About this file

This is a Task Assignment Notification Form for DEP Contract No. PL513, executed between the Florida Department of Environmental Protection (DEP) and Florida State University's Florida Natural Areas Inventory (FNAI). The task assignment was dated July 22, 2024, with a contract term extending from July 22, 2024, through June 30, 2025. The contractor's contract manager is Frank Price (850-224-8207), and the DEP contract managers are Sine Murray and Rebecca Armstrong (850-245-2773). The document was approved by DEP officials including Task Manager Rebecca Armstrong, Budget Representative Amy Horton, and Contractual Authority Callie DeHaven.

Task Assignment 306 encompasses five distinct deliverables for the Florida Park Service Bureau of Natural and Cultural Resources totaling $308,834.00. The scope includes: (1) development of a template and invasive plant management plans for selected state parks ($144,700); (2) invasive plant surveys across 46,500 acres in five DRP districts at $3.00 per acre or $200 per acre for areas requiring boat access, with a maximum of $135,000; (3) one-day compliance inspection training for DRP staff ($7,600); (4) maintenance and updates to an Arthropod Control Plan Web Map ($5,184); and (5) a survey for Conradina cygniflora at Dunn's Creek State Park including a report and GIS data ($8,750). All invoices must be submitted by June 15, 2025, with a final invoice deadline of June 20, 2025. The contract utilizes a Fixed Price structure with a total not-to-exceed amount of $308,834.00, funded through Org Code 37500500000, Object Code 139900, under Fund Category 675005.

View the file

Other files

File Type Posted
CN-370000-PL513-T103.pdf PDF
CN-370000-PL513-T108.pdf PDF
CN-370000-PL513-T202CO3.pdf PDF
CN-370000-PL513-T203.pdf PDF
CN-370000-PL513-T204CO2.pdf PDF
CN-370000-PL513-T208.pdf PDF
CN-370000-PL513-T303.pdf PDF
CN-370000-PL513-T404.pdf PDF
CN-370000-PL513-T405.pdf PDF
CN-370000-PL513.pdf PDF
CN-370000-PL513-GMC1.pdf PDF
CN-370000-PL513-T102.pdf PDF
CN-370000-PL513-T104.pdf PDF
CN-370000-PL513-T104CO1.pdf PDF
CN-370000-PL513-T109.pdf PDF
CN-370000-PL513-T202.pdf PDF
CN-370000-PL513-T204.pdf PDF
CN-370000-PL513-T209.pdf PDF
CN-370000-PL513-T304.pdf PDF
CN-370000-PL513-T401.pdf PDF
CN-370000-PL513-T105.pdf PDF
CN-370000-PL513-T106.pdf PDF
CN-370000-PL513-T107.pdf PDF
CN-370000-PL513-T203CO1.pdf PDF
CN-370000-PL513-T204CO1.pdf PDF
CN-370000-PL513-T207.pdf PDF
CN-370000-PL513-T301.pdf PDF
CN-370000-PL513-T302CO1.pdf PDF
CN-370000-PL513-T305.pdf PDF
CN-370000-PL513-T405CO1.pdf PDF
CN-370000-PL513-T406.pdf PDF
CN-370000-PL513-T101.pdf PDF
CN-370000-PL513-T201.pdf PDF
CN-370000-PL513-T202CO1.pdf PDF
CN-370000-PL513-T202CO2.pdf PDF
CN-370000-PL513-T202CO4.pdf PDF
CN-370000-PL513-T205.pdf PDF
CN-370000-PL513-T206.pdf PDF
CN-370000-PL513-T302.pdf PDF
CN-370000-PL513-T401.pdf.crdownload CRDOWNLOAD file
CN-370000-PL513-T402.pdf PDF
CN-370000-PL513-T403.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOTAL TASK ASSIGNMENT VALUE:

Org Code EO Object Code Fund Category Year Grant # Module/OCA Project # Amount

FLORIDA DEPARTMENT OF ENVIRONMENTAL

PROTECTION

Date

CONTRACTOR

Contract Manager

Contractual Authority

Date

Contract Manager

APPROVED:

Task Manager

Budget Representative

Contractual Authority

TASK ASSIGNMENT NOTIFICATION FORM

DEP CONTRACT NO. PL513

FEE SCHEDULE FIXED PRICE TOTAL TASK ASSIGNMENT VALUE

Task Assignment Number: _______________________________________ Date: _____________________

Contractor: ___________________________________________________________________________________

Contractor Contract Manager: __________________ __ Phone Number:

DEP Contract Manager: ______________________________________ Phone Number: __________________

Task Description (Use additional sheets if necessary): _________________________________________________

Final Deliverables and Due Dates: _________________________________________ ______________________

Performance Measures: ______________ ________________________________________________

Financial Consequences: _______ _______________________________________________________________

Term of Task Assignment: _ _____________________________________________________________________

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

Date

Date

Date

Date

306 07/22/2024

Florida State University/ Florida Natural Areas Inventory

Frank Price 850-224-8207

Sine Murray / Task Manager - Rebecca Armstrong 850-245-2773

FNAI Invasive Plant Management Plans and Surveys

See attached Details for 306

See attached Details for 306

See attached Details for 306

7/22/2024 through 6/30/2025

$ 308,834.00

37500500000 X2 139900 675005 100718 00 NA U1650 NA $ 308,834.00

Digitally signed by Frank Price Date: 2024.07.25 13:43:23 -04'00'

Kathy Pennington for Stacey Patterson

Digitally signed by Kathy Pennington for Stacey Patterson Date: 2024.08.01 08:52:55 -04'00'

Digitally signed by Sine A Murray Date: 2024.07.25 12:27:09 -04'00'

Rebecca Armstrong

Digitally signed by Rebecca Armstrong Date: 2024.07.25 13:18:06 -04'00'

Amy Horton Digitally signed by Amy Horton Date: 2024.07.25 12:46:48 -04'00'

Callie DeHaven Digitally signed by Callie DeHaven Date: 2024.08.02 11:56:12 -04'00'

DDEP PL513-Task Assignment 306 Scope of Work

FL Natural Areas Inventory

Summary

This Scope of Work describes five separate tasks to be completed by the Florida Natural Areas Inventory (FNAI) for the Florida Park Service Bureau of Natural and Cultural Resources (BNCR) during FY2025 to support land management activities in Florida State Parks.

Task 1: Development of draft invasive plant management plans for Florida State Parks

FNAI will augment DRP staff management planning capacity and help to foster the development of institutional memory through staff transitions by developing park specific plans for upland invasive plant management.

1.1. Template invasive management plan development.

In consultation with DRP, FNAI will develop a Word document template with instructions for developing invasive plant management plans for Florida state parks. The template will include a summary page listing projected treatment acreage and costs for the coming five years based on median contracted treatments costs for similar projects.

The following schedule will be followed by FNAI and DRP:

o Sept 1, 2024: FNAI will provide the initial template management plan draft o Sept 15, 2024: DRP will provide comments to FNAI o Sept 30, 2024: FNAI will provide a final draft template to DRP

1.2. Invasive plant management plans

FNAI will use the template created above to develop invasive plant management plans for selected Florida State Parks (see cost schedule below for specific parks) Plan development may include any of the following tasks as FNAI determines is necessary:

o Targeted surveys or site inspections o Consultation with DRP staff at the park or district level o Review of aerial photography, LiDAR, and other remotely sensed data o Review of existing invasive plant data and treatment history in DEP NRTS or other sources DRP will respond to any FNAI data requests related to management plan development within two weeks and if DRP isn’t able to provide the requested materials, FNAI will proceed with plan development without the requested materials. DRP will have a month to review an initial draft of each plan and provide comments before FNAI finalizes the draft to be delivered per this contract.

These plans will address the management of upland and selected occurrences of emergent invasive plants that can be mapped and managed on foot. Submerged aquatic plant management is outside of FNAI’s area of expertise, would need to involve consideration of downstream property owners/users, and is often controversial.

TTask 2: Invasive plant surveys to plan contracted treatment

The intent of this sampling effort is to delineate priority areas for invasive plant treatment within Florida State Parks so that DRP can develop contract specifications for the management of these areas.

Surveys will be conducted as follows:

FNAI will develop a survey plan by reviewing existing invasive plant occurrence and treatment data in NRTS, EDDMapS, and iNaturalist, examining aerial photography and LiDAR to identify areas of development and disturbance, and briefly consulting with the park/district biologist. Surveys will proceed in accordance with the survey plan, targeting areas previously documented or suspected of containing concentrations of invasive plant species. Areas with low invasive plant cover will be lightly surveyed, while areas with high invasive plant cover will be surveyed more thoroughly to collect data necessary to identify and delineate areas for treatment of particular species or groups of species. These surveys will be conducted so as to efficiently identify priority areas for treatment. They are not guaranteed to identify every occurrence or concentration of invasive plants. Any estimates of invasive plant cover that FNAI provides will be based on visual estimates, not quantitative methods. Survey completion will be assessed by FNAI staff based on their professional judgement.

FNAI will provide results in the form of invasive plant polygons in an ESRI ArcGIS Pro compatible File Geodatabase. Each polygon will be attributed with a comma delimited species list, the survey date, and the name of the surveyor.

Surveys will be distributed among the five DRP districts according to the table below:

District Total acres Percent of Total FNAI Cost

1 0 0% 0

2 5,000 11% $15,000

3 15,000 33% $45,000

4 17,000 38% $51,000

5 8,000 18% $24,000

Total 46,500 100% $135,000

Task 3: Compliance inspection training

FNAI staff will provide a single day of training for DRP staff, split between field and office, in the methods used to conduct invasive plant treatment compliance (effectiveness) inspections for the FWC Uplands Invasive Plant Management Section.

Topics covered will include:

Post-treatment inspection timing Inspection planning using contractor tracks Determining treatment effectiveness in the field Common errors/omissions observed Minimum acreage to be inspected

TTask 4: Arthropod Control Plan Web Map

FNAI will maintain a web map to provide a single public access point for current Mosquito Control District (MCD) Arthropod Control Plans (ACP).

Add plans as pdfs to parks already on map (up to 15 plans will be added) Make minor changes (symbology, etc.) based on BNCR staff input.

Task 5: Survey for Conradina cygniflora on Dunn’s Creek State Park

There is currently only one sustainable population (representing 18 source features or discrete sites) of Dunns false rosemary known and all sites occur within Dunns Creek State Park. FNAI proposes to revisit the known occurrences to update records and survey all habitat (approximately 1000 acres of mostly scrub with a small portion of sandhill in which Dunns false rosemary is known to occur) that has received land management activities since the original 2004 survey for new individuals. Data gathered at the known sites will include location (latitude, longitude, township, range, and section), status and condition of populations, habitat characteristics, and management. If new populations are found, information on population size, status and condition, vegetative associates, management needs, and threats to long-term viability will be gathered. Sightings of additional rare species will also be recorded where possible.

Data on existing occurrences will be updated in the FNAI Natural Heritage Database and new occurrences will be incorporated.

The main objectives of this project are to: 1) conduct a survey of Dunns false rosemary in Dunns Creek State Park by revisiting all known extant and historical populations, expand searches for new plants/populations in sites that are receiving active land management activities such as sand pine (Pinus clausa) thinning and removal and prescribed fire, and determine population size and 2) compare the population size documented in this survey to a survey that was conducted in 2004 by FNAI (2004).

Budget and Schedule:

The Contractor shall submit all invoices by June 15, 2025 to DEP Contract Manager, Sine Murray and Amy Horton.

Task Deliverable Date of Submission Total Payment

1.1 Template invasive management plan development Sep 30, 2024 $7,600

1.2

Invasive plant management plans

D1: Maclay (Ravines portion)- $15,500

D2: Paynes Prairie - $36,400 D3: Kissimmee Prairie Preserve

State Park (portion)- $36,400 D3: Wekiwa Springs State Park-

$36,400 D5: Oleta State Park - $20,000

May 15, 2025 for delivery of initial drafts to

DEP

Jun 15, 2025 for delivery of final drafts to

DEP

$144,700

Invasive plant surveys to plan contracted treatment Dec 15, 2024 up to $135,000

$3.00/acre of Management Zone to be surveyed.

$200/ac for management zones requiring boat access

Water bodies may be removed from acreage to reduce cost.

3 Compliance inspection training Jun 15, 2025 $7,600

4 Arthropod Control Plan Web Map with functionality specified above Jun 15, 2025 $5,184

Survey for Conradina cygniflora on Dunn’s Creek State Park

1. A brief report summarizing efforts, population size, and a comparison of the population size in 2004.

2. GIS data including:

File geodatabase of all rare plants observed during survey, including population counts for Dunn’s false rosemary, File geodatabase of incidental rare animals and invasive exotic

Dec 15, 2024 $8,750 plants observed during the survey.

MAXIMUM TOTAL FOR ALL ACTIVITIES IN TASK 306 NOT TO

EXCEED: $308, 834

All invoices shall include the reporting period covered for the invoice amount billed.