This document is a Scope of Work for a Design-Build contract to perform major renovations of Building #3, the Rescue Swimmer Training Facility (RSTF), at U.S. Coast Guard Base Elizabeth City in Elizabeth City, NC. The Contractor shall provide design services from a North Carolina licensed Architecture/Engineering firm, and upon Coast Guard acceptance of the 65% design, shall construct the accepted solution.
The key work includes demolishing the Rescue Swimmer Pool and Pool Room, protecting existing pre-cast walls, constructing a new corridor and exterior walls, reconstituting the building envelope, and restoring all remaining facility functions and systems. The project entails various tasks including demolition, new corridor construction, building repairs and system restoration, and final site restoration. The Contractor shall submit design documents at the 35%, 65%, and 100% completion stages for Coast Guard review and acceptance. The contract is only available to the successful NMACC III Pool 1 offerors.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P/N 24395201
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
ENGINEERING SERVICES DIVISION
SCOPE OF WORK
FOR
DESIGN / BUILD SERVICES
FOR MAJOR M&R OF BLDG #3
AT
U.S. COAST GUARD BASE ELIZABETH CITY
ELIZABETH CITY, NC
APRIL 2024
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT, RM 2179
1240 EAST NINTH STREET
CLEVELAND, OHIO 44199-2060
AUTHOR: J. SILVAROLI DIV 1 FINAL
TABLE OF CONTENTS
Division Section Title Page
1 GENERAL REQUIREMENTS
01 11 00 Scope of Work 4
01 14 00 Contractor Work Hours 15
01 14 13 Pre-bid Site Visits 17
01 14 14 Pre-Construction Site Conditions 18
01 14 16 Coordination 18
01 14 19 Field Adjustments 20
01 18 14 Building Permits 20
01 18 17 Environmental Permits 20
01 26 13 Request for Information 20
01 31 19 Project Meetings 22
01 32 16 Construction Schedule, Schedule of Values and Progress Schedule
01 32 26 Construction Daily Reports 23
01 33 00 Submittal Procedures 24
01 35 29 Safety Program 26
01 51 00 Temporary Utilities 27
01 51 13 Equipment/Utility Lockout and Tagout
Requirements
01 51 16 Temporary Fire Protection 28
01 54 30 Confined Entry 29
01 55 00 Access Roads and Parking 29
01 55 29 Staging Areas and Access 29
01 56 00 Lights, Signs & Barricades 30
01 57 13 Erosion and Sediment Control 30
01 57 23 Pollution Control 31
01 65 00 Recovered Materials Notice 32
01 66 13 Hazardous Waste 32
01 66 16 Safety Data Sheets and Material Handling
Procedures
01 71 33 Protection from Weather and Construction
Operations
01 74 00 General Cleanup and Site Restoration of Work
Areas
TABLE OF CONTENTS (cont.)
Division Section Title Page
1 GENERAL REQUIREMENTS (cont.)
01 78 00 As Built Drawings 34
01 78 23 Operating Instructions and Training 35
01 80 00 Facility Preventative Maintenance Program
(FPMP)
List of Submittals 37
Contract Item Acceptance Request 38
DIVISION 1
(November 2023 Version)
SECTION 01 11 00
SCOPE OF WORK
1. WORK SUMMARY: The Contractor shall provide Design-Build services to perform major renovations of Building #3, the Rescue Swimmer Training Facility (RSTF), at CG Base
Elizabeth City in Elizabeth City, NC. The Contractor shall obtain the services of an
Architecture/Engineering firm licensed in the State of North Carolina to provide design services for the project. The design shall be in conformance with applicable regulations, codes, and regulatory requirements. Upon Coast Guard acceptance of the Contractor’s 65% design, the
Contractor shall construct the accepted design solution. The intent of the project is to demolish and remove the Rescue Swimmer Pool and Pool Room, protect the West, North and East pre-cast walls and features to remain, construct a new corridor and exterior walls along the perimeter of the former pool area, fully reconstitute the building envelope, and restore all remaining facility functions and systems. Major items of work shall include the following:
1.1 BASE WORK: The following are the major work items. Additional descriptions and requirements are listed in the subsequent Task section.
1.1.1 Demolition: Provide Design-Build services to demolish the Rescue Swimmer Pool and
Pool Room, the wave generation room, and the temporary steel shoring equipment in the Pool
Room. Backfill site as required for construction of new corridor addition.
1.1.2 Corridor Construction and Building Envelope Restoration: Provide Design-Build services for a new +/- 14’-0” wide corridor addition to be connected to the three existing pre-cast interior walls of the Rescue Swimmer Pool Room. The corridor shall maintain interior building circulation and facilitate safe egress. In addition to the corridor construction, take all necessary actions to ensure the building envelope is fully restored, watertight, and appropriate for regional conditions.
1.1.3 BLDG #3 Repairs and System Restoration: Provide Design-Build services to fully restore all remaining facility functions and systems, including but not limited to HVAC, plumbing, pool circulation and sanitation, electrical, and fire safety. In addition, provide Design-
Build services for select modifications to facility systems and finishings (See Task 2, paragraph
3).
1.1.4 Site Restoration: Provide Design-Build services for site restoration including the construction of a pedestrian accessible courtyard in the former pool location. Legacy utilities not needed for the new design shall be removed.
1.2 TASKS: The Design Scope of Work shall include but not limited to the following tasks.
The project shall include the two (2) Tasks as follows:
Task 1: Design Documents
1. The Design Scope of Work for the building improvements will include all design stages to the Final Design stage resulting in project construction drawings and completed construction permits, if necessary. Design and Construction tasks are subsequently listed. A conceptual model (C24395201 USCG Concept Design.pdf) has been provided as a reference for design.
Task 2: Project Construction
1. Demolition of RS Pool Room in its entirety; including but not limited to the following:
a. Terminate and remove all utility service lines in the RS Pool Room while maintaining building functionality for long-term normal service to the rest of the building. (Service is not required during construction.)
b. Demolish all equipment in the wave generation room.
c. Demolish all mechanical equipment and ductwork located within the RS Pool
Room, located on the RS Pool roof, or serving the RS Pool Room. Demolish air handling units PTRU-1 and PAHU-2 and associated ductwork, piping, controls, hangers, and accessories that is located within areas of remaining building.
d. Provide any necessary temporary bracing to the south wall of the RS Pool Room.
e. Demolish enclosure of RS Pool wave generation room and foundations.
f. Demolish 6 feet wide x 110 feet long double tee roof beams and existing roof system over the RS Pool Room.
g. Protect all features of Building #3 to remain or be reused including but not limited to utilities and West, North and East pre-cast walls of RSTF Pool Room.
Damaged existing features that are to remain or be reused shall be restored or replaced to match existing conditions or new adjoining work.
h. Demolish steel shoring system. (Existing shoring system is Government property and part of the building. Shoring towers and materials shall be removed by and properly disposed of or become the property of the Contractor.)
i. Demolish South wall consisting of pre-cast concrete wall panels and masonry wall, and foundations. Contractor shall include drilling and installing lifting eyes in all pre-cast wall panels for demolition, as necessary.
j. Demolish pool divider curtain, doors and frames, roof access ladder, and roof drains and piping.
k. Salvage fans, training platforms and all training equipment located on the platforms (hoists, etc.) to BASE for future use.
l. Salvage existing LED lighting fixtures (but not older tube style lighting) to BASE for future use.
m. Demolish air compressor systems within building areas to be removed.
n. Demolish slab on grade and rubber pool deck, flooring, floor drains and all piping, valves, and fittings and necessary RS Pool water circulation and treatment equipment and components within the RS Pool Room. Any below grade piping within the footprint of the remaining Building #3 may be abandoned in place.
Any piping and control equipment located above grade within the remaining
Building #3, that only serves the RS Pool Room, shall be removed. Any below or above grade piping and equipment within the RS Pool Room footprint shall be removed.
o. The Contractor is responsible for draining the pool water. Contractor shall test chlorine level prior to discharging and dechlorinate the water below 0.1 milligrams per liter by using chemical dechlorination additive. Prior to discharging ensure the pH of the water is between 6 and 9, and remove or strain any algae and debris. Discharge at a rate slow enough to not cause erosion, flooding or other nuisance conditions on adjacent properties. Contractor may discharge to storm drain system. Contractor may also discharge to a landscaped area, if discharged at rate slow enough to allow water to percolate into the ground.
p. Demolish entire RS Pool structure (approximately 82 feet wide x 164 feet long), warming tub, and foundation systems.
q. Provide any dewatering, shoring, and bracing necessary for the deconstruction of the RS Pool Room, Pool structure, and features. As part of the Demolition Plan, the Contractor shall provide and design a Support of Excavation System and a
Dewatering System to achieve the proposed work. The Contractor will be responsible to determine the means and methods to prevent settlement of structures to remain as a result of demolition operations.
r. Provide erosion and sediment control throughout construction period.
s. Provide dust and debris control as necessary throughout the construction period.
Prevent the spread of dust and debris to avoid the creation of a nuisance or hazard in the surrounding area. Due to the active runway nearby the project site, minimize generation of small items of debris that could migrate to the runway.
Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
t. Properly backfill the site with engineered material as specified by Contractor’s geotechnical consultant.
2. Construction of new +/- 14’-0” corridor building addition; including but not limited to the following:
a. A new +/- 14’-0” wide corridor shall be constructed to maintain interior circulation and provide egress from the existing spaces that are directly adjacent to the RS Pool Room. The height of the new Corridor shall maintain access to the overhead door that leads into the Inflatables Lab.
b. Provide an accessible ceiling with a minimum height of 15-0”. All suspended acoustic tile ceilings (SATC) shall be moisture resistant, non-directional fissured, square edge, 24" x 24". Suspension system shall be exposed grid, intermediate duty, of aluminum with baked white polyester finish. Provide a minimum 30” plenum space above the ceiling and the bottom of the roof structure.
c. Recessed troffer lighting shall be provided in the suspended ceiling system.
Provide emergency battery lighting to illuminate means of egress in accordance with NFPA 101. Exterior of corridor addition shall have wall mounted LED fixtures along perimeter of courtyard area and at egress locations.
d. A new concrete slab on grade over a vapor barrier and granular fill shall be provided. An epoxy resinous flooring system shall be installed over the slab with an integral coved base.
e. The new exterior wall shall be bearing and shall be constructed of CMU. Where masonry construction is used, wall systems shall include a ventilated airspace with water resistive barrier for drainage plane. Additional framing shall consist of structural steel w-shape members spanning from the newly constructed exterior
CMU wall to the existing interior pre-cast walls. New steel structural supports shall be attached to the existing pre-cast walls to enable a structural connection to new beam framing. New roof decking shall be installed over the beams.
Contractor shall determine if new framing and supports may be attached directly to existing pre-cast walls or if new support columns and foundations are required, which shall be included if necessary.
f. The actual foundation type, capacity, etc. will be determined after contract award by the Contractor's geotechnical consultant based on the actual loads and geotechnical data. Provide suitable shallow or deep foundation system adequate to support all loads imposed on the foundation.
g. The exterior wall construction shall consist of metal composite panels over metal furring and continuous insulation over a fluid applied air and weather barrier on
12” reinforced CMUs. The interior surface of the CMU wall shall be finished with epoxy paint. Metal insulated panels may be considered in lieu of metal composite panels and separate insulation board.
h. The finished roof shall be a standing seam metal roofing system with factory-applied color finish with a complete roof drainage system that shall tie into the existing underground storm system. The roof shall be constructed at a minimum slope of 2:12 with the framing to be constructed from standard metal studs. Metal roof system shall have concealed clip attachment and avoid exposed fastening of panels and flashings in the finished work. Color finishes shall be standard 70 percent polyvinylidene fluoride color finish. Metal roof finish shall have a minimum 30 year warranty. Include all flashing and sealing necessary to provide watertight connection to existing pre-cast walls. In order to maintain the existing interior wall space, interior utilities, and any penetrations through the existing walls, the elevation of new roof connection shall match the existing roof elevation. The existing pre-cast walls shall remain at their current height and are not required to be shortened.
i. Provide vertical and horizontal polystyrene insulation conforming to ASTM C578 or rigid polyisocyanurate board wall insulating products conforming to ASTM
C59. Seal the joints in rigid insulation within cavity/veneer walls for additional moisture protection. Provide fiberglass blanket insulation meeting ASTM C665 with flame spread rating of 25 or less when tested according to ASTM E 84.
Vapor retarder facing shall be foil face Type III, Class B, Category 1. R-values for building insulation shall be determined by the coordination of code requirements, building/base energy management plan, ASHRAE 90.1 and
LEED/sustainable requirements. At a minimum provide: (unless required to be greater by the applicable codes listed above), including roof and wall insulation shall be:
i. Roof = R-30
ii. Walls = R-19
j. A new AHU shall be provided to serve the Corridor. All areas of the addition shall be conditioned to meet ASHRAE 55 standards. HVAC ductwork shall be sheet metal, fabricated, constructed, braced, reinforced, installed, supported, and sealed in accordance with the latest SMACNA DCS. Ducts requiring insulation, other than exhaust ducts, shall be insulated with exterior duct wrap insulation.
Exhaust ducts shall be insulated the last 6 feet to the weather. All HVAC equipment returns shall be ducted. Ceiling plenums are not allowed for return air usage.
k. New storefront windows shall be provided at the new exterior wall to provide natural daylight to the Corridor. Window systems shall be heavy commercial grade fixed windows with insulated, low "E" glass. Aluminum frames shall be thermally broken and match existing window finish. The minimum amount of total window area shall be 20% of the exterior wall area.
l. New HM exterior exit doors shall be provided to maintain egress exit to the exterior. Sizes shall match the existing doors that are located in the southern pre-cast wall that is to be demolished. Additional doors shall be considered where
Program deems appropriate. Exterior doors shall be fully weather-stripped and include a heavy-duty metal threshold that prevents drafts, dirt, water, and insect entry. All exterior doors shall be insulated. Provide all necessary hardware for a complete installation. All exterior doors and fire rated doors shall have closers.
All new locks shall be compatible with existing door system.
m. Provide a complete addressable fire detection and alarm system for the addition that ties into the existing building systems. The new and existing fire safety system shall be connected and compatible with new Siemens BAS.
n. Construction of the building addition shall be classified as Type 1B. The existing building does not have a sprinkler system.
o. Provide electrical wiring, outlets, and switches. Provide electrical receptacle outlets and hard-wired equipment connections as: required for specific equipment items; required by the National Electrical Code (NFPA 70); as a minimum in accordance with the following general criteria; and as otherwise specified.
Receptacle outlets shall be specification grade, heavy duty, grounding type, wall mounted 18” above the finished floor unless specified otherwise. Exterior side of corridor addition shall have GFCI weatherproof outlets.
p. Provide a minimum of three (3) hose bib connections spaced along the exterior of the corridor addition.
3. Various improvements to the remaining RSTF Building #3 and UMET Pool Building #3
(refer to following reference files for overall intent: C19055066D.pdf; C19055066X.pdf;
C19055066 BOD.pdf). Improvements to include but not limited to the following:
a. Convert existing Building Automation System (BAS) to a Siemens BAS. All new and existing control points, sequences of operations, alarms, schedules, etc. must be reconnected to new BAS.
b. Remove and replace the entire existing pool finish on the UMET pool below the tile band, including replacement of all tile markings, and replace with quartz aggregate, fortified with Portland cement finish and tile.
c. Remove existing overhead door and frame located at the northeast corner of the
RS Pool Room and replace with an 8 ft wide x 7 ft tall double door and frame.
Contractor shall frame, fill, and finish in remaining opening space to accommodate new door and frame size. All associated components to match the existing interior door and frame materials within the building area.
d. Replace the condensing unit associated with the UMET pool room air handler
(ACCU-C).
e. Replace UMET Pool water level deck sensor rods and water level controllers.
f. Upgrade UV system and install CO2 gas system with protective bollards for
UMET Pool system.
g. Install programmable VFD drive for recirculation pump of UMET Pool system.
h. Install 2,000 LB capacity davit crane system and pipe bracing in UMET filter room.
i. Replace floor coatings at ramp to the admin/office area, debrief and warming room, diver’s wet storage, associated corridors, and the UMET pool deck. Mill existing floor coating down to concrete slab and replace with high-performance coating (self-leveling urethane concrete with satin urethane top coat). Also apply high-performance coating to new corridor area. Provide floor transitions as necessary.
j. Reroute and replace compressed air systems as necessary to maintain compressed air loop and services to remaining building.
k. Investigate and determine if necessary, the replacement of pumps SP-1 and SP-2 and associated piping, insulation, and accessories. Pumps shall be compatible with proposed BAS.
l. Investigate and determine if necessary, the removal of solar water heating system
BTU meter. Provide solar hot water system DDC controller. (Existing solar hot water system to remain.)
m. Install EUH-1 Unit Heater and supports serving UMET Room.
n. Provide seismic pipe bracing as necessary.
4. Final site restoration; including but not limited to the following:
a. Post construction clean up.
b. Temporary seeding and mulch as necessary during construction.
c. Design final grades to drain away from building. Analyze the proposed storm drainage system to ensure that flooding will not occur at or in any new or existing structures that may be affected by or related to the new construction.
d. New storm water management devices may be tied into existing storm system.
e. Installation of final topsoil (min. 4”) to finish grade, seeding and mulch.
Including protection, fertilizer, and water necessary to establish turf.
f. Installation of pavement / hardscapes necessary to match and tie into existing site and to provide pedestrian access to new courtyard area. Minimum 6 feet wide pedestrian walkway along perimeter of corridor addition.
g. Reconnection, removal, and/or rerouting of any below or above ground utilities.
h. Replacement of airfield fence as necessary, to match existing. (If airfield fence was temporarily relocated during construction operations.)
i. Full restoration of site that may be disrupted during construction.
1.3 MANUFACTURER’S INSTRUCTIONS: All materials, products, and equipment to be furnished by the Contractor shall be properly installed according to the manufacturer’s printed instructions. For bidding and contract performance purposes, the Contractor is deemed to be aware of the requirements of these instructions.
1.4 RECEIPT OF MATERIALS: Shipments of equipment, materials, and supplies shall be addressed to the Contractor – not the Government. The Contractor must be on hand to accept shipments; the Government will not accept shipments.
1.5 Work associated with these items are described in the following specification sections and/or are shown on the contract drawings. Incidental work items not listed above and necessary for completing the project shall be included.
2. DESIGN CRITERIA
2.1 GENERAL: Provide a fully completed design that satisfies all functional and operational requirements of the intended project use. All disciplines shall be separated and clearly identified.
Work requirements shall be reasonably attainable with standard construction equipment and methods available. Design documents shall be technically correct, fully detailed, and complying with all applicable codes and standards. These include, but not limited to:
American National Standards Institute (ANSI)
American Standard for Testing and Materials (ASTM)
American Institute of Steel Construction (AISC)
American Concrete Institute (ACI)
National Electric Code (NEC)
National Fire Protection Association (NFPA)
International Building Code (IBC)
United States Environmental Protection Agency (USEPA)
Code of Federal Regulations (CFR)
Unified Facilities Criteria (UFC)
2.2 PROFESSIONAL STAMP: Project design shall be executed under the direction of a licensed Professional Engineer and Architect registered in the State of North Carolina. Project design calculations, drawings, specifications, and reports shall be signed and sealed.
2.3 PERMITS: The Contractor shall prepare for and obtain all permits required for project work. At the beginning of the design process, establish and obtain all necessary federal, state, and local application and permit requirements for project work. Coordinate with appropriate agencies during design to ensure that the project design will be in compliance with federal, state, and local permit requirements. Prepare all forms, drawings, and supporting documentation necessary to apply for permits and coordinate with the appropriate agency officials to assure the application is properly completed. Completed applications shall be forwarded to CEU Cleveland for signature and subsequent forwarding by the Contractor to the appropriate federal, state, or local agency. The applicant for permits shall be:
Commanding Officer
U.S. Coast Guard
Civil Engineering Unit, Room 2179
Cleveland, Ohio 44199-2060
2.3.1 Local building permits are not required as work performed on federal property is exempt.
Environmental permits are required as applicable.
2.4 CALCULATIONS: The Contractor shall prepare calculations as required to design new or analyze existing project components. Calculations shall be complete, legible, detailed, and shall clearly indicate all assumptions, criteria, references, manufacturer’s data, codes, and standards used. Calculations shall be provided for all major civil, structural, electrical, and mechanical components of the project. Provide an electronic copy of the calculations as a “.pdf” file in addition to hard copies.
2.5 DRAWINGS & SPECIFICATIONS: The Contractor shall prepare project specifications and drawings. The specifications and drawings shall be coordinated and consistent in format, wording, referencing, and extent of descriptions. Specifications and drawings shall be clear, concise, and complete. Specifications may be incorporated into the construction drawings, in lieu of producing a separate bound specification document. Specifications included in the drawings shall identify materials, and methods or standards of installation and execution. Use the following project identifying information on specifications and drawings:
Project Title: Major M&R of BLDG #3
Project Number: 24395201
Drawing Number: 24395201-D
2.5.1 Drawings: Drawings shall be prepared in AutoDesk AutoCAD 2020 using the standard
Coast Guard template. AutoCAD drawing templates and CAD support files are provided electronically. All borders, dimensions, and text shall be in paper (layout) space. The title block shall not be exploded or modified. Plans, elevations, details, and sections shall be placed in individual view ports. All images shall be drawn in model space on a one-to-one scale. For final submittal of AutoCAD drawings each sheet/layout shall have its own AutoCAD file. Files shall be named C24395201[Discipline Designator][Sheet Number].dwg. If XREF’s are used, then the Contractor shall “bind” all XREF’s to the final drawings so that no external files will be required to view the drawings.
2.6 DESIGN STAGE SUBMITTALS & REQUIREMENTS: Submittals shall be completed and presented as indicated herein. Items to be submitted shall be transmitted using the attached
Submittal Approval Request Form and be delivered to the Contracting Officer. The following is a List of Submittals required:
2.6.1 Site Survey Report: Notify Mr. Ronald Haight, CEU Cleveland Detachment at (252)
470-7414, at least five (5) working days in advance of all site visits. Submit to the Contracting
Officer an electronic “.pdf” copy via DoD Safe, plus deliver four (4) copies of the Site Survey
Report that summarizes information collected. The report shall cover the following areas:
1. Existing conditions.
2. Existing utilities.
3. Operational criteria/requirements.
4. Comments/suggestions collected.
5. Drawings of existing site and facilities.
6. Identify permits and coordination required and their requirements.
7. Identify problem areas and questions.
8. Suitability of existing items/equipment for continued use.
9. Identify any new deficiencies.
10. Photographs of the work area.
2.6.2 Demolition Plan: Submit to the Contracting Officer an electronic “.pdf” copy via DoD
Safe, plus deliver four (4) copies of the Demolition Plan signed and sealed by a licensed engineer. This item may be included in the 35% Design Submittal. The plan shall include the following:
1. Contractor staging area.
2. Professional engineering provisions to safely and efficiently complete work.
3. Proposed work and sequencing of all demolition work. (USCG does not have erection sequencing plans from the original construction. It shall be incumbent upon the Contractor to develop the demolition sequencing plan.)
4. Methods for protecting existing features to remain.
5. Support of Excavation System.
6. Dewatering System.
2.6.3 35% Design Submittal: The design shall be complete to the 35% stage of the overall project. Submit an electronic “.pdf” copy of each item via DoD Safe, plus deliver five (5) copies of the 35% drawings (four ½ size sets and one full size set) and five (5) copies (double-sided and bound) of each item to be submitted unless otherwise noted. Review comments from the 35%
Design Submittal will be provided to the Contractor and shall be incorporated into the 65%
Design Submittal. The 35% Design Submittal shall include the following items:
1. Construction Drawings: Complete to the 35% stage overall, with no individual discipline less than 30% complete. Drawings shall include at least the following:
a. Title/Cover Sheet
b. Site Plan
c. Demolition Plans
d. Building/Structural Plans
e. Standard Details
2. Specification Outline: List of final specification sections that will be in the final specifications. (If applicable, this item is not required if specifications are included within the Construction Drawings.)
3. Major System Descriptions: Detailed scope of work including a description of construction materials.
4. Design Calculations
5. Permit Applications and Information (if applicable)
2.6.4 65% Design Submittal: Comments from the 35% Design Review are to be incorporated in the 65% Design Submittal. The 65% Design shall be complete to the 65% stage of the overall project. Submit an electronic “.pdf” copy and original file format of each item via DoD Safe, plus five (5) copies of the 65% drawings (four ½ size and one full size set) and five (5) copies
(double-sided and bound) of each item to be submitted unless otherwise noted. Review comments from the 65% Design Submittal will be provided to the Contractor and shall be incorporated into the 100% Design Submittal. The Contractor may start construction after review for conformance of the 65% Design Submittal items by the Government. The 65%
Design Submittal shall include the following items:
1. Construction Drawings: Complete to the 65% stage overall, with no individual discipline less than 60% complete. Drawings shall be detailed and reviewed.
2. Specifications: Complete and typed. (If applicable, this item is not required if specifications are included within the Construction Drawings.)
3. Construction Timeline
4. Design Calculations
5. Response to Government 35% Review Comments
2.6.5 100% Design Submittal: Comments from the 65% Design Review are to be incorporated in the 100% Design Submittal. The 100% Design shall be complete and reviewed prior to submittal. Submit an electronic “.pdf” copy and original file format of each item via DoD
Safe, plus five (5) copies of the 100% drawings (four ½ size and one full size set) and five (5) copies (double-sided and bound) of each item to be submitted unless otherwise noted. Review comments from the 100% Design Submittal will be provided to the Contractor and shall be incorporated into the Final Design Submittal. The 100% Design Submittal shall include the following items:
1. Construction Drawings: Drawings shall be complete, detailed and reviewed.
2. Specifications: Complete and typed. (If applicable, this item is not required if specifications are included within the Construction Drawings.)
3. Design Calculations
4. Response to Government 65% Review Comments
2.6.6 Final Design Submittal: After Government final review for conformance and acceptance, submit the original drawings, sealed on all sheets by a licensed engineer and/or architect who can legally represent the design firm. Submit an electronic signed and sealed “.pdf” copy and original file format of each item via DoD Safe, plus five (5) copies of the Final drawings (four
½ size and one full size set) and five (5) copies (double-sided and bound) of each item to be submitted unless otherwise noted. The Final Design Submittal shall include the following items:
1. Construction Drawings
2. Specifications (If applicable, this item is not required if specifications are included within the Construction Drawings.)
3. Design Calculations
4. Response to Government 100% Review Comments
2.6.7 Post-Construction Engineering Report: An engineering report summarizing all findings and work completed is required. Report shall be technically accurate, clear, concise, coordinated, and complete. Report shall be consistent in format, wording, referencing, and extent of descriptions. Report shall clearly and concisely convey project requirements indicated and the Professional Engineer’s judgment, recommendations, and design. As applicable, the report contents shall include but not limited to narrative descriptions, as-built drawings, photographs, and specs for materials of construction, including a compilation of approved technical submittals during construction. Submit to the Contracting Officer an electronic “.pdf” copy via DoD Safe, signed and sealed by a licensed engineer. The following submittals are required:
1. Draft of Engineering Report: Draft for Government review and comment.
2. Final Engineering Report: Signed and sealed.
2.7 DURATION OF REVIEWS: The Contractor shall allow for the number of consecutive calendar days specified below, as the time required by the Government to review each design submittal. The time for review begins upon receipt of the submittal by the Contracting Officer.
Site Survey Report and Demolition Plan 14 Calendar Days
35%, 65%, and 100% Design Submittal 21 Calendar Days
Final Design Submittal 14 Calendar Days
Engineering Report 14 Calendar Days
2.8 DESIGNER OF RECORD REVIEW REQUIREMENTS: Review and acceptance of construction submittals, identified in the design specifications by the Designer of Record (DOR), shall be forwarded to the Contracting Officer for informational purposes. The DOR is responsible for review and acceptance of all construction submittals, including but not limited to the following: technical construction type (catalog cut sheets, product data, shop drawings, samples, and certificates), test reports (factory and field), design data (calculations, mix designs, analyses or other data pertaining to a part of work), manufacturer’s instructions, and manufacturer’s field reports.
2.9 GEOTECHNICAL DESIGN: Previous reports have been provided for informational purposes. Contractor assumes all responsibilities and costs associated with the demolition operations, foundation design and construction. Contractor shall retain the services of a regional geotechnical consultant registered as a Professional Engineer in the state of North Carolina and who has experience in the site’s local soil conditions. After reviewing the site investigation, soil borings, and laboratory testing for completeness of the design, if the Contractor’s geotechnical consultant determines that additional geotechnical investigation is necessary, the Contractor shall assume all costs for additional investigations and/or studies. Additional geotechnical investigations shall be coordinated with the Contracting Officer Representative (COR) and shall not interfere with normal Coast Guard operations. The cost of additional required geotechnical work shall be included in the Contract Sum.
3. CONTRACT DOCUMENTS: Drawings and the accompanying specifications are the property of the Government and comprise legal documentation that pertains exclusively to this project. Drawings will be made available in a format determined by the solicitation method.
CEU Cleveland will not provide hard copies of drawings.
3.1 Construction Drawings: None
3.2 Construction Documents: CEUC USCG Approved Equipment Enrollment Catalog.pdf
CEUC Equipment Enrollment Form.xlsx
CAD Support Files.zip
3.3 Reference Drawings: C24395201 USCG Concept Design.pdf
RSTF As-Builts.pdf
C19055066D.pdf
C19055066 Temp Shoring.pdf
DT Shop Dwgs by Metromont.pdf
PC Wall Shop Dwgs by Metromont.pdf
3.4 Reference Documents: C19055066X.pdf
C19055066 BOD.pdf
Geotechnical Report by Terracon.pdf
Geotechnical Report by GET Solutions.pdf
Infiltration and Pavement Design Report by GET
Solutions.pdf
Structural Report by WSP.pdf
SECTION 01 14 00
CONTRACTOR WORK HOURS
1. WORK HOURS: Accomplish work during normal unit operational hours of 6:00 a.m. to
6:00 p.m., Monday through Friday unless otherwise approved by the Coast Guard. Note any departures from these work hours on the Daily Reports. Any activities that require Government supervision and/or acceptance shall be scheduled at least 24 hours in advance and occur between
7:30 a.m. and 4:00 p.m., Monday through Friday unless otherwise approved by the Coast Guard.
2. SATURDAY, SUNDAY AND HOLIDAYS: The contractor shall provide the
Contracting Officer's Representative at least forty-eight hours advance notice prior to working on weekends or Federal holidays. The Government may reject any such request without impacting the completion time of the contract.
3. CONTRACT COMPLETION: The contractor shall complete work within the time frame indicated upon issuance of the Notice to Proceed. Limitations imposed by these work hours will not entitle the Contractor additional time to complete the project. Refer to FAR Clause 52.211-10
"Commencement, Prosecution and Completion of Work".
4. RAPIDGATE PROGRAM: US Coast Guard Base Elizabeth City has implemented the
RAPIDGate Program for their security protocol. The contractor shall register with RAPIDGate and obtain security passes in accordance with the instructions below prior to commencing any on site work.
RAPIDGate Program Enrollment Information
1. Enroll your company by calling 1-877-RAPIDGate (1-877-727-4342)
To enroll your company in the RAPIDGate Program, please go to the following web address to fill out the enrolment forms, https://eform.rapidgate.com/ . On the enrollment forms you will need to provide your USCG Base Elizabeth City Sponsor Contracting Officer Representative
(COR) point of contact, including a name, phone number, and e-mail address Mr. Ronald Haight at 252-470-7414, Ronald.A.Haight@uscg.mil. USCG Base Elizabeth City must authorize your request to participate in the RAPIDGate Program. The minimum elapsed time from company enrollment to an employee receiving his or her RAPIDGate Credential is approximately two weeks. If you would like additional information please call Eid Passport at 1-877- RAPIDGate
(1-877-727-4341). A customer service representative will give you all the necessary information regarding the RAPIDGate Program.
If your company is already enrolled in the RAPIDGate Program at another installation, it may request access for its employees at this installation by calling 1-877-RAPIDGate (1-877-727-
4341). Once your company is approved by USCG Base Elizabeth City, your employee who already holds a RAPIDGate Credential may be able to use the same credentials at the additional installation.
2. Employees register at onsite registration stations.
Once your company has been approved for the enrollment and paid the enrollment fee your company will receive an email with you company’s RAPIDGate Company Code. Instruct your employees who need access to USCG Base Elizabeth City to register at the self-service registration station located at USCG Base Elizabeth City. Each employee should be ready to provide your company’s RAPIDGate company code, his or her address, phone number, date of birth, and Social Security Number. The registration station will capture the employee’s photograph for credentialing and fingerprints for identity verification.
Assisted registration at your company’s location may be available if you have 50 or more employees to register. Call 1-877-RAPIDGate (1-877-727-4341) for details.
3. The RAPIDGate Program performs background screening and credentialing.
Once your company has approved each employee for participation and paid the registration fee, the RAPIDGate Program performs identity authorization and background screening. Your company will be notified when qualified employees may pick up their personalized RAPIDGate
Credentials at the USCG Base Elizabeth City Pass and ID. Each employee must show proof of https://eform.rapidgate.com/ mailto:Ronald.A.Haight@uscg.mil identity by presenting one form of identification from List A, or two forms of identification from list B (next page) to retrieve their credentials.
After activating their RAPIDGate Credentials, employees present their credentials to request entry to USCG Base Elizabeth City, and must wear and display the credentials at all times while on the installation. Questions about the USCG Base Elizabeth City RAPIDGate Program should be addressed to info@rapidgate.com with the subject line RE: RAPIDGate Program.
Forms of acceptable identification for picking up your credentials:
List A – one needed
• U.S. Passport (unexpired)
• Permanent Resident Card or Alien Registration Receipt Card (Form I-551)
• Unexpired foreign passport, with I551 stamp or attached form I-94 indicating unexpired employment authorization
• Unexpired employment authorization document that contains a photograph (Form
I-766, I-688, I-688A, or I668B)
List B – two needed
• Driver’s License or ID card issued by a state
• ID card issued by federal, state, or local government agencies or entities
• School ID card with a photograph
• Voter’s registration card
• U.S. Military or draft record
• Military dependent’s ID card
• U.S. Coast Guard Merchant Mariner Card
• Native American Tribal Document
• Drivers License issued by a Canadian government authority
• U.S. Social Security card issued by the Social Security Administration
• Certificate of Birth Abroad issued by the Department of State (Form FS-545 or
DS 1350)
• Original or certified copy of a birth certificate issued by a state, country, municipal authority or outlying possession of the Unites States bearing an official seal.
• U.S. Citizen ID Card (Form I-197)
• ID Card for use of resident citizen in the United States (Form I-179)
• Unexpired employment authorization document issued by DHS (other than those listed in list A)
SECTION 01 14 13
PRE-BID SITE VISITS
1. GENERAL: Bidders are responsible for visiting the site to field verify existing conditions and determine actual dimensions and the nature of the work required. Failure to visit the site does not relinquish the bidder from determining the extent and scope of the work mailto:info@rapidgate.com required and estimating the difficulty and cost to complete the project. Requests for equitable adjustments, in either time or money, arising from failing to field verify site conditions may be denied. Provisions regarding the site visit requirements are outlined in FAR Clause 52.236-3
“Site Investigation and Conditions Affecting the Work”.
2. SITE VISIT: Arrange pre-bid site visits to Base Elizabeth City to verify existing conditions with Mr. Ronald Haight, CEU Cleveland Detachment at (252) 470-7414.
SECTION 01 14 14
PRE-CONSTRUCTION SITE CONDITIONS
1. SITE CONDITION VERIFICATION: The Contractor shall verify the conditions of the existing site, equipment and facilities potentially affected by the work under this contract and photograph and/or videotape the conditions in order to document their pre-construction condition. Copies of the photos and videos shall be submitted to the Contracting Officer prior to starting work.
2. UTILITIES: The contractor shall use proactive measures such as digging, metering, testing, underground utility location devices, and utility company location services to locate all underground utilities identified in the area of work at no additional expense to the Government.
Additional cost of unplanned outages and repair of damaged utilities, including emergency repairs by others, not properly identified by the Contractor shall be the Contractor’s responsibility.
SECTION 01 14 16
COORDINATION
1. INTERFERENCE WITH COAST GUARD OPERATIONS: Accomplish work in a manner that causes minimal impact on normal operations. The Contractor shall notify the
Contracting Officer’s Representative at least five working days in advance of any planned outages of water, electrical, telephone, or sanitary facilities. Notify the Contracting Officer’s
Representative at least one week prior to beginning construction.
2. MILITARY STATION REGULATIONS:
2.1 The Contractor, his employees, and subcontractors shall become familiar with and obey all station regulations. All personnel employed on the project shall keep within the limits of the work and avenues of ingress and egress, and shall not enter any other areas outside of the site of the work unless required to do so in the performance of their duties. The Contractor's equipment shall be conspicuously marked for identification.
2.2 There shall be NO SMOKING in any Coast Guard building. Smoking shall only occur in designated smoking areas.
2.3 Storage Areas: The Contracting Officer’s Representative will determine exact location and boundaries of staging areas. Under no circumstances shall materials be stored in areas that will interfere with airfield operations.
2.4 Storm Protection: If a high wind warning or higher is issued, take precautions to minimize any danger to persons and protect the work and nearby Government property.
Precautions shall include, but not be limited to, temporary construction fences, barriers, closings, removing loose materials, tools and equipment, etc. from exposed locations. Remove and secure scaffolding and temporary work. Close openings in the work area if storms of lessor intensity are imminent.
3. INTERFERENCE WITH AIRFIELD OPERATIONS:
3.1 Scheduling: Schedule work to accommodate aircraft operations. The Government will make every effort to schedule aircraft operations so as to permit the maximum amount of time for contractor activities. However, in the event of an emergency, intense operational demand, adverse wind conditions, and other such unforeseen difficulties, the contractor shall discontinue operations at the specified locations in the aircraft operation area for the safety of the contractor and military personnel and the protection of Government property. Submit a schedule to the
Contracting Officer describing work to be accomplished, work locations relative to distances from buildings, runways, etc., and dates and times work is scheduled. Keep the Contracting
Officer and the Contracting Officer’s Representative apprised of any changes to this schedule.
3.2 Hazards to Airfield and Heliport Operations: Follow strict precautions regarding aircraft operations for all construction work within proximity of runways, taxiways, parking aprons, runway end zones and within 100 feet on either side of runways and taxiways. Park equipment in an area designated by the Contracting Officer’s Representative and under no circumstances shall equipment be parked overnight or for any extended period of time in proximity to runways or taxiways. Do not store materials in aircraft operation areas.
3.3 Airfield Fence Removal: To accommodate for demolition operations, the airfield fencing may be removed as long as temporary fencing, equipment, and operations remain a minimum
100 feet from the runways and taxiways. Temporary fencing shall be chain link and match height of existing fencing. Disturbed airfield fencing shall be replaced in kind. The Contractor shall submit a schedule as required in Item 3.1.
3.4 Dust and Debris: Prevent the spread of dust and debris to avoid the creation of a nuisance or hazard in the surrounding area. Due to the active runway nearby the project site, minimize generation of small items of debris that could migrate to the runway. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
SECTION 01 14 19
FIELD ADJUSTMENTS
1. Field adjustments are those alterations that do not affect time, price, or intent of the contract documents. All field adjustments shall be documented in the Daily Reports and on the
As-Built Drawings.
SECTION 01 18 14
BUILDING PERMITS
1. NO BUILDING PERMITS from state or local governments are required for work performed on federal property. Courtesy permits may be obtained at the Contractor's option. No payment will be made to the Contractor for any permit cost. Design changes to obtain courtesy permits, even at no cost, will not be allowed without written approval of the Contracting Officer.
SECTION 01 18 17
ENVIRONMENTAL PERMITS
1. Unless directed by other sections of this specification, the Contractor will not be responsible for obtaining environmental permits.
SECTION 01 26 13
REQUESTS FOR INFORMATION
1. SUMMARY:
A. Section Includes: Administrative requirements for requests for information.
2. DEFINITIONS:
A. Request for Information: A document submitted by the Contractor requesting clarification of a portion of the contract documents, hereinafter referred to as RFI (Request for
Information).
B. Proper RFIs: A properly prepared request for information shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested.
1. RFIs shall be sequentially numbered.
2. Drawings shall be identified by drawing number and location on the drawing sheet.
3. Specifications shall be identified by Section number, page and paragraph.
C. Improper RFIs: RFIs that are not properly prepared.
1. Improperly prepared RFIs will not be processed by the Contracting Officer, but will be returned unprocessed.
D. Frivolous RFIs: RFIs that request information that is clearly shown on the Contract
Documents.
1. Frivolous RFIs may be returned unprocessed.
3. CONTRACTOR’S REQUESTS FOR INFORMATION:
A. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Contracting Officer shall be requested to make a clarification of the indeterminate item.
1. Wherever possible after contract award, such clarification shall be requested at the next site visit by the Contracting Officer’s Representative (COR), with the response entered on the daily reports. When clarification at the COR’s site visit is not possible either because of the urgency of the need, or the complexity of the item, Contractor shall prepare and submit an
RFI to the Contracting Officer.
B. Contractor shall endeavor to minimize the number of RFIs. In the event that the process becomes unwieldy, in the opinion of the Contracting Officer because of the number and frequency of the RFIs submitted, the Contracting Officer may require the Contractor to abandon the process and submit future requests as either submittals, substitutions or requests for change.
C. RFIs shall be submitted on the form provided by the Contracting Officer. Forms completely filled in, and if prepared by hand, shall be fully legible after electronic transmission.
Each page of the attachments to RFIs shall bear the RFI number in the upper right corner.
D. RFIs shall be originated by the Prime Contractor.
1. RFIs from subcontractors or material suppliers shall be submitted through, reviewed by, and signed by the Prime Contractor prior to submitting to the
Contracting Officer.
2. The Contracting Officer will neither act on nor respond to RFIs received directly from subcontractors or suppliers.
E. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract
Documents will be deemed either Improper or Frivolous as defined above.
F. In cases where RFIs are issued to request clarification of coordination issues, for example, pipe and duct routing, clearances, specific locations of work…