This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (DEP) under Indefinite Delivery Vehicle (IDV) contract PL513. The contractor is Florida State University/Florida Natural Areas Inventory (FNAI), with Frank Price serving as the Contractor Contract Manager and Sine Murray as the DEP Contract Manager. Task Assignment Number 303 was executed on June 20, 2024, and is effective from July 1, 2024, through June 15, 2025.
The scope of work encompasses five activities related to Florida Forever Measures Data Layers Maintenance and Reporting: (1) providing Project Comparative Analysis Tables using F-TRAC and Single Resource Rank analyses in PDF and Excel formats for ARC ranking meetings; (2) revising, updating, and developing three to seven resource layers related to Florida Forever goals, including posting updated GIS data and providing hosted feature services with metadata; (3) delivering Natural Resource Acquisition Progress Reports, benchmark progress analyses, and routine documentation of data updates; (4) coordinating with resource experts and stakeholders through meetings and maintaining the Florida Forever Conservation Data Viewer web tool; and (5) updating the ARC Florida Forever Project Ranking Tool Excel Spreadsheet. The total task assignment value is $85,700.00, payable through two invoices due January 15, 2025 ($36,870) and June 16, 2025 ($48,830), subject to a 10% negotiated overhead rate. Funding is allocated from Florida's budget as follows: Org Code 37102400000, Object Code 139900, Fund Category 423001, Category 084108, Year 23, Project 80047, in the amount of $85,700.00.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOTAL TASK ASSIGNMENT VALUE:
Org Code EO Object Code Fund Category Year Grant # Module/OCA Project # Amount
FLORIDA DEPARTMENT OF ENVIRONMENTAL
PROTECTION
Date
CONTRACTOR
Contract Manager
Contractual Authority
Date
Contract Manager
APPROVED:
Task Manager
Budget Representative
Contractual Authority
TASK ASSIGNMENT NOTIFICATION FORM
DEP CONTRACT NO. PL513
FEE SCHEDULE FIXED PRICE TOTAL TASK ASSIGNMENT VALUE
Task Assignment Number: _______________________________________ Date: _____________________
Contractor: ___________________________________________________________________________________
Contractor Contract Manager: __________________ __ Phone Number:
DEP Contract Manager: ______________________________________ Phone Number: __________________
Task Description (Use additional sheets if necessary): _________________________________________________
Final Deliverables and Due Dates: _________________________________________ ______________________
Performance Measures: ______________ ________________________________________________
Financial Consequences: _______ _______________________________________________________________
Term of Task Assignment: _ _____________________________________________________________________
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Date
Date
Date
Date
$ 85,700.00
37102400000 QH 139900 423001 084108 23 80047 $ 85,700.00
07/09/2024
PL513 – Task Assignment 303 – Florida Forever Measures Data Layers Maintenance and Reporting
Activity 1 – F-TRAC and Single Resource Rank Analyses for ARC
At least 4 weeks prior to the scheduled ARC ranking meeting, FNAI will provide a "Project Comparative Analysis Table" on new proposals and existing Florida Forever projects using the F- TRAC and Single Resource Rank analyses in Adobe Acrobat® (pdf) format and Microsoft Excel® (xlsx) format for distribution to ARC members and staff and will post it on the web. The analysis will be based on existing and proposed boundaries as they exist two weeks prior to the October ARC meeting. All documents to be posed to the web shall comply with section 508 of the Rehabilitation Act of 1973, which addresses standards for electronic information (https://www.access-board.gov/ict/).
Activity 2 – Data Maintenance, Updates, Revisions
FNAI will revise, update and/or develop a subset of resource layers related to Florida Forever goals and measures. FNAI will consult with the DEP Contract Manager to determine which layers to be updated or developed based on newly available information, guidance from the Florida Forever Expert Advisory Group (see activity 4, below) and/or the needs of the Division of State Lands. FNAI will update or develop at least 3 and up to 7 resource layers during the fiscal year; the total number of layers will be agreed upon by FNAI and the Contract Manager. FNAI also will continue assisting with updates of statewide land cover that will then be used to update the extent and prioritization of other resource data layers. FNAI will submit biannual progress reports and ArcGIS® files of data updates to allow DEP to track and evaluate improvement. Following substantive updates of any Florida Forever data layers, FNAI will: (a) post updated GIS data layers on its website, including GIS protocols used for the revisions/updates/new subsets of resource layers and notify the DEP's Contract Manager about each revised/updated/new GIS data layer; and (b) annually provide DEP's Contract Manager with updated DEP Acquisition Triage Resource GIS data layers. FNAI will provide these layers as hosted feature services with metadata including methodology and data sources.
Activity 3 – Florida Forever Progress Reporting and Documentation
At least three weeks before the December ranking of the Florida Forever list by ARC, FNAI will provide: (a) a Natural Resource Acquisition Progress Report (NRAP) in Adobe Acrobat® (pdf) format (section 508 compliant) for distribution to ARC members and staff and for posting on its website and in Microsoft Excel® (.xlsx) format for the CONTRACT MANAGER. In addition, FNAI will provide (b) a benchmark progress analysis in .xlsx format for the CONTRACT MANAGER; and
(c) routine documentation of data updates biannually.
Activity 4 – Coordination with Experts and Stakeholders
FNAI will convene resource experts as needed to advise on methods and inputs used in the Florida Forever Conservation Needs Assessment. Following guidance of the group and in consultation with the DEP Contract Manager, FNAI will evaluate and explore alternative
Details for PL513 - Task Assignment #203 (continued) methods, conduct sensitivity analyses, and document final methodology, including a description of GIS protocols.
As needed and in consultation with the DEP Contract Manager, FNAI will coordinate and participate in meetings to inform DEP staff as well as stakeholders such as ARC, the public, and others about the Florida Forever Conservation Needs Assessment data and analyses.
Deliverables will include agenda, meeting summaries and presentation materials. In addition, FNAI will update & maintain the Florida Forever Conservation Data Viewer web tool and explore new tools to facilitate data review by experts and project review by DEP, ARC staff and the public.
Activity 5 – Update DEP ARC Florida Forever Project Ranking Tool
FNAI will make incremental revisions to the design of the ARC Florida Forever Project Ranking Tool Excel Spreadsheet based on feedback from ARC members and DEP staff. At least 4 weeks prior to the December 2023 ARC ranking meeting, FNAI will update the spreadsheet with latest data for all measures in coordination with DEP staff, and provide the updated Tool for distribution to ARC in advance of the December ranking meeting. The update will be based on existing and proposed boundaries as they exist two weeks prior to the October ARC meeting.
Activity schedule and costs (Work done under this Task is subject to the negotiated overhead rate of 10% as specified in the master agreement PL513.).
Activity Payment Amount
Invoice Date
Total Payment
1 Project Comparative Analysis Table (.xlsx & .pdf)
$8,410 1/15/2025
$8,410
2(a) Updated FF GIS Layers on Web $52,985 6/16/2025 $52,985
2(b) Updated Triage GIS layers $2,597 1/15/2025 $2,597
3(a) Updated NRAP (.xlsx & .pdf) $2,474 1/15/2025 $2,474
3(b) Benchmark Progress Analysis (.xlsx)
$1,546 6/16/2025
$1,546
3(c) Documentation of data updates $1,670 1/15/2025 &
6/16/2025 $3,340
4 Coordination with Experts and Stakeholders
$7,669 6/16/2025
$7,669
5 Updated DEP ARC Ranking Tool $6,679
1/15/2025 $6,679
Total Task Assignment $85,700
Invoices shall be submitted electronically by 1/15/2025 and by 6/17/2025. Invoices should be sent to the DEP CONTRACT MANAGER, Sine Murray(Sine.Murray@FloridaDEP.gov) and to Amy Horton (Amy.Horton@FloridaDEP.gov)
Details for PL513 - Task Assignment #203 (continued)
All invoices shall include the corresponding reporting period.
(For Example: Reporting Period: July 1, 2024 –December 31, 2024).