Attachment S-8 (Pier and Drydock Graphical Representation Template).xlsx

XLSX spreadsheet 17 KB Posted

Attached to
Amendment A0012 - USS MUSTIN (DDG 89) FY22 Depot Modernization Period (DMP)
Solicitation number
N00024-21-R-4485
Issued by

About this file

This document includes a solicitation and graphical representation template for a federal contract opportunity. The Naval Sea Systems Command is soliciting proposals for the USS MUSTIN (DDG 89) Fiscal Year 2022 Depot Modernization Period, requiring maintenance, modernization, and repair services. Offerors must have substantial facilities including a capable pier and drydock, as well as personnel resources. The period of performance is from May 2022 to November 2023 at a place of performance in the western United States. Interested parties must register in the System for Award Management and monitor the solicitation on SAM.gov, where restricted attachments can be requested after confirming contractor status. The government anticipates a single award by March 2022.

View the file

Other files

File Type Posted
N00024-21-R-4485_CONFORMED THROUGH A0012.pdf PDF
N00024-21-R-4485_A0012.pdf PDF
N00024-21-R-4485_A0011.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0011.pdf PDF
Attachment J-8 (GFM List) (Rev 3).xlsx XLSX spreadsheet
N00024-21-R-4485_A0010.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0010.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0009.pdf PDF
N00024-21-R-4485_A0009.pdf PDF
Attachment J-8 (GFM) List) (Rev 2).xlsx XLSX spreadsheet
N00024-21-R-4485_A0008.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0008.pdf PDF
Attachment J-8 (GFM List) (Rev 1).xlsx XLSX spreadsheet
N00024-21-R-4485_A0007.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0007.pdf PDF
Attachment S-9 (Past Performance Questionnaire) (Rev1).docx DOCX document
N00024-21-R-4485_CONFORMED THROUGH A0006.pdf PDF
N00024-21-R-4485_A0006.pdf PDF
N00024-21-R-4485_A0005.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0005.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0004.pdf PDF
N00024-21-R-4485_A0004.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0003.pdf PDF
N00024-21-R-4485_A0003.pdf PDF
N00024-21-R-4485_CONFORMED THROUGH A0002.pdf PDF
N00024-21-R-4485_A0002.pdf PDF
N00024-21-R-4485 CONFORMED THROUGH A0001.pdf PDF
N00024-21-R-4485_A0001.pdf PDF
Attachment S-4 (Manpower Performance Data Sheet).xlsx XLSX spreadsheet
Attachment S-2 (Past Performance Questionnaire).docx DOCX document
CDRL A017 Encl (1) Monthly Manning Report Template.xlsx XLSX spreadsheet
Attachment J-7 (Schedule Model Review).docx DOCX document
Attachment J-8 (GFM List).xlsx XLSX spreadsheet
Attachment J-10 (Open and Inspect Milestone Reports Due).xlsx XLSX spreadsheet
N00024-21-R-4485_MUSTIN FY22 DMP.pdf PDF
CDRL Exhibit C.pdf PDF
Attachment S-3 (Pre-Proposal Information Form) - 9Jun21.xlsx XLSX spreadsheet
CDRL Exhibit B.pdf PDF
Attachment S-9 (Past Performance CPARS References).docx DOCX document
CDRL Exhibit A.pdf PDF
Attachment S-5 (Eligibility Criteria Data Sheet).docx DOCX document
CDRL A016 Enc (1) End of Avail Report Template.xlsx XLSX spreadsheet
Attachment J-5 (Quality Assurance Surveillance Plan).docx DOCX document
Attachment S-7 (Proposal Assessment).xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template

Name of Offeror:Ship(s) and Scenario:
LEGENDMay-22Jun-22Jul-22Aug-22Sep-22Oct-22Nov-22Dec-22Jan-23Feb-23Mar-23Apr-23May-23Jun-23Jul-23Aug-23Sep-23Oct-23Nov-23Dec-23Jan-24Feb-24
CURRENTLY AWARDED WORK
OTHER PROPOSED WORK
THIS PROPOSAL
Offeror's Pier(s)
Pier X
Pier Y
Pier Z
Add Additional as needed
Subcontracted Pier(s)
Add if required
Government Owned Pier(s)
Add if required
Offeror's Drydock(s)
Drydock 1
Drydock 2
Add Additional as needed
Subcontracted Drydock(s)
Add if required
Government Owned Drydock(s)
Add if required
Provide the pierside, dock and undock dates for each requirement, in acordance with the applicable Execution Milestones and Key Events attachment

Example and Notes

Name of Offeror:Ship(s) and Scenario:
LEGENDApr-19May-19Jun-19Jul-19Aug-19Sep-19Oct-19Nov-19Dec-19Jan-20Feb-20Mar-20Apr-20May-20Jun-20Jul-20Aug-20Sep-20Oct-20Nov-20Dec-20Jan-21<Note 1
CURRENTLY AWARDED WORK
OUTSTANDING PROPOSED WORK
THIS PROPOSAL
Offeror's Pier(s)
Pier X
Pier YUSS CURRENTLY AWARDED (15AUG19 - 10APR20) NOTE 6
Pier ZUSS THIS PROPOSAL (01JUN19 - 25SEP19) NOTE 8USS THIS PROPOSAL (15DEC19 - 10JUL20) NOTE 8
Add Additional as needed
Subcontracted Pier(s)
Add if required<Note 2
Government Owned Pier(s)
Add if required<Note 3
Offeror's Drydock(s)
Drydock 1
Drydock 2USS THIS PROPOSAL (25SEP19 - 15DEC19) NOTE 8
USS PROPOSED WORK (01JUN19 - 15SEP19) NOTE 7
Add Additional as needed
Subcontracted Drydock(s)
Add if required<Note 4
Government Owned Drydock(s)
Add if required<Note 5
Note 1: Chart must display time from proposal submission through end of period of performance
Note 2: Required if any current awarded work, proposed work, or this proposal utilize subcontracted pier(s). Add additional rows if required.
Note 3: Required if any current awarded work, proposed work, or this proposal utilize government owned pier(s). Add additional rows if required.
Note 4: Required if any current awarded work, proposed work, or this proposal utilize subcontracted pier(s)drydock(s). Add additional rows if required.
Note 5: Required if any current awarded work, proposed work, or this proposal utilize government owned pier(s)drydock(s). Add additional rows if required.
Note 6: This bar represents a currently awarded ship utilizing Pier Y from 15AUG19 - 10APR20.
Note 7: This bar represents an outstanding proposal in which the offeror proposes to utilize drydock 2 from 01JUN19 - 15SEP19.
Note 8: These bars represent this proposal in which the offeror proposes to utilize Pier Z from 01JUN19 - 25SEP19, drydock 2 from 25SEP19 - 15DEC19 and Pier Z from 15DEC19 - 10JUL20.
Note 9: Use notes section to explain any apparent conflicts/ mitigations.

DATES ARE FOR EXAMPLE PURPOSES ONLY

File details come from the government source that posted it. Updated .