Task Assignment Summary

This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under DEP Contract No. HW558. The task assignment authorizes Earth Systems, a contractor specializing in environmental engineering services, to conduct annual groundwater monitoring activities at the Concord Custom Cleaners #045 site located at 1940-77 North Monroe Street, Tallahassee, Leon County, Florida. The assignment was executed in December 2020 and is managed by FDEP's Killian Talley, with Jim Paxton serving as the contractor's representative.

The scope of work consists of two subtasks: Project Management and Annual Groundwater Sampling and Reporting. Subtask 1 allocates $450.58 for project management oversight based on total direct labor hours. Subtask 2, valued at $4,387.29, encompasses groundwater sampling from four monitoring wells (MW001, MW002, MW003, and MW005), depth-to-water measurements from six additional wells, field parameter collection, analysis of four groundwater samples for volatile organic compounds via EPA Method 8260B, and preparation of a comprehensive Groundwater Monitoring Report. The total task assignment value is $4,837.87 with 42 labor hours, structured as a fixed-price task type with no retainage. The final deliverable—a Natural Attenuation Monitoring Report and GIS/ADaPT documentation—was due October 14, 2021, with task completion scheduled for December 17, 2021. Invoicing is contingent upon FDEP receipt and approval of the monitoring report, at which time the full contract amount becomes due.

View the file

Other files

File Type Posted
CN-370000-HW558-A3.pdf PDF
CN-370000-HW558-A5.pdf PDF
CN-370000-HW558-A7.pdf PDF
CN-370000-HW558-CO2.pdf PDF
CN-370000-HW558-DC001G.pdf PDF
CN-370000-HW558-DC005G.pdf PDF
CN-370000-HW558-DC005i.pdf PDF
CN-370000-HW558-DC012FCO.pdf PDF
CN-370000-HW558-DC013F.pdf PDF
CN-370000-HW558-DC017E.pdf PDF
CN-370000-HW558-DC017F.pdf PDF
CN-370000-HW558-DC017H.pdf PDF
CN-370000-HW558-DC018C.pdf PDF
CN-370000-HW558-DC019F.pdf PDF
CN-370000-HW558-DC019H.pdf PDF
CN-370000-HW558-DC01ACO4.pdf PDF
CN-370000-HW558-DC01E.pdf PDF
CN-370000-HW558-DC01F.pdf PDF
CN-370000-HW558-DC022D.pdf PDF
CN-370000-HW558-DC023F.pdf PDF
CN-370000-HW558-DC025B.pdf PDF
CN-370000-HW558-DC027G.pdf PDF
CN-370000-HW558-DC028A.pdf PDF
CN-370000-HW558-DC028F.pdf PDF
CN-370000-HW558-DC02C.pdf PDF
CN-370000-HW558-DC02E.pdf PDF
CN-370000-HW558-DC02EC01.pdf PDF
CN-370000-HW558-DC02L.pdf PDF
CN-370000-HW558-DC03J.pdf PDF
CN-370000-HW558-DC03L.pdf PDF
CN-370000-HW558-DC04G.pdf PDF
CN-370000-HW558-DC04J.pdf PDF
CN-370000-HW558-DC04L.pdf PDF
CN-370000-HW558-DC04MCO1.pdf PDF
CN-370000-HW558-DC05C.pdf PDF
CN-370000-HW558-DC08ECO1.pdf PDF
CN-370000-HW558-DC09GCO1.pdf PDF
CN-370000-HW558-DC09H.pdf PDF
CN-370000-HW558-DC09I.pdf PDF
CN-370000-HW558-DC09ICO1.pdf PDF
CN-370000-HW558-DC09ICO2.pdf PDF
CN-370000-HW558-DC10E.pdf PDF
CN-370000-HW558-DC11G.pdf PDF
CN-370000-HW558-DC11GCO1.pdf PDF
CN-370000-HW558-DC11GCO2.pdf PDF
CN-370000-HW558-DC11H.pdf PDF
CN-370000-HW558-DC11J.pdf PDF
CN-370000-HW558-DC11MCO1.pdf PDF
CN-370000-HW558-DC11oCO1.pdf PDF
CN-370000-HW558-DC12B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93)

Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW558

D000 N/ADC027E

Earth Systems

Jim Paxton

850-245-8928Killian Talley

ERIC_4870

Concord Custom Cleaners #045

1940-77 North Monroe Street, Tallahassee, Leon

Monitoring

This Task Assignment authorizes Earth Systems to conduct annual groundwater monitoring activities in accordance with the attached scope of work and cost estimate.

Natural Attenuation Monitoring Report; GIS/ADaPT

10/14/2021

12/17/2021

$ 4,837.87 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Killian Talley Digitally signed by Killian Talley Date: 2020.12.15 13:56:12 -05'00'

Killian Talley Digitally signed by Killian Talley Date: 2020.12.15 13:56:24 -05'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2020.12.16 12:24:37 -05'00'

Mark A. Tumeo Digitally signed by Mark A. Tumeo Date: 2020.12.17 13:12:20 -05'00'

$ 4,837.87

Task Assignment Notification/Change Order

Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtasks 1-2: Submittal of Natural Attenuation Monitoring Report; GIS/ADaPT 10/14/2021

Subtasks 1-2: FDEP receipt and approval of Natural Attenuation Monitoring Report;

GIS/ADaPT $ 4,837.87

$ 4,837.87

HW558

DC027E

Florida Department of Memorandum Environmental Protection

Printed on recycled paper.

To: HW558 Contract Negotiation File Concord Custom Cleaners #045 Tallahassee, Leon County

ERIC_4870

From: Killian Talley, Project Manager Date: December 15, 2020 Subject: Negotiation Summary

HW558 DC027E

Task Assignment authorizes Earth Systems to conduct annual groundwater monitoring at the Concord Custom Cleaners #045 site.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.

Subtask 2: Annual Groundwater Sampling & Reporting Subtask includes costs and labor for Earth Systems to conduct groundwater sampling along with analysis and reporting. Field event will be comprised of the following activities; collection of depth to water will be measured from site monitoring wells, field parameters for geochemical data, and four (4) groundwater samples for analysis of volatile organic compounds via EPA Method 8260B. Upon receipt of the groundwater analytical data, Earth Systems will generate a Groundwater Sampling Report outlining and describing the field event, procedures, and analytical results. The report will also provide conclusion and recommendations.

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $4,837.87with 42 labor hours.

Earth Systems may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

Cost Estimate Contractor: Earth Systems

Date: 12/15/2020

Task #: SubTask 1 Project Management SubTask 6

Site: Concord Cleaners #045 SubTask 2 Annual Groundwater Sampling and Reporting SubTask 7

Activity/Phase: SubTask 3 SubTask 8

Project Manager: Killian Talley SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.62 Principal Manager (Paxton) 4 3.8 $42.30 Principal Manager (Tumeo) 2 2 0 0 0 0 0 0 0 0 $40.62 Project Manager (Paxton) 18 18 0 0 0 0 0 0 0 0 $38.46 Senior Eng/Geologist (Payne) 3 3 0 0 0 0 0 0 0 0 $20.43 Senior Technician (Mojock) 9 9 0 0 0 0 0 0 0 0 $24.27 Eng./Geologist 0 0 0 0 0 0 0 0 0 0 $18.00 Technician/Draftsperson II (Morse) 4 4 0 0 0 0 0 0 0 0 $17.00 Administrative Assistant (Meserve) 1 1 0 0 0 0 0 0 0 0 $25.44 Eng./Geologist (Russell) 1 1 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 42 4 38 0 0 0 0 0 0 0 0

Direct Labor $1,383.13 $153.68 $1,229.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 63.00% $871.37 $96.82 $774.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 65.00% $899.03 $99.89 $799.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 34.00% $470.26 $52.25 $418.01 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,623.79 $402.64 $3,221.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $69.15 $7.68 $61.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Annual GW Monitoring 2021

Cost EstimateContractor: Earth Systems

Date: 12/15/2020

Task #: SubTask 1 Project Management SubTask 6

Site: Concord Cleaners #045 SubTask 2 Annual Groundwater Sampling and Reporting SubTask 7

Activity/Phase: SubTask 3 SubTask 8

Project Manager: Killian Talley SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Annual GW Monitoring 2021

Travel Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $330.00 $330.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $330.00 $330.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $208.55 $208.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $114.50 $114.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $355.55 $355.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $4,475.49 $410.32 $4,065.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $362.38 $40.26 $322.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $4,837.87 $450.58 $4,387.29 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Concord Cleaners #045 SUBTASK: Annual Groundwater Sampling and Reporting

DATE: ########

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Brooke Payne -Project Manager Coordinate activities 3

M. Mojock - Senior Technician Travel time to and from site 1

WLs & GW Samples (MW001, MW002, MW003, and MW005), plus trip blank. Analyses for V 8 via 8260B. Purge water treated and disposed on-site as non-haz per generator's knowledge.

WLs only from 6 wells (MW004, MW006, MW007, MW009, through MW011)

Report:

M. Tumeo - Principal Manager Annual MNA report review 2

J Paxton- Project Manager Annual MNA report preparation 18

L. Russell - Field Geologist ADaPT 1

S Meserve - Admin Compiling PDF of MNA report, printing and shipping hard copy 1

Kath Morse - Drafting Figures 1-4 4

TOTAL LABOR 38.0

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Shallow GW sampling kit $208.55 day 1 $208.55

Portable Compressor $48.50 day 1 $48.50

Expendables $32.50 day 1 $32.50

Portable Generator $66.00 day 1 $66.00

TOTAL EQUIPMENT $355.55

VEHICLE TYPE RATE UNIT USEAGE

Truck $97.00 day 1 $97.00

TOTAL VEHICLE $97.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

4 wells, 1 TB, VOH by 8260B $66.00 4 1 $330.00

$0.00

$0.00

TOTAL LAB $330.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

TOTAL $0.00

FINAL --7/24/96

223 12th Avenue North, Jacksonville Beach, Florida 32250, Tel 904.247.0740, Fax 904.247.7650

Florida • Colorado • North Dakota • New Jersey

December 3, 2020

Mr. Killian Talley Bureau of Waste Cleanup Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road, M. S. 4520 Tallahassee, Florida 32399-2400

Subject: Proposal for Annual Groundwater Monitoring - 2021 Concord Custom Cleaners #045 1940-77 North Monroe Street, Tallahassee, Florida

ERIC_4870

Dear Mr. Talley:

Earth Systems has prepared this proposal for conducting annual Monitoring of Natural Attenuation (MNA) sampling at the subject site. The tasks associated with this scope of work are as follows:

SUBTASK 1 – Project Management

Allowable costs for Project Management according to the Bureau of Waste Cleanup’s (BWC) contract with Earth Systems.

SUBTASK 2 – Annual Groundwater Sampling and Reporting

Earth Systems will mobilize a Senior Technician to the site to collect groundwater samples from 4 wells (MW001, MW002, MW003, and MW005). In addition, depth to water measurements will be collected in 6 wells (MW004, MW006, MW007, MW009 through MW011) to determine a groundwater contour map of the area. The groundwater samples will be analyzed for VOHs using EPA Method 8260. One trip blank will also be analyzed.

All VOH samples will be analyzed by one of Earth Systems’ contract laboratories, Pace or Accutest. Annual groundwater sampling activities will be conducted on August 30, 2019, in consistency with the annual sampling frequency.

After receipt of the analytical results, Earth Systems will provide a Groundwater Monitoring Report. The report will include updated groundwater tables, figures, laboratory analytical data, and recommendations for additional work.

Proposal for Confirmatory Soil Sampling and Groundwater Monitoring Concord Custom Cleaners #45, Tallahassee, Florida FDEP Facility No. 37-9502169 / ERIC_4870

Cost and Schedule

The proposed cost and schedule for this project are provided in the table below.

Task Proposed

Cost Proposed Schedule/Deliverables

Subtask 1 – Project Management $450.58

December 13, 2021

Subtask 2 – Annual Groundwater Sampling August 2021

$4,387.29

October 14, 2021

Total/Completion Date $4,837.87

December 13, 2021

If you have questions or comments concerning this proposal, please contact me at (904) 247-0740.

Sincerely, James Paxton Operations Manager