This is a price schedule for dockside availability services for the USCGC NORTHLAND (WMEC-270A) during fiscal year 2026, covering the period of August 3, 2026 through September 27, 2026. The schedule outlines 24 definite line items and multiple option items related to vessel maintenance and repair work, including engine cleaning and maintenance, heat exchanger servicing, tank inspection and preservation, piping renewal, deck plating replacement, and system valve renewal. Each item is priced on a job or unit basis with quantities specified (primarily 1 job per line item), though the actual unit prices are not populated in this draft version of the document.
The pricing schedule includes provisions for composite labor rates (hourly), a government-furnished property report (NSP—not separately priced), and travel and per diem costs. The document also establishes the framework for over-and-above or growth work, with labor rates and material markup/handling fees to be applied if additional work is added via contract modification during the contract's life. The schedule indicates that 5 laydays are budgeted for the performance period. All extended prices currently display as $0.00, indicating this is a draft document awaiting completion of pricing information by the contractor.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: |
| USCGC NORTHLAND (WMEC-270A) DOCKSIDE AVAILABILITY FY2026 |
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Flexible Couplings, Renew | JOB | 1 | ||
| D-002 | Seawater Heat Exchangers, Clean, Inspect And Hydro | JOB | 1 | ||
| D-003 | Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean | JOB | 1 | ||
| D-004 | Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean | JOB | 1 | ||
| D-005 | Lube Oil Heat Exchangers; Clean, Inspect And Hydro | JOB | 1 | ||
| D-006 | Chill Water System, Clean and Flush | JOB | 1 | ||
| D-007 | Potable Water Pneumatic Tanks, Clean and Inspect | JOB | 1 | ||
| D-008 | Hot Water Accumulator Tanks, Clean and Inspect | JOB | 1 | ||
| D-009 | Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift | JOB | 1 | ||
| D-010 | Fin Stabilizers (General), Inspect and Repair | JOB | 1 | ||
| D-011 | Appleton FB 20-21 Single Point Davit (SPD), Inspect and Service | JOB | 1 | ||
| D-012 | Sewage Discharge and Transfer Pumps, Renew | JOB | 1 | ||
| D-013 | Grey Water Holding Tanks, Clean and Inspect | JOB | 1 | ||
| D-014 | Sewage Holding Tanks, Clean, Inspect and Repair | JOB | 1 | ||
| D-015 | Sewage Piping, Clean and Flush | JOB | 1 | ||
| O-016 | Tanks, Grey Water Holding, Preserve, Partial | JOB | 1 | ||
| D-017 | Tanks (Sewage Holding), Preserve, Partial | JOB | 1 | ||
| D-018 | Padeyes, Inspect and Test | JOB | 1 | ||
| D-019 | Temporary Services, Heating and Cooling | JOB | 1 | ||
| D-020 | Emergency Diesel Generator Raw Water Pump, Replace | JOB | 1 | ||
| D-021 | Deck Plating (Bosn’s Workshop and Focsle), Renew | JOB | 1 | ||
| D-022 | Deck Plating (Auxiliary Machinery Space 1), Renew | JOB | 1 | ||
| D-023 | Auxiliary Sea Water System Valves, Renew | JOB | 1 | ||
| D-024 | Air Compressor System Piping, Renew | JOB | 1 | ||
| O-00A | Composite Labor Rate | Hour | 0 | ||
| D-00B | GFP Report | NSP | EA | NSP | |
| D-00C | Travel and Perdiem | JOB | |||
| O-00Z | Laydays | Day | 5 | ERROR:#REF! | |
| Total Price of Definite Items | $0.00 | ||||
| Total Price of Option Items | $0.00 | ||||
| Total Price of Definite and Optional Items | $0.00 | ||||
| Over and Above/Growth Work | |||||
| The Labor Rates and Material Markup/Handling Fee will be used throughout the life of the contract if growth work is added to the scope of the contract. If Over and Above/Growth Work is issued, these items will be awarded at the quantities needed via a contract modification. The values shown are an estimate only and may be exceeded at the unit prices offered. The total extended price for both CLINs below are being used solely for the purposes of evaluating price. | |||||
| **Fill in the sections highlighted below: | |||||
| OA/G-001 | Over and Above/Growth Labor Rate | Hour | 1,258 | $0.00 | |
| OA/G-002 | Over and Above/Growth Material Markup/Handling Fee | $48,540.00 | Percent | $0.00 | |
| Total Evaluated Price of Over and Above/Growth | $0.00 |
(9/9/2025)_x000D_ Draft-0 - Page &P of &N