About this file
This is a Request for Quotation (RFQ) document issued by the West Virginia Department of Health and Human Resources (DHHR), Office of Health Facilities, for a camera and digital video recorder (DVR) system installation at Jackie Withrow Hospital in Beckley, West Virginia. The project requires vendors to supply and install a new camera/DVR system covering all exterior doors of the facility. The scope includes providing 25 total cameras, with 22 to be installed and 3 retained as replacements for damages or malfunctions. All cameras must be exterior-rated, weather-proof units with 1080p HD or greater resolution capable of capturing a minimum 180-degree view. The system must include plenum-rated Cat-5 cabling and support a minimum of 30 days of recording capacity. A mandatory pre-bid conference will be held to provide specific camera location details. The contract will be awarded to the lowest qualified responsible bidder and includes a 2-year parts and labor warranty, excluding weather-related or vandalism damages, with guaranteed next-business-day technician response for service calls during the warranty period.
Vendors must submit pricing on a lump-sum basis for both the installation and the 2-year warranty on the pricing page included in the solicitation. Bidders must demonstrate a minimum of three successfully completed similar projects and possess a valid West Virginia contractor's license. Vendors are responsible for obtaining all necessary permits and licenses, performing all final cleanup activities, and designating a primary contract manager available during normal business hours. All work must be performed during standard hours (Monday through Friday, 8 a.m. to 5 p.m.), with any outside-hours work requiring advance agency approval and no additional compensation. The specifications explicitly prohibit the use of existing unused facility cable, requiring all new plenum-rated cabling for the installation.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION
ARFQ JWH23*1 Camera/DVR system for JWH
GENERAL CONSTRUCTION SPECIFICATIONS (No AIA Documents)
1. PURPOSE AND SCOPE: The West Virginia Dept of Health and Human Resources (DHHR), Office of Health Facilities (OHF), is currently soliciting bids to establish a contract for the following:
The purchase and installation of a new Camera/DVR system to cover all the exterior doors of Jackie Withrow Hospital located at 105 S Eisenhower Dr. Beckley, WV 25801
The Vendor shall furnish all materials, labor, and equipment necessary to complete all Construction Services. The Vendor shall furnish any incidental work, materials, labor, and equipment that are necessary to complete the Construction Services, even if such incidental work is not explicitly included in the Project Plans.
The DHHR has a website that can be viewed at https://dhhr.gov/office-of-drug-control-policy/news/documents/eeo/%20utilization%20report%20completed%form%201-29-final%pdf%20review%20for%approval%20to%20submit%283%.29.pdf
2. DEFINITIONS: The terms listed below shall have the meanings assigned to them below. Additional definitions can be found in section 2 of the General Terms and Conditions and in the Project Plans as defined below.
2.1 “Construction Services” means the purchase and installation of a new Camera/DVR System as more fully described in the Project Plans.
2.2 “Pricing Page” means the pages contained in wvOASIS, attached hereto as Exhibit A, or included in the Project Plans upon which Vendor should list its proposed price for the Construction Services.
2.3 “Solicitation” means the official notice of an opportunity to supply the State with Construction Services that is published.
2.4 “Project Plans” means documents developed by an architect, an engineer, the Agency, or another design professional, which are attached hereto as Exhibit B, that provide detailed instructions on how the Construction Services are to be performed. In the event that Project Plans contain drawings or other documents too large to attach in Exhibit B, Vendors can obtain copies in accordance with Section 9 of these Specifications.
3. ORDER OF PRECEDENCE: This General Construction Specifications document will have priority over, and supersede, anything contained in the Project Plans.
4. QUALIFICATIONS: Vendor, or Vendor’s staff if requirements are inherently limited to individuals rather than corporate entities, shall have the following minimum qualifications:
4.1. Experience: Vendor, or Vendor’s supervisory staff assigned to this project, must have successfully completed at least 3 projects that involved work similar to that described in these specifications or the Project Plans. Compliance with this experience requirement will be determined prior to contract award by the State through references provided by the Vendor upon request, through knowledge or documentation of the Vendor’s past projects, through confirmation of experience requirements from the architect assisting the State in this project, or some other method that the State determines to be acceptable. Vendor must provide any documentation requested by the State to assist in confirmation of compliance with this provision. References, documentation, or other information to confirm compliance with this experience requirement may be requested after bid opening and prior to contract award.
4.2. WV Contractor’s License
5. CONTRACT AWARD: The Contract is intended to provide Agency with a purchase price for the Construction Services. The Contract will be awarded to the lowest qualified responsible bidder meeting the required specifications. If the Pricing Pages contain alternates/add-ons, the Contract will be awarded based on the grand total of the base bid and any alternates/add-ons selected.
6. SELECTION OF ALTERNATES: Pursuant to W. Va. Code § 5-22-1(f), any solicitation of bids shall include no more than five alternates. Alternates, if accepted, shall be accepted in the order in which they are listed on the bid form. Any unaccepted alternate contained within a bid shall expire 90 days after the date of the opening of bids for review. Determination of the lowest qualified responsible bidder shall be based on the sum of the base bid and any alternates accepted.
7. PERFORMANCE: Vendor shall perform the Construction Services in accordance with this document and the Project Plans.
8. SUBSTITUTIONS: Any substitution requests must be submitted in accordance with the official question and answer period described in the INSTRUCTIONS TO VENDORS SUBMITTING BIDS, Paragraph 4. Vendor Question Deadline. Vendors submitting substitution requests should submit product brochures and product specifications during the official question and answer period.
9. PROJECT PLANS: The checked box will apply to Project Plans for this solicitation.
X No Additional Project Plan Documents: There are no additional Project Plans other than those attached hereto as Exhibit B or any subsequent addenda modifying Exhibit B.
10. CONDITIONS OF THE WORK
10.1. Permits: The Vendor shall procure all necessary permits and licenses to comply with all applicable Federal, State, or Local laws, regulations and ordinances of any regulating body.
10.2. Existing Conditions: If discrepancies are discovered between the existing conditions and those noted in the specifications, Vendor must immediately notify the Agency's representative. Vendor must also immediately notify the Agency if suspected hazardous materials are encountered.
10.3. Standard Work Hours: The standard hours of work for this Contract will be Monday thru Friday 8a to 5p excluding holidays recognized by the State of West Virginia. Any work outside of the standard hours of work must be approved in advance at the Agency’s sole discretion. Authorization of work outside of the standard hours of work will not entitle Vendor to additional compensation.
10.4. Project Closeout: Project Closeout shall include the following:
10.4.1. Final Cleanup: Vendor shall perform the final cleanup activities listed below, along with any other final cleanup activities normally associated with the work performed under this Contract, prior to final inspection:
10.4.1.1. All work areas where work performed must be cleaned and free of any debris after each day completed. Vendors tools must be taken with them after each shift is completed, the facility cannot store vendor property on the premises.
10.4.2. Final Inspection: Vendor shall participate in a final inspection with the Agency’s project manager. The purpose of the final inspection will be to identify deficiencies that need to be remedied prior to Agency’s final acceptance of the work. Vendor shall at all times be obligated to perform in accordance with the Contract and must take all actions necessary to ensure that work complies with requirements of Contract prior to final acceptance. Final acceptance does not waive or release Vendor from its obligation to ensure that work complies with the Contract requirements. Vendor shall submit any warranty documents to the Agency project manager at final inspection.
11.2 11.3 11.4
11. FACILITIES ACCESS: Performance of Contract Services may require access cards and/or keys to gain entrance to Agency’s facilities. In the event that access cards and/or keys are required:
8.
9.
10.
11.
12.
11.1. Vendor must identify principal service personnel which will be issued access cards and/or keys to perform service.
11.2. Vendor will be responsible for controlling cards and keys and will pay replacement fee, if the cards or keys become lost or stolen.
11.3. Vendor shall notify Agency immediately of any lost, stolen, or missing card or key.
11.4. Anyone performing under this Contract will be subject to Agency’s security protocol and procedures.
11.5. Vendor shall inform all staff of Agency’s security protocol and procedures.
12. MISCELLANEOUS:
12.1. Contract Manager: During its performance of this Contract, Vendor must designate and maintain a primary contract manager responsible for overseeing Vendor’s responsibilities under this Contract. The Contract manager must be available during normal business hours to address any customer service or other issues related to this Contract. Vendor should list its Contract manager and his or her contact information below.
Contract Manager: _________________________________________________
Telephone Number: ________________________________________________
Fax Number: ______________________________________________________
Email Address: ____________________________________________________
EXHIBIT A – Pricing Page
| Item |
| Unit |
| Total |
To provide all parts, materials, labor, travel, and any other associated fees for the successful installation of a new Camera/DVR system as outlined in Exhibit B Project Plans
| Lump sum |
| $ |
| 2 year warranty |
| Lump sum |
| $ |
| Grand total |
| $ |
Vendor: ______________________________________________________ Address: _____________________________________________________________ Contact name and title: _____________________________________________________ Email: _____________________________________________ Signature: _________________________________________ Date: ____________________________
EXHIBIT B – PROJECT PLANS
1) Vendor must provide all parts, materials, labor, and any other associated fees for the installation of a new Camera/DVR system for Jackie Withrow Hospital
2) Vendor must supply a total of 25 cameras. 22 of them are to be installed and 3 will be left at the facility to replace any for damages or any malfunction. Locations of where the cameras need to be installed will be given at the Mandatory pre-bid conference.
3) Cameras must be exterior (weather- proof) rated as they will be placed on the exterior of the building
4) Camera must have a 1080p HD view or greater and must pick up a minimum of 180 degrees
5) Cable used must be plenum rated cat-5 and must be new for the cameras and/or power supply. No existing un-used cable in the facility can be used for this project.
6) Memory for the system must have a minimum of 30 days recording.
7) If the vendor needs to remove any cable, cameras, or anything from the existing system, they are permitted to do so, but it must be left with the facility.
8) System must have a minimum 2 year parts and labor warranty excluding any weather related or vandalism damages. During the warranty period if a service call is placed, vendor must ensure a technician is on-site the next business day.