This document is a Task Assignment Notification Form (DC017F) issued by the Florida Department of Environmental Protection (FDEP) under Contract HW558 with Earth Systems, a private environmental engineering contractor. The task assignment authorizes work at the Adams Cleaners site (ERIC_5013) located at 2525 East South Street, Orlando, Florida. The contract manager is Crystal Posey, and the contractor representative is Jim Paxton. The assignment falls under the Monitoring phase of the project, with oversight from FDEP's Bureau of Waste Cleanup.
The task assignment authorizes Earth Systems to conduct annual groundwater sampling and monitoring of natural attenuation (MNA) activities, including sampling from well MW010 and gauge wells MW002, MW004, MW007, MW008, MW009, MW011, and MW012. Samples will be analyzed for volatile organic compounds (VOHs) using EPA Method 8260, with one trip blank included. The deliverable is an Annual Groundwater Monitoring Report and ADaPT/GIS update, due March 31, 2020, with final project completion by June 1, 2020. The total fixed-price assignment value is $4,694.67, allocated as $402.77 for Subtask 1 (Project Management) and $4,291.90 for Subtask 2 (Annual MNA Sampling and Reporting). Costs include direct labor, overhead, general and administrative expenses, fringe benefits, travel, laboratory analysis, field equipment, and a completion fee. Invoice submission requires FDEP approval of the Annual Groundwater Monitoring Report and ADaPT/GIS update prior to payment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW558 Task Assignment #: DC017F
Deliverables:
Deliverable Deliverable Due Date Annual Groundwater Monitoring Report and ADaPT/GIS update (submitted electronically and hardcopy)
31-Mar-20
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced Subtasks 1 and 2: FDEP approval of Annual Groundwater Monitoring Report and ADaPT/GIS update (submitted electronically and hardcopy)
$4,694.67
TOTAL COST $4,694.67
BWC TAFORM 01/18
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Noah Valenstein Secretary
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 3
2399-2400
Memorandum
TO:
FROM:
SUBJECT:
DATE:
HW558 Contract File
Crystal Posey, Project Manager
Adams Cleaners
ERIC_5013
HW558 DC017F
Task Assignment
October 16, 2019
This Task Assignment authorizes Earth Systems to conduct annual groundwater sampling (with water level data) from MW011 and gauge wells MW002, MW004, MW007, MW008, MW009, MW011, and MW012. MW011 and one trip blank will be analyzed for VOHs using EPA Method 8260.
DO017F was modified by technical staff to reduce the amount of samples to only one sample (MW010), based on previous groundwater sampling data. The task assignment's negotiated cost was reduced by $578.73.
Earth Systems will provide an Annual Monitoring of Natural Attenuation Report, which will include updated tables and figures, the laboratory analytical data, and recommendations for additional work.
This Task Assignment is in accordance with the Earth Systems scope of work and cost estimate form attached and dated October 9,2019.
The cost of this Task Assignment is $4,694.67.
FDEP COST ESTIMATEContractor: Earth Systems
Date: 10/16/2019
Task #: SubTask 1 Project Management SubTask 6
Site: Adams Cleaners SubTask 2 Annual MNA Sampling 2020 SubTask 7
Activity/Phase: Annual MNA Sampling SubTask 3 SubTask 8
Project Manager: Crystal Posey SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.62 Project Manager (Paxton) 3 3.4 $42.30 Principal Manager Beardall P.G. 2 2 0 0 0 0 0 0 0 0 $40.62 Project Manager (Paxton) 18 18 0 0 0 0 0 0 0 0
$0.00 Senior Engineer/Geologist/Scientist 0 0 0 0 0 0 0 0 0 0 $32.70 Associate Eng. 0 0 0 0 0 0 0 0 0 0
$0.00 Staff Engineer/Geolgist/Scientist 0 0 0 0 0 0 0 0 0 0 $23.02 Senior Technician (Byrnes) 10 10 0 0 0 0 0 0 0 0 $26.15 Field Geologist (Russell) 0 0.0 0.0 0.0 0.0 0 0 0 0 0
$0.00 Technician/Draftsperson I 0 0 0 0 0 0 0 0 0 0 $18.00 Technician/Draftsperson II (Morse) 2 2 0 0 0 0 0 0 0 0 $17.00 Administrative Assistant (Meserve) 1 1 0 0 0 0 0 0 0 0
$0.00 General Office Clerk 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 36 3 33.0 0.0 0.0 0.0 0 0 0 0 0
Direct Labor $1,236.33 $137.37 $1,098.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 63.00% $778.88 $86.54 $692.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 65.00% $803.61 $89.29 $714.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 34.00% $420.36 $46.71 $373.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,239.18 $359.91 $2,879.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $61.82 $6.87 $54.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel
REV: 02/03 CEF EARTH SYSTEMS Page 1
FDEP COST ESTIMATEContractor: Earth Systems
Date: 10/16/2019
Task #: SubTask 1 Project Management SubTask 6
Site: Adams Cleaners SubTask 2 Annual MNA Sampling 2020 SubTask 7
Activity/Phase: Annual MNA Sampling SubTask 3 SubTask 8
Project Manager: Crystal Posey SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $136.00 $136.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $233.00 $233.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $132.00 $132.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $132.00 $132.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $557.75 $557.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $114.50 $114.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $704.75 $704.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,370.75 $366.78 $4,003.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $323.92 $35.99 $287.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $4,694.67 $402.77 $4,291.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF EARTH SYSTEMS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Adams Cleaners SUBTASK: 2 Annual MNA Sampling 2020
DATE: 10/16/2019
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager - J. Paxton Schedule job and notify off-site property owners 2
Senior Tech. - T. Byrnes Travel time to and from site (2.5 hrs each way) 5 Senior Tech. - T. Byrnes Day 1 Redevelop well MW010 (Deep GW Sampling Kit) Overnight stay 2
Day 2 Collect GW sample from well MW010. Analyses for VOHs via 8260C. Purge water 3 treated and disposed onsite as non-haz per generator's knowledge. 1 Trip Blank VOHs Gauge wells MW002, 004, 007, 008, 009, 011 and 0012.
Report:
G Beardall - Principal Manager. Annual MNA report review 2 J Paxton - Project Manager Annual MNA report preparation 16 S. Meserve - Admin Compiling PDF of MNA report, printing and shipping hard copy 1 Kath Morse - Drafting Figures 1-3 2
TOTAL LABOR 33.0
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Sample Shallow GW sampling kit $208.55 day 1 $208.55 Develop Deep GW Sampling Kit $349.20 day 1 $349.20
IDW Portable Compressor $48.50 day 1 $48.50 IDW Expendables $32.50 day 1 $32.50 IDW Portable Generator $66.00 day 1 $66.00
TOTAL EQUIPMENT $704.75
VEHICLE TYPE RATE UNIT USEAGE
Truck $97.00 day 1 $97.00
TOTAL VEHICLE $97.00
PER DIEM STAFF RATE UNIT USEAGE
Sr. Tech - Terry Byrnes - Meals $36.00 per day 1 $36.00 Sr. Tech - Terry Byrnes - Hotel $100.00 per day 1 $100.00
TOTAL PER DIEM $136.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
1 well, 1 TB, VOH by 8260B $66.00 1 1 $132.00
TOTAL LAB $132.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
FINAL --7/24/96
223 12th Avenue North, Jacksonville Beach, Florida 32250, Tel 904.247.0740, Fax 904.247.7650
Florida • Colorado • North Dakota • New Jersey
October 9, 2019
Ms. Crystal Posey Bureau of Waste Cleanup Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road, M. S. 4520 Tallahassee, Florida 32399-2400
Subject: Proposal to Conduct Annual MNA Sampling Adams Cleaners 2525 East South Street, Orlando, Florida FDEP No. ERIC_5013
Dear Ms. Posey:
Earth Systems has prepared this proposal for conducting annual Monitoring of Natural Attenuation (MNA) sampling at the subject site. The tasks associated with this scope of work are as follows:
SUBTASK 1 – Project Management
Allowable costs for Project Management according to the Bureau of Waste Cleanup’s (BWC) contract with Earth Systems.
SUBTASK 2 – Annual MNA Sampling and Reporting
Earth Systems will mobilize a senior technician to the site to re-develop well MW010. The next day Earth Systems will collect a groundwater sample (with water level data) from well MW010 and gauge wells MW002, MW004, MW007, MW008, MW009, MW011, and MW012. The samples will be analyzed for VOHs using EPA Method 8260. One trip blank will also be analyzed. All VOH samples will be analyzed by one of Earth Systems contract laboratories, Pace Analytical.
If the groundwater analytical results are below GCTLs, Earth Systems will submit a TACO to complete another round of groundwater sampling to achieve No Further Action.
After receipt of the analytical results, Earth Systems will provide an Annual Monitoring of Natural Attenuation Report. The report will include updated tables and figures, the laboratory analytical data, and recommendations for additional work.
Proposal to Annual MNA Sampling Adams Cleaners, Orlando, Florida FDEP Facility No. ERIC_5013
Note that this sampling will be conducted as a “milk run” by combining it with a sampling event at the nearby Sunland Cleaners site. Combining the two sampling events will reduce the cost of mobilizing to the Orlando area. In this proposal, Earth Systems requests 2.5 hours to mobilize from Jacksonville to Adams Cleaners and one night of per diem. Earth Systems will sample Sunland Cleaners the next business day.
Task Proposed
Cost Proposed Schedule/Deliverables
Subtask 1 – Project Management $402.77 May 31, 2020
Subtask 2 – 2020 MNA GWS Sampling
$4,291.90 March 31, 2020 Submittal of MNA Report.
Total/Completion Date $4,694.67 May 31, 2020
If you have questions or comments concerning this proposal, please contact me at (904) 247-0740.
Sincerely, James Paxton Operations Manager