CDRL A017 Encl (1) Monthly Manning Report Template.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
Amendment A0012 - USS MUSTIN (DDG 89) FY22 Depot Modernization Period (DMP)
Solicitation number
N00024-21-R-4485
Issued by

About this file

This solicitation requests proposals for the execution of the USS MUSTIN (DDG 89) FY22 Depot Modernization Period (DMP). The Naval Sea Systems Command seeks a highly capable contractor to complete maintenance, modernization, and repair work at a capable pier facility. Interested offerors must request access to restricted attachments containing key events, milestones, pricing information, and compartment closeout requirements. Proposals are due in March 2022, with work to begin in May 2022 and be completed by November 2023. The place of performance is the west coast of the United States. The Government anticipates a single award for this opportunity.

View the file

Other files

File Type Posted
N00024-21-R-4485_CONFORMED THROUGH A0012.pdf PDF
N00024-21-R-4485_A0012.pdf PDF
N00024-21-R-4485_A0011.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0011.pdf PDF
Attachment J-8 (GFM List) (Rev 3).xlsx XLSX spreadsheet
N00024-21-R-4485_A0010.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0010.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0009.pdf PDF
N00024-21-R-4485_A0009.pdf PDF
Attachment J-8 (GFM) List) (Rev 2).xlsx XLSX spreadsheet
N00024-21-R-4485_A0008.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0008.pdf PDF
Attachment J-8 (GFM List) (Rev 1).xlsx XLSX spreadsheet
N00024-21-R-4485_A0007.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0007.pdf PDF
Attachment S-9 (Past Performance Questionnaire) (Rev1).docx DOCX document
N00024-21-R-4485_CONFORMED THROUGH A0006.pdf PDF
N00024-21-R-4485_A0006.pdf PDF
N00024-21-R-4485_A0005.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0005.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0004.pdf PDF
N00024-21-R-4485_A0004.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0003.pdf PDF
N00024-21-R-4485_A0003.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0002.pdf PDF
N00024-21-R-4485_A0002.pdf PDF
N00024-21-R-4485 CONFORMED THROUGH A0001.pdf PDF
N00024-21-R-4485_A0001.pdf PDF
Attachment S-4 (Manpower Performance Data Sheet).xlsx XLSX spreadsheet
Attachment S-2 (Past Performance Questionnaire).docx DOCX document
Attachment J-7 (Schedule Model Review).docx DOCX document
Attachment J-8 (GFM List).xlsx XLSX spreadsheet
Attachment J-10 (Open and Inspect Milestone Reports Due).xlsx XLSX spreadsheet
N00024-21-R-4485_MUSTIN FY22 DMP.pdf PDF
Attachment S-8 (Pier and Drydock Graphical Representation Template).xlsx XLSX spreadsheet
CDRL Exhibit C.pdf PDF
Attachment S-3 (Pre-Proposal Information Form) - 9Jun21.xlsx XLSX spreadsheet
CDRL Exhibit B.pdf PDF
Attachment S-9 (Past Performance CPARS References).docx DOCX document
CDRL Exhibit A.pdf PDF
Attachment S-5 (Eligibility Criteria Data Sheet).docx DOCX document
CDRL A016 Enc (1) End of Avail Report Template.xlsx XLSX spreadsheet
Attachment J-5 (Quality Assurance Surveillance Plan).docx DOCX document
Attachment S-7 (Proposal Assessment).xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prime KTR CNO Avail Totals This worksheet shall be completed with manpower requirements to execute CNO availabilities for which the company is the Prime contractor. This includes prime, subcontractor, temporary labor requirements.

CNO AVAIL TOTALS BY PROJECTFY 2020FY 2021
Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Mar-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21
Project X
(Ship Name)Project X
(Avail Type)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours
Contract Start Date:Monthly BCWP Hours
Contract Completion Date:Monthly BCWS Hours
Project Y
(Ship Name)Project Y
(Avail Type)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours
Contract Start Date:Monthly BCWP Hours
Contract Completion Date:Monthly BCWS Hours
Project Z
(Ship Name)Project Z
(Avail Type)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours
Contract Start Date:Monthly BCWP Hours
Contract Completion Date:Monthly BCWS Hours

SubKTR CNO Avail Totals This worksheet shall be completed to specify manpower provided by the company as a subKTR to other CNO availabilities.

CNO AVAIL TOTALS BY PROJECTFY 2020FY 2021
Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Mar-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21
Project 1
(Ship Name)Project 1
(Avail Type)Project 1
(Prime KTR)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours
Project 2
(Ship Name)Project 2
(Avail Type)Project 2
(Prime KTR)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours
Project 3
(Ship Name)Project 3
(Avail Type)Project 3
(Prime KTR)Actual/Forecast Start Date:Monthly ACWP Hours
Actual/Forecast Completion Date:Monthly ETC Hours

Non-CNO Workload

OTHER WORK TOTALS BY CATEGORYFY 2020FY 2021
Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Mar-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21
Non-CNO Navy WorkMonthly ACWP Hours
Monthly ETC Hours
Other Government Work (Coast Guard, MARAD, MSC, etc.)Monthly ACWP Hours
Monthly ETC Hours
Commercial WorkMonthly ACWP Hours
Monthly ETC Hours

Trade Totals

TOTAL TRADE INFORMATIONFY 2020FY 2021
Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21Feb-21Mar-21Apr-21May-21Jun-21Jul-21Aug-21Sep-21
Trade 1Monthly ACWP Hours
Monthly ETC Hours
Trade 2Monthly ACWP Hours
Monthly ETC Hours
Trade 3Monthly ACWP Hours
Monthly ETC Hours
Other Support Functions1Monthly ACWP Hours
Monthly ETC Hours
Note 1: Other Support Functions includes direct charge trades such as project management, contracts, QA, scheduling, etc.

Monthly Manning Summary

MONTHLY MANNING SUMMARY
AT YARD LEVELORGANICTEMPTOTAL
Production EmployeesN/A
Total Production Hours Worked
Straight Time Hours Worked
Overtime Hours Worked