C54261_AGREEMENT_LB.pdf
PDF 557 KB Posted
- Attached to
- Bus Hoist Replacement at Anaheim Bus Base
- Solicitation number
- 5-4261
- Issued by
- Orange County, California
About this file
This is a contract agreement (Agreement No. C-5-4261) between the Orange County Transportation Authority (OCTA) and a contractor for bus hoist replacement services at the Anaheim Bus Base located at 1717 E. Via Burton Avenue, Anaheim, California. The scope of work involves removing and replacing an existing bus lift, control console, and all accessories in the steam clean area while protecting the surrounding concrete platform, drainage systems, hydraulic systems, electrical connections, adjacent building structures, utilities, wall steel panels, and wall lights. The contractor must obtain and pay for all required licenses from applicable jurisdictions. The project is scheduled for completion within 240 calendar days from the date of the Notice to Proceed, with the contractor required to provide 72 hours advance notice before commencing work. The contractor must submit construction schedules within five calendar days of notification and implement recovery schedules if the critical path schedule reflects 30 or more days of negative total float.
The contract price is established as a firm fixed sum, with a maximum cumulative payment obligation amount to be determined, covering all labor, equipment, materials, and facilities necessary for project completion. This is a U.S. Department of Transportation (DOT) assisted contract subject to federal prevailing wage requirements under the Davis-Bacon Act and California prevailing wage standards. A Disadvantaged Business Enterprise (DBE) goal of 6 percent has been established for this project. The contractor must furnish performance bonds, payment bonds, and guaranty documents equal to 100 percent of the contract price, along with comprehensive insurance coverage including commercial general liability of $1,000,000 per occurrence and $2,000,000 general aggregate, automobile liability of $1,000,000 per accident, and workers' compensation with waiver of subrogation. Progress and final payments will be made in accordance with contract terms, with retainage returned to subcontractors within seven days for construction contracts upon project completion. The project is classified as a Level 3 Health, Safety and Environmental Specifications facility modification project subject to all applicable federal, state, and local laws and regulations.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Last Rev: 12/18/2024
AGREEMENT NO. C-5-4261
BETWEEN
ORANGE COUNTY TRANSPORTATION AUTHORITY
AND
THIS AGREEMENT is effective this _____ day of ________________________, 20__ (“Effective
Date”), by and between the Orange County Transportation Authority, 550 South Main Street, P.O. Box
14184, Orange, CA 92863-1584, a public corporation of the State of California (hereinafter referred to as
"AUTHORITY"), and , , , , (hereinafter referred to as "CONTRACTOR").
WITNESSETH:
WHEREAS, AUTHORITY has determined that it requires Bus Hoist Replacement at Anaheim
Bus Base; and
WHEREAS, said work cannot be performed by the regular employees of AUTHORITY; and
WHEREAS, CONTRACTOR has represented that it has the requisite personnel, experience, material, and equipment and is otherwise qualified to perform such services; and
WHEREAS, CONTRACTOR wishes to perform these services; and
WHEREAS, AUTHORITY’s Board of Directors authorized this Agreement on .
NOW, THEREFORE, it is mutually understood and agreed by AUTHORITY and CONTRACTOR as follows:
ARTICLE 1. COMPLETE AGREEMENT
A. This Agreement, including all exhibits and other documents incorporated herein and made applicable by reference, constitutes the complete and exclusive statement of the terms and conditions of the Agreement between AUTHORITY and CONTRACTOR and it supersedes all prior representations, understandings and communications. The invalidity in whole or in part of any term or condition of this
Agreement shall not affect the validity of other terms or conditions.
B. AUTHORITY's failure to insist in any one or more instances upon the performance of any terms or conditions of this Agreement shall not be construed as a waiver or relinquishment of
AUTHORITY's right to such performance by CONTRACTOR or to future performance of such terms or conditions and CONTRACTOR's obligation in respect thereto shall continue in full force and effect.
CONTRACTOR shall be responsible for having taken steps reasonably necessary to ascertain the nature and location of the work, and the general and local conditions, which can affect the work or the cost thereof. Any failure by CONTRACTOR to do so will not relieve it from responsibility for successfully performing the work without additional expense to AUTHORITY.
C. AUTHORITY assumes no responsibility for any understanding or representations concerning conditions made by any of its officers, employees or agents prior to the execution of this Agreement, unless such understanding or representations by AUTHORITY are expressly stated in this Agreement.
D. Time shall be of the essence hereunder; but CONTRACTOR shall perform work hereunder only to the minimum extent consistent with requirements herein.
E. Changes to any portion of this Agreement shall not be binding upon AUTHORITY except when specifically confirmed in writing by an authorized representative of AUTHORITY and issued in accordance with the provisions of this Agreement.
ARTICLE 2. AUTHORITY DESIGNEE
The Chief Executive Officer of AUTHORITY, or designee, shall have the authority to act for and exercise any of the rights of AUTHORITY as set forth in this Agreement.
ARTICLE 3. SCOPE OF WORK
CONTRACTOR shall provide all labor, equipment, materials and facilities necessary for all work related to at AUTHORITY's in strict compliance with all the requirements specified herein and in:
Attachment A, entitled “Disadvantaged Business Enterprise (DBE) Contract Provisions for U.S.
DOT-assisted Contracts”
Attachment A-1, entitled “DBE Participation Commitment Form”
Exhibit A, entitled "General Provisions"; Addendum No’s ;
Exhibit B, entitled “Specifications”;
Exhibit C, entitled "List of Drawings";
Exhibit D-1, entitled "List of Subcontractors";
Exhibit E, entitled "Performance Bond";
Exhibit F, entitled "Payment Bond"; and
Exhibit G, entitled "Guaranty";
Exhibit H, entitled “Level III Safety Specifications”;
Exhibit I, entitled “Contract Change Order”;
all of which documents are attached to and, by this reference, incorporated in and made a part of this
Agreement. By this reference, also incorporated in and made a part of this Agreement are all applicable provisions of the IFB and all representations made by CONTRACTOR in its original bid to AUTHORITY, including, but not limited to, CONTRACTOR's certifications relative to Workers' Compensation Insurance, and compliance with Section 7028.15 of the State of California Business and Professions Code.
ARTICLE 4. DELIVERY / RECOVERY SCHEDULE
A. CONTRACTOR shall fully complete the herein above described work within (240 ) calendar days from the effective date of written Notice to Proceed (NTP) issued by AUTHORITY. CONTRACTOR shall give AUTHORITY not less than seventy-two (72) hours advance notice of the start of any work.
Within five (5) calendar days after said notice, CONTRACTOR shall provide any construction schedules as may be requested by AUTHORITY.
B. If at any time, the critical path schedule reflects -30 or a greater negative number of days of total float, then CONTRACTOR, within ten (10) days after CONTRACTOR first becomes aware of such schedule delay, shall prepare and submit to AUTHORITY for review and approval a Recovery Schedule demonstrating CONTRACTOR’s proposed plan to regain lost schedule progress and to achieve the original contractual milestones in accordance with the Agreement. AUTHORITY shall notify
CONTRACTOR within ten days after receipt of each such Recovery Schedule whether the schedule is deemed accepted or rejected. Within five (5) days after AUTHORITY’s rejection of the schedule, CONTRACTOR will resubmit a revised Recovery Schedule incorporating AUTHORITY’s comments.
When AUTHORITY accepts CONTRACTOR’s Recovery Schedule, CONTRACTOR shall, within five (5) days after AUTHORITY’s acceptance, incorporate and fully include such schedule into the Project
Schedule and deliver it to AUTHORITY.
C. All costs incurred by CONTRACTOR in preparing, implementing and achieving the Recovery
Schedule shall be borne by CONTRACTOR and shall not result in a change to the contract price.
D. In the event that CONTRACTOR fails to provide an acceptable Recovery Schedule within thirty (30) days of CONTRACTOR’s receipt of a notice to do so, CONTRACTOR shall have no right to receive progress payments until CONTRACTOR has prepared and AUTHORITY has approved such
Recovery Schedule.
ARTICLE 5. START OF WORK
CONTRACTOR shall incur no costs, and shall not perform or furnish any work, services, materials or equipment under this Agreement, unless and until a written Notice to Proceed has been given to
CONTRACTOR by AUTHORITY. Conditions precedent to AUTHORITY issuing said Notice to Proceed are CONTRACTOR furnishing the Exhibit E "Performance Bond", Exhibit F "Payment Bond", Exhibit G
"Guaranty", and certificates of insurance as set forth in Article 11 hereunder. CONTRACTOR shall furnish said documents within ten (10) calendar days after notification of contract award from AUTHORITY.
Upon receipt of acceptable bonds, guaranty, and insurance certificates, AUTHORITY will within ten (10) working days thereafter, issue the written Notice to Proceed.
ARTICLE 6. PAYMENT
A. For CONTRACTOR's full and complete performance of its obligations under this Agreement, and subject to the maximum cumulative payment obligation provision set forth in Article 8, AUTHORITY shall pay CONTRACTOR the firm fixed sum of Dollars ($ .00).
B. Progress payments and the final payment will be made by AUTHORITY to CONTRACTOR in accordance with the terms as set forth in Exhibit A, "General Provisions", under the "Progress
Payments" and "Final Payment and Claims" sections therein. The acceptance by CONTRACTOR of
AUTHORITY's final payment hereunder shall constitute a waiver of all claims against AUTHORITY under or arising out of this herein Agreement, as such may from time to time be amended.
C. Failure by AUTHORITY to pay amount in dispute shall not alleviate, diminish or modify in any respect the CONTRACTOR's obligation to achieve final acceptance of and all work in accordance with the contract documents, and CONTRACTOR shall not cease or slow down its performance under this
Agreement on account of any such amount in dispute. CONTRACTOR shall proceed as directed by
AUTHORITY pending resolution of dispute. Upon resolution of dispute, each party shall promptly pay any amount owing.
ARTICLE 7. PROMPT PAYMENT CLAUSE
A. AUTHORITY has adopted a prompt payment provision on all U.S. DOT-assisted contracts to facilitate timely payment to all subcontractors in accordance with regulatory mandates. The provisions of this Article apply to both DBE and non-DBE subcontractors. Pursuant to Title 49 of the Code of Federal
Regulations (CFR) Part 26.29:
B. “CONTRACTOR or subcontractor agrees to pay each subcontractor under this Agreement for satisfactory performance of its Agreement no later than seven (7) days for construction contracts and fifteen (15) days for consultant contracts from the receipt of each progress payment CONTRACTOR receives from AUTHORITY on account of the work performed by the subcontractor. CONTRACTOR agrees further to return retainage payments to each subcontractor within seven (7) days for construction contracts and fifteen (15) days for consultant contracts after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the Agreement work by
AUTHORITY. Any delay or postponement of payment from the above referenced time frame may take place only for good cause and with AUTHORITY’s prior written approval.” CONTRACTOR agrees further to return retainage payments on construction-related contracts to each subcontractor within seven (7) days after receiving payment for work satisfactorily completed and accepted including incremental acceptances of portions of the Agreement work by AUTHORITY. CONTRACTOR shall incorporate this clause verbatim, set forth above, in all subcontract, broker, dealer, vendor, supplier, purchase order or other source agreements issued to both DBE and non-DBE firms. In the event that there is a dispute over all or any portion of the amount due on a progress payment from CONTRACTOR or subcontractor to a subcontractor, CONTRACTOR or subcontractor may withhold no more than 150 percent of the disputed amount.
C. Any violation of these provisions shall subject the violating CONTRACTOR to the penalties, sanctions, and other remedies specified in Section 7108.5 of the California Business and Professions
Code and Section 10262 of the California Public Contract Code for construction contracts, and Section
3321 of the California Civil Code for consultant contracts. This requirement shall not be construed to limit or impair any contractual, administrative or judicial remedies otherwise available to CONTRACTOR or subcontractor in the event of a dispute involving late payment or nonpayment by CONTRACTOR;
deficient subcontract performance or noncompliance by a subcontractor.
D. Failure to comply with these provisions without prior written approval from AUTHORITY will constitute noncompliance, which shall result in the application of appropriate administrative sanctions to the licensee, including, but not limited to, a penalty payable to the subcontractor, of two percent (2%) of the invoice amount due per month, for every month that full payment is not made.
ARTICLE 8. MAXIMUM OBLIGATION
Notwithstanding any provisions of this Agreement to the contrary, AUTHORITY and
CONTRACTOR mutually agree that AUTHORITY's maximum cumulative payment obligation hereunder
(including obligation for CONTRACTOR 's profit), shall be Dollars ($ .00), which shall include all amounts payable to CONTRACTOR for its subcontracts, leases, materials and costs arising from, or due to termination of, this Agreement.
ARTICLE 9. NOTICES
All notices hereunder and communications regarding the interpretation of the terms of this
Agreement, or changes thereto, shall be effected by delivery of said notices in person or by depositing said notices in the U.S. mail, registered or certified mail, returned receipt requested, postage prepaid and addressed as follows:
To CONTRACTOR: To AUTHORITY:
Orange County Transportation Authority
550 South Main Street
P.O. Box 14184
, Orange, CA 92863-1584
ATTENTION: ATTENTION: Josie Mellen
Title: Title: Sr. Contract Administrator
Phone:
Email:
Phone: (714) 560 - 5860
Email: jmellen@octa.net
AUTHORITY will provide timely notification to CONTRACTOR of the receipt of any third-party claim relating to the Agreement, and CONTRACTOR agrees to timely reimburse AUTHORITY for its reasonable costs incurred in providing such notice in accordance with Public Contract Code Section
9201.
ARTICLE 10. INDEPENDENT CONTRACTOR
A. CONTRACTOR's relationship to AUTHORITY in the performance of this Agreement is that of an independent contractor. CONTRACTOR's personnel performing work under this Agreement shall at all times be under CONTRACTOR's exclusive direction and control and shall be employees of
CONTRACTOR and not employees of AUTHORITY. CONTRACTOR shall pay all wages, salaries and other amounts due its employees in connection with this Agreement and shall be responsible for all reports and obligations respecting them, such as social security, income tax withholding, unemployment compensation, workers' compensation and similar matters.
B. Should CONTRACTOR’s personnel or a state or federal agency allege claims against
AUTHORITY involving the status of AUTHORITY as employer, joint or otherwise, of said personnel, or allegations involving any other independent contractor misclassification issues, CONTRACTOR shall defend and indemnify AUTHORITY in relation to any allegations made.
ARTICLE 11. INSURANCE
A. CONTRACTOR shall procure and continuously maintain in full force and effect through contract completion, insurance coverages specified herein. Coverages shall not be subject to self-insurance provisions. CONTRACTOR shall provide the following insurance coverage:
1. Commercial General Liability, to include Products/Completed Operations, Independent Contractors’, Contractual Liability, and Personal Injury with a minimum limit of $1,000,000 per occurrence and $2,000,000 general aggregate.
2. Automobile Liability to include owned, hired and non-owned autos with a combined single limit of $1,000,000 each accident;
3. Workers’ Compensation with limits as required by the State of California, including waiver of subrogation, in favor of AUTHORITY, its officers, directors, employees and agents.
4. Builders All Risk policy or course of construction including earthquake and flood coverage with minimum limits of $(project amount).
5. Employers’ Liability with minimum limits of $1,000,000.
B. Prior to commencement of any work hereof, CONTRACTOR shall furnish to AUTHORITY’s
Contract Administrator broker-issued insurance certificate showing the required insurance coverages and further providing that:
1. AUTHORITY, its officers, directors, employees and agents must be named as additional insured on Commercial General Liability and Automobile Liability policy with respect to performance hereunder; and
2. The coverage shall be primary and noncontributory as to any other insurance with respect to performance hereunder; and
3. Thirty (30) days prior written notice of cancellation or material change be given to
AUTHORITY.
C. "Occurrence," as used herein, means any event or related exposure to conditions, which result in bodily injury or property damage.
D. Upon AUTHORITY’s request, certified, true and exact copies of each of the insurance policies shall be provided to AUTHORITY.
E. AUTHORITY shall notify CONTRACTOR in writing of any changes in the requirements to insurance required to be provided by CONTRACTOR. Except as set forth in this Article, any additional cost from such change shall be paid by AUTHORITY and any reduction in cost shall reduce the
Agreement price pursuant to a change order.
F. CONTRACTOR shall also include in each subcontract the stipulation that subcontractors shall maintain coverage in the amounts required as provided in this Agreement.
G. CONTRACTOR shall be required to immediately notify AUTHORITY of any modifications or cancellation of any required insurance policies.
H. CONTRACTOR shall submit required insurance certificates to AUTHORITY’s insurance tracking contractor, InsureTrack. CONTRACTOR shall respond directly to InsureTrack’s request for updated insurance certificates and other insurance-related matters by email to octa@instracking.com.
I. CONTRACTOR shall include on the face of the certificate of insurance, the following information:
1. The Agreement Number C- and, the Contract Administrator’s Name,
2. For Certificate Holder: The Orange County Transportation Authority, its officers, directors, employers, and agents, c/o InsureTrack, P.O. Box 60840 Las Vegas, NV 89160.
ARTICLE 12. BONDS
A. By submitting Exhibit E, entitled “Performance Bond", and Exhibit F, entitled "Payment Bond", CONTRACTOR shall satisfy AUTHORITY's requirements that CONTRACTOR deposit with AUTHORITY bonds with values in the sum of one hundred percent (100%) of this Agreement's price to cover
CONTRACTOR's failure to fully perform hereunder and CONTRACTOR's failure to pay its labor, material or failure to comply with Article 39 of this Agreement, in performing hereunder. If the Agreement price is increased in connection with a Change Order, AUTHORITY may, in its sole discretion, require a corresponding increase in the amount of the Performance and Payment bonds or new bonds covering the Change Order work.
mailto:octa@instracking.com
B. Notwithstanding any other provision set forth in this Agreement, performance by a Surety or
Guarantor of any obligations of CONTRACTOR shall not relieve CONTRACTOR of any of its obligations thereunder.
ARTICLE 13. ORDER OF PRECEDENCE
To the extent there are any conflicts or inconsistency arising between any provisions or documents incorporated in this Agreement, the order of precedence for conflict resolution in descending order shall be as follows: (1) the provisions of this Agreement, including its Exhibits; (2) the provisions of
IFB including all Addendums; (3) the bid submitted to AUTHORITY by CONTRACTOR in response to said IFB; and (4) any other documents, cited herein or incorporated by reference. In the event of conflicting provisions between Exhibit B “Specifications”, and Exhibit C "List of Drawings", the
Specifications (Exhibit B) shall take precedence.
ARTICLE 14. CHANGES
A. By written notice or order, AUTHORITY may, from time to time, order work suspension and/or make any change in the general scope of this Agreement, including, but not limited to, changes in the drawings, specifications, schedules (either deceleratory or acceleratory) or any other particular of the specifications or provisions of this Agreement. If any such work suspension or change causes an increase or decrease in the price or time required for performance, CONTRACTOR shall promptly notify
AUTHORITY thereof and assert its claim for adjustment within ten (10) calendar days after the change or work suspension is ordered, and an equitable adjustment shall be negotiated. However, nothing in this clause shall excuse CONTRACTOR from proceeding immediately with the Agreement as changed.
Changes will be made in accordance with the terms as set forth in Exhibit A, "General Provisions", paragraph F, Extra Work and Changes, by written Change Order.
B. No claims by CONTRACTOR for equitable adjustment hereunder shall be allowed if asserted after final payment under this Agreement.
C. Any work performed beyond the technical provisions specified in this Agreement, or any extra work performed without AUTHORITY's written authority, will be considered unauthorized work and the cost thereof will not be paid for. Upon order of AUTHORITY's Engineer or its designee, unauthorized work shall be remedied, removed or replaced at CONTRACTOR's expense.
D. Any changes under this Article will be made using AUTHORITY’s Contract Change Order form, set forth in Exhibit I, “Contract Change Order”.
E. Any changes which constitute a “Claim” as defined by Public Contract Code Section 9204
(hereinafter “Section 9204”) will be processed in accordance with Section 9204 and Exhibit A, “General
Provisions.”
ARTICLE 15. MODIFICATION BID-PRICE BREAKDOWN
CONTRACTOR, in connection with any bid it makes for a change order, shall furnish a price breakdown, itemized as required by AUTHORITY. Unless otherwise directed, the price breakdown shall be in sufficient detail to permit an analysis of all material, labor, equipment, subcontract and overhead costs, as well as profit, and shall cover all work involved in the modification, whether such work was deleted, added or changed. Any expense claimed by subcontractors shall be supported by a similar price breakdown. In addition, if the bid includes a time extension, a justification therefore shall be furnished.
The bid, together with the price breakdown and time extension justification, shall be furnished by the date specified by AUTHORITY.
ARTICLE 16. DISPUTES
A. Except as otherwise provided in this Agreement, when a dispute arises between
CONTRACTOR and AUTHORITY, the project managers shall meet to resolve the issue. If project managers do not reach a resolution, the dispute will be decided by AUTHORITY’s Director of Contracts
Administration and Materials Management (CAMM), who shall reduce the decision to writing and mail or otherwise furnish a copy thereof to CONTRACTOR. The decision of the Director, CAMM, shall be the final and conclusive administrative decision.
B. Pending final decision of a dispute hereunder, CONTRACTOR shall proceed diligently with the performance of this Agreement and in accordance with the decision of AUTHORITY's Director, CAMM. Nothing in this Agreement, however, shall be construed as making final the decision of any
AUTHORITY official or representative on a question of law, which questions shall be settled in accordance with the laws of the State of California.
ARTICLE 17. TERMINATION FOR CONVENIENCE
A. AUTHORITY may terminate this Agreement for its convenience at any time in whole or in part, by giving CONTRACTOR written notice thereof. AUTHORITY shall terminate by delivering to
CONTRACTOR a written Notice of Termination for Convenience specifying the extent of termination and its effective date. Upon termination, AUTHORITY shall pay CONTRACTOR its allowable costs incurred to date of that portion terminated. The rights, duties and obligations of the parties shall be construed in accordance with the applicable provisions of the Code of Federal Regulations (CFR) Title 48, Chapter 1, part 49, of the Federal Acquisition Regulation (FAR) and specific subparts and other provisions thereof applicable to termination for convenience. If AUTHORITY sees fit to terminate this Agreement for convenience, said notice shall be given to CONTRACTOR in accordance with the provisions of the FAR referenced above and Article 9, herein. Upon receipt of said notification, CONTRACTOR shall immediately proceed with all obligations, regardless of any delay in determining or adjusting any amounts due under this Article, and agrees to comply with all applicable provisions of the FAR pertaining to termination for convenience.
ARTICLE 18. TERMINATION FOR DEFAULT-DAMAGES FOR DELAY-TIME EXTENSIONS
A. If CONTRACTOR refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will ensure its completion within the time specified in this Agreement, or any extension thereof, or fails to complete said work within such time, AUTHORITY may, by written notice to
CONTRACTOR that specifies the nature of the default, terminate CONTRACTOR's right to proceed with the work or such part of the work as to which there has been delay. In such event, AUTHORITY may take over the work and prosecute the same to completion, by Agreement or otherwise, and may take possession of and utilize in completing the work such materials, appliances and plant as may be on the site of the work and necessary therefore. Whether or not CONTRACTOR's right to proceed with the work is terminated, CONTRACTOR and its sureties shall be liable for any damage to AUTHORITY resulting from its refusal or failure to complete the work within the specified time.
B. If AUTHORITY so terminates CONTRACTOR's right to proceed, the resulting damage will consist of such liquidated damages as set forth in the Article 38 in this Agreement entitled "Liquidated
Damages," until such reasonable time as may be required for final completion of the work together with any increased costs occasioned AUTHORITY in completing the work. If AUTHORITY does not so terminate CONTRACTOR's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.
C. CONTRACTOR's right to proceed shall not be so terminated nor the CONTRACTOR charged with resulting damage if:
1. The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of CONTRACTOR, including but not restricted to, acts of God, acts of the public enemy, acts or omissions of AUTHORITY, acts of another CONTRACTOR in the performance of an Agreement with AUTHORITY, fires, floods, epidemics, quarantine restrictions, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both CONTRACTOR and such subcontractors or suppliers; and
2. CONTRACTOR, within ten (10) calendar days from the beginning of any such delay, notifies AUTHORITY in writing of the causes of delay. AUTHORITY shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in its judgment, the findings of fact justify such an extension, and its findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in the "Disputes" clause of this Agreement. Any such time extensions will not become effective until approved by AUTHORITY's Engineer in writing. AUTHORITY's Engineer will furnish CONTRACTOR a weekly statement showing the number of calendar days charged to the
Agreement for the preceding week, the number of calendar days of time extensions being considered or approved, the number of calendar days originally specified for the completion of this Agreement and the number of calendar days remaining to complete this Agreement, and the extended date for completion thereof.
3. Should at any time extensions be included by AUTHORITY's Engineer on the Weekly
Statement of Contract Calendar Days, a change order covering the sum total of the time extensions will be issued to CONTRACTOR at periodic intervals during the project.
D. If, after notice of termination of CONTRACTOR's right to proceed under the provisions of this clause, it is determined for any reason that CONTRACTOR was not in default under the provisions of this clause, or that the delay was excusable under the provisions of this clause, the rights and obligations of the parties shall be the same as if the notice of termination had been issued pursuant to Article 17, entitled
"Termination for Convenience".
E. The rights and remedies of AUTHORITY provided in this clause are in addition to any other rights and remedies provided by law or under this Agreement.
F. As used in paragraph C.1 of this Article, the term "subcontractors or suppliers," means subcontractors or suppliers at any tier.
ARTICLE 19. INDEMNIFICATION
CONTRACTOR shall indemnify, defend, and hold harmless AUTHORITY, its officers, directors, employees and agents from and against any and all claims (including attorneys' fees and reasonable expenses for litigation or settlement) for any loss, costs, penalties, fines, damages, bodily injuries, including death, damage to or loss of use of property, arising out of, resulting from, or in connection with the performance of CONTRACTOR, its officers, directors, employees, agents, subcontractors or suppliers under the Agreement. Notwithstanding the foregoing, such obligation to defend, hold harmless, and indemnify AUTHORITY, its officers, directors, employees and agents shall not apply to such claims or liabilities arising from the sole or active negligence or willful misconduct of AUTHORITY.
ARTICLE 20. ASSIGNMENTS AND SUBCONTRACTS
A. Neither this Agreement nor any interest herein nor claim hereunder may be assigned by
CONTRACTOR either voluntarily or by operation of law. CONTRACTOR shall not have the right to make any substitutions of any subcontractor listed in Exhibit D, entitled "List of Subcontractors," except in accordance with the provisions of the Subletting and Subcontractors Fair Practices Act, Public Contract
Code Section 4100 et seq. AUTHORITY's consent shall not be deemed to relieve CONTRACTOR of its obligation to fully comply with the requirements of this Agreement.
B. CONTRACTOR shall be fully responsible to AUTHORITY for all acts and omissions of its own employees, and of subcontractors and their employees. CONTRACTOR shall coordinate the work performed by any subcontractor.
C. AUTHORITY shall have the right, but not the obligation, to review the form of any subcontract used by CONTRACTOR for the project and to require modifications thereto to conform to the requirements set forth herein.
ARTICLE 21. ACCESS TO RECORDS AND REPORTS
CONTRACTOR shall provide AUTHORITY, the U.S. Department of Transportation (DOT), the
Comptroller General of the United States, and their respective representatives, and any other agents of
AUTHORITY, such access to CONTRACTOR's accounting books, records, payroll documents and facilities of the CONTRACTOR which are directly pertinent to this Agreement for the purposes of examining, auditing and inspecting all accounting books, records, work data, documents and activities related hereto. CONTRACTOR shall maintain such books, records, data and documents in accordance with generally accepted accounting principles and shall clearly identify and make such items readily accessible to such parties during CONTRACTOR's performance hereunder and for a period of four (4) years from the date of final payment by AUTHORITY, except in the event of litigation or settlement of claims arising from the performance of this Agreement, in which case CONTRACTOR agrees to maintain same until AUTHORITY, or any of their duly authorized representatives, have disposed of all such litigation, appeals, claims or exceptions related thereto. AUTHORITY’s right to audit books and records directly related to this Agreement shall also extend to all first-tier subcontractors. CONTRACTOR shall permit any of the foregoing parties to reproduce documents by any means whatsoever or to copy excerpts and transcriptions as reasonably necessary. CONTRACTOR agrees to include these requirements in all subcontracts at any tier.
ARTICLE 22. CONFLICT OF INTEREST
CONTRACTOR agrees to avoid organizational conflicts of interest. An organizational conflict of interest means that due to other activities, relationships or contracts, the CONTRACTOR is unable, or potentially unable to render impartial assistance or advice to AUTHORITY; CONTRACTOR’s objectivity in performing the work identified in the Scope of Work is or might be otherwise impaired; or
CONTRACTOR has an unfair competitive advantage. CONTRACTOR is obligated to fully disclose to
AUTHORITY in writing Conflict of Interest issues as soon as they are known to CONTRACTOR. All disclosures must be submitted in writing to AUTHORITY pursuant to the Notice provision herein. This disclosure requirement is for the entire term of this Agreement.
ARTICLE 23. CODE OF CONDUCT
CONTRACTOR agrees to comply with AUTHORITY’s Code of Conduct as it relates to Third-
Party contracts which is hereby referenced and by this reference is incorporated herein. CONTRACTOR agrees to include these requirements in all of its subcontracts.
ARTICLE 24. PROHIBITION ON PROVIDING ADVOCACY SERVICES
CONTRACTOR and all subcontractors performing work under this Agreement, shall be prohibited from concurrently representing or lobbying for any other party competing for a contract with
AUTHORITY, either as a prime contractor or subcontractor. Failure to refrain from such representation may result in termination of this Agreement.
ARTICLE 25. FEDERAL, STATE AND LOCAL LAWS
CONTRACTOR warrants that, in the performance of this Agreement, it shall comply with all applicable federal, state and local laws, statutes and ordinances and all lawful orders, rules and regulations promulgated thereunder.
ARTICLE 26. EQUAL EMPLOYMENT OPPORTUNITY
During the performance of this Agreement, CONTRACTOR agrees as follows:
A. CONTRACTOR will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin.
CONTRACTOR will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following: Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. CONTRACTOR agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
B. CONTRACTOR will, in all solicitations or advertisements for employees placed by or on behalf of CONTRACTOR, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.
C. CONTRACTOR will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with CONTRACTOR’s legal duty to furnish information.
D. CONTRACTOR will send to each labor union or representative of workers with which
CONTRACTOR has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of CONTRACTOR’s commitments under this Article, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
E. CONTRACTOR will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
F. CONTRACTOR will furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to CONTRACTOR’s books, records, and accounts by the DOT and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
G. In the event of CONTRACTOR’s noncompliance with the nondiscrimination clauses of this
Agreement or with any of the said rules, regulations, or orders, this Agreement may be canceled, terminated, or suspended in whole or in part and CONTRACTOR may be declared ineligible for further
Government contracts or federally-assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
H. CONTRACTOR will include the portion of the sentence immediately preceding Paragraph (A) and the provisions of Paragraphs (A) through (H) of this Article in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section
204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. CONTRACTOR will take such action with respect to any subcontract or purchase order as the DOT may direct as a means of enforcing such provisions, including sanctions for noncompliance: provided, however, that in the event CONTRACTOR becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the DOT, CONTRACTOR may request the United States to enter into such litigation to protect the interests of the
United States.
ARTICLE 27. FINISHED AND PRELIMINARY DATA
A. All of CONTRACTOR’s finished technical data, including but not limited to illustrations, photographs, tapes, software, software design documents, including without limitation source code, binary code, all media, technical documentation and user documentation, photoprints and other graphic information required to be furnished under this Agreement, shall be AUTHORITY’s property upon payment and shall be furnished with unlimited rights and, as such, shall be free from proprietary restriction except as elsewhere authorized in this Agreement. CONTRACTOR further agrees that it shall have no interest or claim to such finished, AUTHORITY-owned, technical data; furthermore, said data is subject to the provisions of the California Public Records Act, Government Code Section 7920.000 et seq.
B. It is expressly understood that any title to preliminary technical data is not passed to
AUTHORITY but is retained by CONTRACTOR. Preliminary data includes roughs, visualizations, software design documents, layouts and comprehensives prepared by CONTRACTOR solely for the purpose of demonstrating an idea or message for AUTHORITY’s acceptance before approval is given for preparation of finished artwork. Preliminary data title and right thereto shall be made available to
AUTHORITY if CONTRACTOR causes AUTHORITY to exercise Article 17, and a price shall be negotiated for all preliminary data.
ARTICLE 28. NONDISCRIMINATION
A. Nondiscrimination: In accordance with Federal transit law at 49 U.S.C. Section 5332, CONTRACTOR agrees that it will not discriminate against any employee or applicant for employment because of race, color, religion, national origin, sex, disability, or age. CONTRACTOR agrees to comply with all applicable regulations and other implementing requirements the Federal Transit Administration
(FTA) may issue.
B. Race, Color, Creed, National, Origin, Sex: In accordance with Title VII of the Civil Rights
Act, as amended, 42 U.S.C. Section 2000e et seq.; and Federal transit laws at 49 U.S.C. Section 5332;
CONTRACTOR agrees to comply with all applicable equal employment opportunity requirements of
U.S. Department of Labor (U.S. DOL) regulations, "Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor;" 41 CFR part 60.. CONTRACTOR further agrees to comply with Title VI of the Civil Rights Act, as amended, 42 U.S.C. Section 2000d et seq.;
49 CFR part 21; the most recent version of FTA Circular 4702.1B, “Title VI Requirements and
Guidelines for Federal Transit Administration Recipients;” DOT Order 5610.2(a) to Address
Environmental Justice in Minority Populations and Low Income Populations;” Executive Order No.
13166 and DOT Policy Guidance concerning Recipients’ Responsibilities to Limited English
Proficiency (70 FR 74087, Dec. 14, 2005); and the most recent version of FTA Circular 4704.1 “Equal
Employment Program Guidelines for Grant Recipients,” as applicable. CONTRACTOR agrees to comply with any implementing requirements FTA may issue.
C. Age: In accordance with the Age Discrimination in Employment Act, 29 U.S.C. Sections 621-
634; U.S. Equal Employment Opportunity Commission regulations, “Age Discrimination in Employment
Act,” 29 C.F.R. part 1625; the Age Discrimination Act of 1975, as amended, 42 U.S.C. Section 6101 et seq.; U.S. Health and Human Services regulations, “Nondiscrimination on the Basis of Age in Programs or Activities Receiving Federal Financial Assistance,” 45 CFR part 90; and Federal transit law at 49 U.S.C.
Section 5332; CONTRACTOR agrees to refrain from discrimination against present and prospective employees for reason of age. CONTRACTOR agrees to comply with implementing requirements FTA may issue.
D. Disabilities: In accordance with Section 504 of the Rehabilitation Act of 1973, as amended, 29 U.S.C. Section 794; the Americans with Disabilities Act of 1990, as amended, 42 U.S.C. Section
12101 et seq.; the Architectural Barriers Act of 1968, as amended, 42 U.S.C. Section 4151 et seq., and Federal transit law at 49 U.S.C. Section 5332; CONTRACTOR agrees that it will not discriminate against individuals on the basis of disability. CONTRACTOR agrees to comply with all applicable implementing regulations and requirements FTA may issue, including 49 CFR parts 27, 37, 38, and 39 and the most recent version of FTA Circular 4710.1 “Americans with Disabilities Act: Guidance.”
E. DISADVANTAGED BUSINESS ENTERPRISE (DBE): CONTRACTOR shall not discriminate on the basis of race, color, national origin, or sex in the performance of this Contract. The
CONTRACTOR shall carry out applicable requirements of 49 CFR Part 26 in the award and administration of U.S. DOT-assisted contracts. In administering the AUTHORITY components of the DBE
Program Plan, CONTRACTOR, subrecipient or subconsultant will not, directly, or through contractual or other arrangements, use criteria or methods of administration that have the effect of defeating or substantially impairing accomplishment of the objectives of the DBE Program Plan with respect to individuals of a particular race, color, sex, or national origin. Failure by the CONTRACTOR to carry out these requirements is a material breach of this Agreement, which may result in the termination of this
Agreement or such other remedy as the AUTHORITY deems appropriate, which may include, but is not limited to:
(1) Withholding monthly progress payments;
(2) Assessing sanctions;
(3) Assessing liquidated damages; and/or
(4) Disqualifying the CONTRACTOR from future proposing as non-responsible.
CONTRACTOR agrees to include the language above, verbatim and not by reference, in every subcontract agreement, broker, dealer, vendor, supplier, purchase order (PO) or other source agreements issued to both DBE and non-DBE firms. CONTRACTOR agrees to include these requirements in all subcontracts at any tier.
ARTICLE 29. DISADVANTAGED BUSINESS ENTERPRISES
A. In conformance with Title 49 CFR Part 26, “Participation by Disadvantaged Business
Enterprises in Department of Transportation Financial Assistance Programs,” AUTHORITY has established a six (6%) percent Disadvantaged Business Enterprise (DBE) participation goal for the services required in this Agreement.
B. At the time of contract execution, the CONTRACTOR committed to utilize one or more
Disadvantaged Business Enterprise (DBE) Firms in the performance of this DOT-assisted contract.
CONTRACTOR agrees to enter into agreements with the DBE subcontractors listed on Attachment A-1
“DBE Participation Commitment” and ensure they perform work and/or supply materials in accordance with original commitments. No changes to CONTRACTOR’s DBE commitment shall be made until proper review and approval by AUTHORITY is rendered in writing.
C. CONTRACTOR must take appropriate actions to ensure that it will satisfy good faith efforts to attain the DBE goal and/or the DBE commitment made at award (whichever is higher), when change orders or other modifications alter the dollar amount of the Agreement or the distribution of work.
CONTRACTOR must apply and report its DBE goal commitment against the total current Agreement value, including any change orders and/or amendments.
D. If there is a DBE goal and/or DBE commitment on the Agreement, CONTRACTOR must complete and submit within the specified timelines, DBE documentation electronically through the
AUTHORITY-approved electronic reporting system (ECAT).
E. CONTRACTOR shall comply with all the requirements set forth in Attachment A titled, “DISADVANTAGED BUSINESS ENTERPRISE (DBE) CONTRACT PROVISIONS FOR U.S. DOT-
ASSISTED CONTRACTS”, which is attached to and, by this reference, incorporated in and made a part of this Agreement.
ARTICLE 30. PRIVACY ACT
A. CONTRACTOR shall comply with, and assures the compliance of its employees with, the information restrictions and other applicable requirements of the Privacy Act of 1974, 5 U.S.C. Section
552(a). Among other things, CONTRACTOR agrees to obtain the express consent of the Federal
Government before CONTRACTOR or its employees operate a system of records on behalf of the
Federal Government. CONTRACTOR understands the requirements of the Privacy Act, including the civil and criminal penalties for violation of that Act, apply to those individuals involved, and that failure to comply with the terms of the Privacy Act may result in termination of the underlying Agreement.
B. CONTRACTOR agrees to include this requirement in all of its subcontracts.
ARTICLE 31. OWNERSHIP OF REPORTS AND DOCUMENTS
A. The originals of all letters, documents, reports and other products and data produced under this Agreement shall be delivered to, and become the property of AUTHORITY. Copies may be made for CONTRACTOR’s records but shall not be furnished to others without written authorization from
AUTHORITY. Such deliverables shall be deemed works made for hire and all rights in copyright therein shall be retained by AUTHORITY.
B. All ideas, memoranda, specifications, plans, manufacturing, procedures, drawings, descriptions, and all other written information submitted to CONTRACTOR in connection with the performance of this Agreement shall not, without prior written approval of AUTHORITY, be used for any purposes other than the performance under this Agreement, nor be disclosed to an entity not connected with the performance of the project. CONTRACTOR shall comply with AUTHORITY’s policies regarding such material. Nothing furnished to CONTRACTOR, which is otherwise known to CONTRACTOR or is or becomes generally known to the related industry shall be deemed confidential. CONTRACTOR shall not use AUTHORITY’s name, photographs of the project, or any other publicity pertaining to the project in any professional publication, magazine, trade paper, newspaper, seminar or other medium without the express written consent of AUTHORITY.
C. No copies, sketches, computer graphics or graphs, including graphic artwork, are to be released by CONTRACTOR to any other person or agency except after prior written approval by
AUTHORITY, except as necessary for the performance of services under this Agreement. All press releases, including graphic display information to be published in newspapers, magazines, etc., are to be handled only by AUTHORITY unless otherwise agreed to by CONTRACTOR and AUTHORITY.
ARTICLE 32. INCORPORATION OF FTA TERMS
All contractual provisions required by the DOT, whether or not expressly set forth in this document, as set forth in FTA Circular 4220.1F, are hereby incorporated by reference. Anything to the contrary herein notwithstanding, all FTA mandated terms shall be deemed to control in the event of a conflict with other provisions contained in this Agreement. CONTRACTOR shall not perform any act, fail to perform any act, or refuse to comply with any AUTHORITY requests, which would cause AUTHORITY to be in violation of the FTA terms and conditions.
ARTICLE 33. FEDERAL CHANGES
CONTRACTOR shall at all times comply with all applicable FTA regulations, policies, procedures and directives, including without limitation those listed directly or by reference in the agreement between
AUTHORITY and FTA, as they may be amended or promulgated from time to time during this Agreement.
CONTRACTOR’s failure to comply shall constitute a material breach of Agreement.
ARTICLE 34. NO GOVERNMENT OBLIGATION TO THIRD PARTIES
AUTHORITY and CONTRACTOR acknowledge and agree that, notwithstanding any concurrence by the Federal Government in or approval of the solicitation or award of the underlying
Agreement, absent the express written consent by the Federal Government, the Federal Government is not a party to this Agreement and shall not be subject to any obligations or liabilities to AUTHORITY, CONTRACTOR, or any other party (whether or not a party to this Agreement) pertaining to any matter resulting from the underlying Agreement. CONTRACTOR agrees to include this requirement in all of its subcontracts.
ARTICLE 35. PROGRAM FRAUD AND FALSE OR FRAUDULENT STATEMENTS AND
ACTS
A. CONTRACTOR acknowledges that the provisions of the Program Fraud Civil Remedies Act of 1986, as amended, 31 U.S.C. Sections 3801 et seq. and DOT regulations, “Program Fraud Civil
Remedies,” 49 CFR Part 31, apply to its actions pertaining to this project. By execution of this Agreement, CONTRACTOR certifies or affirms the truthfulness and accuracy of any statement it has made, it makes, it may make, or causes to be made, pertaining to the underlying Agreement of the FTA assisted project for which this Agreement's work is being performed.