The provided document is titled "Calculation of Self Performed Work" and contains instructions for offerors of a federal construction contract opportunity to calculate the percentage of work that must be self-performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or verified SDVOSB subcontractors.
The related federal contract opportunity is for an infrastructure upgrade project at the Tennessee Valley Healthcare System Albion Street VA Clinic, with a NAICS code of 236220 (Commercial and Institutional Building Construction) and a contract value between $100,000 and $250,000. This is a 100% set-aside for SDVOSB concerns, and the contractor must be listed in the Registry at the time of offer and award. Offerors must submit a proposal, along with a bid bond, by the due date via email. There will be one site visit scheduled, and all questions must be submitted as written Requests for Information.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK (626A4-19-101)
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes with 237 and 238 prefix) of the cost of the contract performance incurred for personnel must be performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or those of a verified SDVOSB subcontractor. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
| Specification Division |
| SDVOB Vendor (Y or N) |
| Personnel Cost |
| Material/Equipment Costs |
Division 01
| $ |
| $ |
Division 02
| $ |
| $ |
Division 03
| $ |
| $ |
(Add additional lines as necessary for each Division applicable to this project)
| $ |
| $ |
| $ |
| $ |
Sub Total (Personnel Costs, Material/Equipment Costs)
| Profit |
| $ |
| Home Office Overhead |
| $ |
| Bond |
| $ |
| Grand Total |
| $ |
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $
3. Remainder is ‘Total amount of work to be self-performed under the
| Contract’: | $ | |
| 4. Self-performed work = Line 3/Line 1 x 100 = | % |
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)