CLEANUP SPECS Farnsworth #1 (002).docx
DOCX document 32 KB Posted
- Solicitation number
- ARFQ 0313 DEP2100000057 2
- Issued by
- Webster County, West Virginia
About this file
This is a Technical Specifications document prepared by the West Virginia Department of Environmental Protection, Office of Oil and Gas, for the remediation and reclamation of the Farnsworth #1 well site located at 542 Goose Creek Road in Wirt County, West Virginia (API #47-105-80305). The scope of work requires the successful contractor to provide equipment, materials, labor, and professional services to remove contaminants associated with the oil and natural gas well and reclaim all disturbed land in accordance with West Virginia Code 22-6 and the West Virginia Erosion and Sediment Control Field Manual. Work items include excavation and disposal of contaminated soil, installation of 24-inch diameter corrugated plastic conductor casing, operation of a minimum 3-inch trash pump for wastewater transfer, application of crushed limestone gravel, disposal of liquid waste at a licensed Underground Injection Control facility, installation and removal of silt fence, application of topsoil, site reclamation with lime, fertilizer, seed and mulch, and supply of oil absorbent materials including booms (minimum 10 feet long), absorbent pads (minimum 2 feet by 2 feet), and peat sorb in 50-pound bags. The contractor will be responsible for all required manifesting and documentation, with copies submitted to the Office of Oil and Gas for record-keeping purposes.
Pricing for the project is organized by individual line items with various billing structures: excavation and disposal of soil is bid by the ton based on landfill weight tickets; conductor casing is bid by the foot; the trash pump is bid by the hour; gravel is bid by the ton; liquid waste disposal is bid by the barrel; silt fence is bid by the foot including installation and removal labor; topsoil is bid by the ton including trucking and application; and site reclamation is a lump sum for all materials and labor. Oil absorbent booms are bid per unit, absorbent pads are bid by the bundle, and peat sorb is bid per 50-pound bag. The contractor must obtain soil sampling confirmation from Office of Oil and Gas personnel before backfill operations commence, with expedited turnaround time to be used for laboratory results.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WEST VIRGINIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
OFFICE OF OIL AND GAS
COUNTY
OF
Wirt
NAME OF PROJECT
Farnsworth #1 / Reclamation
API #47-105-80305
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
| SECTION | PAGE | |
| I. | SPECIAL PROVISIONS | |
| I. Location/Site Description | 3 | |
| II. Scope of Work | 4 | |
| II. | TECHNICAL SPECIFICATIONS | |
| 1.0 | Excavation and Disposal of Soil | 5 |
| 2.0 | Conductor Casing | 5 |
| 3.0 | Trash Pump | 5 |
| 4.0 | Gravel | 5 |
| 5.0 Disposal of Liquid Waste | 6 | |
| 6.0 Silt Fence | 6 | |
| 7.0 Topsoil | 6 |
8.0 Site Reclamation……………………………………………………………6
9.0 Oil Absorbent Supplies 6
Farnsworth #1
REMEDIATION PROJECT
API #47-105-80305
I. SPECIAL PROVISIONS
1.0 Location/Site Description
Located at 542 Goose Creek Road, Wirt County The GPS location is as follows: 477789.2E, 4358800.1N UTM17 NAD83 Directions to site:
From the Charleston Area:
Take I-77 N towards Parkersburg. Take Exit 174. At the bottom of the ramp turn left onto Route 47 east toward Freeport, go approximately 16 miles. Turn left off onto Goose Creek Road (County Road 2/1) travel north on Goose Creek 6/10 mile. The site is on the right. The entrance is at a green farmgate. From there the well is 3/10 mile.
Approaching from the Parkersburg Area:
Take I-77 S to exit 174 Staunton Ave/WV-Rte.47. Turn left on Rte. 47 E and follow the directions above to the well site.
II. SCOPE OF WORK
The successful bidder shall provide appropriate equipment, materials, labor and professional services for the removal of contaminants associated with the oil and natural gas well(s) and the reclaiming of all land disturbed in association with the removal operations in accordance with West Virginia Code § 22-6 (http://code.wvlegislature.gov/22-6/) and the West Virginia Erosion and Sediment Control Field Manual. The General Performance Standards (GPS) shall apply to all items. The work to be performed will include the following items listed in the technical specifications.
The contractor will be responsible for removing contaminated soil around the well bore. Once they determine that all contaminated soil has been removed, Office of Oil and Gas personnel will conduct soil sampling to confirm. Expedited turnaround time will be used. No backfill will be completed until results indicate that all contaminants have been removed.
II. TECHNICAL SPECIFICATIONS
1.0 Excavation and Disposal of Soil
Description Excavation and disposal of all solid waste generated from the site will be the responsibility of the contractor. This will include all manifesting required by law. Copies of all documents will be submitted to the Office of Oil and Gas for record keeping purposes. Excavation and disposal will be bid by the ton from landfill weight tickets and will include all labor and equipment including mobilization and demobilization needed to complete the project.
2.0 Conductor Casing
Description The conductor pipe purchased will be made of corrugated plastic and include delivery cost and setting around the well bore. Conductor pipe will be purchased by the foot and must be twenty-four (24) inches in diameter. This includes equipment and labor to install at the site.
3.0 Trash Pump
The trash pump must be a minimum of three (3) inches (inlet and outlet diameters) with all hoses and fittings included. This is used to transfer wastewater. The trash pump will be bid by the hour.
4.0 Gravel
Gravel will be crushed limestone. Gravel will be bid by the ton and will include trucking and application.
5.0 Disposal of Liquid Waste
Disposal of liquid waste generated from the site will be disposed of at a licensed Underground Injection Control (UIC) facility. Proper manifesting and disposal are the responsibility of the contractor. Copies of all documents will be submitted to the Office of Oil and Gas for record keeping purposes. Liquid waste disposal will be bid by the barrel.
6.0 Silt Fence
Description
Silt Fence will have stakes pre-attached and will be installed in accordance with provisions contained in the West Virginia Erosion and Sediment Control Field Manual May 2012: https://dep.wv.gov/oil-and- gas/Documents/Erosion%20Manual%2004.pdf Silt fence will also be removed at the completion of reclamation. Silt fence will be bid by the foot and include the labor to install and remove.
7.0 Topsoil
Topsoil will be needed to bring the surface location back up to elevation, and to ensure proper vegetation of the site. Topsoil shall be bid by the ton and includes trucking to site and equipment and labor to distribute.
8.0 Site Reclamation
Site reclamation includes lime, fertilizer, seed and mulch used and applied in accordance to provisions contained in the West Virginia Erosion and Sediment Control Field Manual May 2012: https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.. The bid will be a lump sum for the materials and labor needed to complete site reclamation.
19.0 Oil Absorbent Supplies
Oil Absorbent Supplies are used to absorb and contain oil as directed by the DEP.
0. Booms will be bid per boom; booms must be a minimum of ten (10) feet long.
0. Absorbent pads will be bid by the bundle, pads must be a minimum of two (2) feet by two (2) feet.
0. Peat sorb will be bid per fifty (50) pound bag.