RFI 12-22 - PCG.pdf

PDF 150 KB Posted

Attached to
Z2DB--626-22-705QA - EHRM Infrastructure Upgrade Albion Clinic
Solicitation number
36C24924R0098
Issued by

About this file

This document is a Request for Information (RFI) for the EHRM Infrastructure Upgrade Albion Clinic project located at the Tennessee Valley Healthcare System Albion Street VA Clinic in Nashville, TN. The project involves furnishing labor, materials, equipment, transportation, and supervision to prepare the site per the drawings and specifications. The project is a Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside with a contract value between $100,000 and $250,000.

Contractors are instructed to submit written requests for information (RFIs) that clearly identify the specification section, paragraph, and page number. RFIs must be submitted by 1:00 PM CT on October 28, 2024. There will be one mandatory site visit scheduled. Proposals must be submitted electronically and include the complete solicitation. This is a Lowest Price Technically Acceptable (LPTA) procurement. Key details addressed in the RFI include venting requirements, temporary sprinklers, fire alarm and security system coordination, and painting specifications.

View the file

Other files

File Type Posted
Combined Readigov.pdf PDF
36C24924R0098 0008.docx DOCX document
36C24924R0098 0007.docx DOCX document
36C24924R0098 0006.docx DOCX document
RFI Sheet for 36C24924R0098 Meharry Clinic Room 150 TR Room Upgrade .xlsx XLSX spreadsheet
36C24924R0098 0005.docx DOCX document
Albion Clinic Lobby - 626-22-705QA - EHRM Infrastructure Upgrade Albion Clinic Pre-Bid Site Visit 2.pdf PDF
RFI 01 - NetPlanner Systems - 10-15-24.pdf PDF
RFI 02 - NetPlanner Systems - 10-15-24.pdf PDF
RFI 1-11 - PCG.pdf PDF
36C24924R0098 0004.docx DOCX document
Pre-bid site visit Sign in - Albion Street.pdf PDF
Albion Clinic meeting spot site visit 2.pdf PDF
36C24924R0098 0003.docx DOCX document
Albion Clinic meeting spot.pdf PDF
36C24924R0098 0002.docx DOCX document
Amendment RFI Response.docx DOCX document
36C24924R0098 0001.docx DOCX document
RFI Form.docx DOCX document
Contractor EMR Certification Form.docx DOCX document
Calculation of Self Performed Work.docx DOCX document
Wage Determination.docx DOCX document
22-153 BD Dwgs.pdf PDF
22-153 BD Specs.pdf PDF
36C24924R0098_1.docx DOCX document
UEI _ TAX ID.docx DOCX document
ATTACHMENT 6- Schedule-of-Values-Sample Template.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

36C24924R0098

PROJECT NUMBER: 626-22-705QA Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents.

When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.

PROJECT TITLE: EHRM Infrastructure Upgrade Albion Clinic

PROJECT LOCATION: Albion Street VA Clinic, 1818 Albion St Suite 114, Nashville, TN 37208

TO:

Brian Bentley Brian.Bentley@va.gov

RFI NO.: 12 - 22 DATE: 10.15.2024 SPEC/DWG. REFERENCE: General Questions & Drawing A-101 / ET401

REPLY NEEDED BY: 10.18.2024

INFORMATION NEEDED:

12. Will we have to remove a window in each room to vent air outside or is there another means of venting air from the space to achieve the negative pressure required by ICRA? Hepa Scrubbing will be satisfactory.

13. Will temporary sprinklers be required? No.

14. Will the contractor be required to turn the existing sprinkler heads up during construction once the ceiling is removed?

See drawings and specs. VA is a tenant to the building. Coordinate with Lessor.

15. Will we have to test and balance the HVAC system after the work is complete? Will be covered in start up.

16. Who is the manufacturer of the current Fire Alarm system? Coordinate with Lessor.

17. Please provide contacts information for those who services the current Fire Alarm System. Coordinate with Lessor.

18. Who is the manufacturer of the current Security and Access Control system. JCI/TYCO is the proposed security vendor.

19. Please provide contact information for those who services the current Security and Access Control System. Tim Huffines, phone number is available to the winning bidder.

20. When touch-up painting, can we go doorway to doorway, or do we have to go corner to corner? Doorway to doorway

21. Is there a specification for the replacement of metal studs & drywall (is buy American the only directive)? See specs.

22. Note numbers 1 & 2 on page ET401, references two different model numbers for the channel rack and cable management system. Are these Ortronics model numbers?? Yes.

REPLY FROM: DATE:

ATTACHMENTS: COPY TO:

SUBMITTED BY: Paramount Construction Group City/State: Madison, Mississippi

PHONE NO.: 601.427.5454

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

VHATVHKiteK Highlight

File details come from the government source that posted it. Updated .