request explicitly states that submission of a proposal does not authorize the contractor to proceed with the proposed work or stop previously scheduled work. A Contract Change Order and Notice To Proceed will only be issued upon approval of the proposal. Contractors should clearly state in their proposals any impacts to project completion timelines. The specific proposal due date, engineer approval, and owner's representative approval are to be completed by the City of Carmel at the time of issuance.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
TO: REQUEST FOR PROPOSAL NO
DATE:
PROJECT NAME:
PROJECT NO.:
Specification Reference:
Drawing Reference: _____________ Drawing Date:____________
Identification of Attachments:
Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any.
DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST:
REASON FOR CHANGE:
SPECIAL INSTRUCTIONS:
THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK
NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract Change Order and a Notice To Proceed will be issued.
Please state in your proposal the effect the acceptance of this Request will have on the Project’s Substantial Completion and Final Completion, if accepted within ___ days of proposal due date.
YOUR PROPOSAL DUE DATE: _____________________________________
By: _____________________________________ _________________ Engineer Date