This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (DEP) for Contract No. PL513, Task Assignment 405, dated December 15, 2025. The contractor is Florida State University's Florida Natural Areas Inventory (FNAI), represented by Frank Price, with DEP Contract Manager Sine Murray overseeing the assignment. The change order maintains the original contract terms with no modifications to the task amount or completion timeline.
Task Assignment 405 involves updates and enhancements to the Florida Ecological Greenways Network (FEGN), a critical data layer supporting conservation priorities for the Florida Forever program. FNAI, in collaboration with the University of Florida Center for Landscape Conservation Planning (CLCP) through a subcontract, will refine Florida Forever Strategic Priorities, provide quarterly updates to GIS data layers, and conduct statewide boundary and priority reviews. The total task assignment value is $88,290.00, consisting of FNAI direct costs of $34,213, a UF subcontract of $40,105, off-campus rent of $5,946, and indirect costs at 10% totaling $8,026. Deliverables are scheduled quarterly from October 2025 through June 2026, with invoice amounts of $22,072 for Q1, Q2, and Q3 updates, and $22,074 for the annual update. The task period extends from September 12, 2025, through June 12, 2026, funded through Organization Code 37102400000 under Fund Category 423001.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
OOO-012 (Effective 09-14-2015) Page 1 of 2
Required Signatures: Adobe Signature
Contract Number: Task Assignment Number: Date: Change Order No.
Contractor Name:
Contractor Representative:
DEP Contract Manager:
Description of Change (Use additional sheets if necessary):
Change in Task Amount Item Cost Reimbursement Fee Schedule Total Original Task Amount:
Task amount prior to this change order:
Net increase/decrease in task amount:
Task amount with all change orders:
Change in Task Time Original task completion date:
Completion date prior to this change:
Net increase/decrease in task period:
Completion date with all change orders:
PL513 405 12/15/2025 1
Florida State University/Florida Natural Areas Inventory
Frank Price Sine Murray
$88,290.00 See attached $88,290.00
$88,290.00 $88,290.00
$88,290.00 See attached $88,290.00
6/12/2026
6/12/2026
6/12/2026
This change order is to update the schedule and budget for this task.
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
OOO-012 (Effective 09-14-2015) Page 2 of 2
Change in Funding Information
Budget Entity
Org. # EO Fund Category / Year
Obj. Project Grant Amount
TOTAL:
CONTRACTOR FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Cont Date
Contract Manager Signature Date
APPROVED:
Bureau Chief Signature Date
Budget Representative Signature Date
Contractual Authority Signature Date cc: Procurement Section (MS93) Bureau of Finance & Accounting (MS78) - 2 copies
Contract Manager Signature Date
37100400 37102400000 QH 423001 084108/26 139900 80047 $88,290.00
Digitally signed by Frank Price Date: 2025.12.16 11:15:39 -05'00'
$88,290.00
Digitally signed by Sine A Murray Date: 2025.12.16 10:44:02 -05'00' 12/16/25
Digitally signed by Sine A Murray Date: 2025.12.16 10:44:11 -05'00' 12/16/25
Jill Buckley Digitally signed by Jill Buckley Date: 2025.12.16 11:06:43 -05'00'
Bryan Bradner Digitally signed by Bryan Bradner Date: 2026.01.06 08:14:05 -05'00'
Taylor Dearman for Stacey Patterson/VPR
Digitally signed by Taylor Dearman for Stacey Patterson/
VPR
Date: 2025.12.17 09:40:20 -05'00'
Deliverable Submission date Invoice due date
Invoice amount
FFSP Q1 and Q2 update
Oct 10, 2025
Jan 15, 2026
Oct 17, 2025
Jan 22, 2026
$22,072
$44,144
FFSP Q2 update Dec 12, 2025 Dec 19, 2025
$22,072
FFSP Q3 update Final FEGN 2026 update, including updated base boundary and as outlined in Task 3
Mar 13, 2026
Mar 20, 2026
$22,072
FFSP Annual update including new data and methods
June 5, 2026
June 12, 2026
$22,074
TOTAL TASK ASSIGNMENT VALUE:
Org Code EO Object Code Fund Category Year Grant # Module/OCA Project # Amount
FLORIDA DEPARTMENT OF ENVIRONMENTAL
PROTECTION
Date
CONTRACTOR
Contract Manager
Contractual Authority
Date
Contract Manager
APPROVED:
Task Manager
Budget Representative
Contractual Authority
TASK ASSIGNMENT NOTIFICATION FORM
DEP CONTRACT NO. PL513
FEE SCHEDULE FIXED PRICE TOTAL TASK ASSIGNMENT VALUE
Task Assignment Number: _______________________________________ Date: _____________________
Contractor: ___________________________________________________________________________________
Contractor Contract Manager: __________________ __ Phone Number:
DEP Contract Manager: ______________________________________ Phone Number: __________________
Task Description (Use additional sheets if necessary): _________________________________________________
Final Deliverables and Due Dates: _________________________________________ ______________________
Performance Measures: ______________ ________________________________________________
Financial Consequences: _______ _______________________________________________________________
Term of Task Assignment: _ _____________________________________________________________________
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Date
Date
Date
Date
$ 88,290.00
37102400000 139900 084108 26 $ 88,290.00
10/06/2025
10/14/2025
09/12/2025
09/12/2025
PL513 - Task Assignment 405 - Updates and Enhancements to the Florida Ecological Greenways Network
The Florida Ecological Greenways Network (FEGN) is a key data layer and map that informs conservation priorities for the Florida Forever program. Like all data in the Florida Forever Conservation Needs Assessment, the FEGN requires regular updates and refinement to remain relevant to conservation decisions. Updates to component data sources as well as changes in the landscape due to new development and newly acquired conservation lands all necessitate regular review and update of conservation priorities. The FSU Florida Natural Areas Inventory (FNAI) will work with the UF Center for Landscape Conservation Planning (CLCP) on enhancements and updates to the Florida Ecological Greenways Network to support prioritization and decision-making in the Florida Forever program. This work will include both one-time activities to be accomplished in the current fiscal year, and ongoing activities that are expected to continue beyond this year, as noted further below. FNAI will subcontract and collaborate with CLCP in this effort and accomplish the following activities:
1. Refine FEGN Florida Forever Strategic Priorities (FFSP) - In collaboration with CLCP, FNAI will further refine the Florida Forever Strategic Priorities first developed in the 2021 FEGN update. Florida Forever Strategic Priorities are designed to further prioritize the FEGN into finer classes to aid decision-making at the scale of individual Florida Forever project acquisitions. This activity will include:
Incorporate new CLC version 4 land cover update.
Incorporate updates to FEGN basemap and priorities completed or in progress as of August 2025.
Revise interior corridor buffers to better reflect edge effect penalties.
Evaluate revisions to priorities for FEGN corridors that are effectively connected and/or completed.
Work with CLCP to review the Peace River-Myakka River prioritization model as a potential source of additions or revisions to the FEGN Strategic Priorities model.
Work with CLCP to review the statewide FEGN P1-P5 corridor prioritization as a potential source of additions or revisions to the FEGN Strategic Priorities model. Collaborate with CLCP to review and refine critical bottlenecks to better identify a smaller subset for inclusion in the FFSP. This will include a focused review of small critical gaps that run through relatively intensive land uses.
2. Quarterly Updates of Florida Forever Strategic Priorities – For each quarter of FY 25/26, FNAI will provide DEP with updates of the Florida Forever Strategic Priorities GIS data layer. These updates primarily will address priorities affected by changes to conservation lands boundaries due to additional land acquisitions as well as significant land use changes. No changes will be made to overall FEGN priorities in these updates; updates will solely be made to strategic priorities within existing FEGN priority classes.
3. Review and update FEGN model and conduct boundary updates for priorities in the vicinity of Florida Forever projects and conservation lands – CLCP, as a subcontract with FNAI, will finalize statewide revisions to the FEGN base boundary and priorities to complete a 2026 FEGN update in time for incorporation into the final Strategic Priorities update for the contract period. This will include the following tasks:
Incorporate CLC version 4 land cover updates into FEGN base boundary and remove recently developed lands.
Finalize base boundary and priorities updates to sub-regions including Peace River/Myakka River watersheds, the Santa Fe River corridor, Northeast Florida, and other corridors previously under review.
Collaborate with FNAI to review and refine critical bottlenecks to better identify a smaller subset for inclusion in the FFSP, as noted under Activity 1 above. This will include a focused review of small critical gaps that run through relatively intensive land uses.
Schedule and budget
Deliverable Submission date
Invoice due date
Invoice amount
FFSP Q1 update Oct 10, 2025 Oct 17, 2025 $22,072
FFSP Q2 update Dec 12, 2025 Dec 19, 2025 $22,072
FFSP Q3 update Final FEGN 2026 update, including updated base boundary and priorities as outlined in Task 3
Mar 13, 2026 Mar 20, 2026 $22,072
FFSP Annual update including new data and methods outlined in Activity 1
June 5, 2026 June 12, 2026 $22,074
BUDGET SUMMARY
FNAI Direct Costs $34,213 UF Subcontract $40,105 Off-campus Rent $5,946 Indirect @10% $8,026
TOTAL $88,290