This is a Statement of Work (SOW) for baghouse filter replacement services at the Naval Surface Warfare Center Crane (NSWC-CR) in Indiana.

The contractor shall provide all necessary personnel, equipment, tools, materials, and transportation to replace filters within baghouse machines (fabric filters/dust collectors) at Building 365 and Building 366. For Building 365, the contractor must provide and install 84 new cartridge filters and one new Air Actuator, repair actuator tubing, and install one inspection port in the exhaust stack. All work requires provision of lifts, labor, and a service truck. For Building 366, the contractor must provide and install 480 new cartridge bag filters, cages, clamps, gaskets, and venturis, and replace the filter for the Mikropul dust collector, also requiring lifts, labor, and a service truck. Used filters shall be placed in Government-supplied receptacles for disposal by the Government.

The contractor must comply with all applicable safety, security, and environmental regulations, including OSHA standards (29 CFR Part 1910), EM 385-1-1 safety requirements, and load handling equipment operations standards for equipment exceeding 2,000 lbs. lifting capacity. Hot work permits from the fire department are required. Security compliance with NSWCCRANEINST 5510.1A and 5530.1A is mandatory, and contractor personnel must be U.S. Citizens with proper identification, providing personal information five days in advance of work. All work shall be performed in Government spaces under applicable security regulations. The technical point of contact is Marty Terry at 812-854-8407 or marty.s.terry2.civ@us.navy.mil.

View the file

Other files

File Type Posted
SOW_REVISED_5_6_26-1.pdf PDF
SOW REVISED 5_6_26.pdf PDF
Solicitation Amendment N0016426Q01190002 SF 30.pdf PDF
CDRL_A001_5_6_26.pdf PDF
MikroPul Owners Manual.pdf PDF
VISITOR REQUIREMENTS -N0016426Q0119.pdf PDF
Baghouse QA.pdf PDF
Solicitation Amendment N0016426Q01190001 SF 30.pdf PDF
C07_ WD_15-4821 (1).txt TXT text file
Solicitation - N0016426Q0119.pdf PDF
C07_WH_1313_Poster.govc.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement A: Approved for Public Release; Distribution is unlimited.

Statement of Work Baghouse Filter Replacement Services

1.0 Scope

The purpose of this requirement is for the replacement of filters within the baghouse machines (also known as a fabric filter or dust collector) at Building 365 and Building 366. These efforts include providing all necessary personnel, equipment, tools, materials, and transportation to perform the requirement defined in this Statement of Work (SOW).

2.0 Applicable Documents

• Occupational Safety and Health Act (OSHA) (Public Law 91-596)

• Occupational Safety and Health Administration (29 CFR Part 1910)

• Safety and Occupational Health Requirements (EM 385-1-1)

• NSWCCRANEINST 5510.1A Security Policy, Procedures, and Program Manual

• NSWCCRANEINST 5530.1A Physical Security Policy Manual

3.0 Performance Requirements

3.1 General: The contractor shall provide and operate all required equipment for repair of the baghouse equipment at Building 366 of Naval Surface Warfare Center Crane (NSWC-CR).

Contractor will ensure all necessary permits and licenses are obtained to operate machinery IAW with all Federal and State Laws as well as any additional compliances required by the DoD and Navy as noted in 2.1 of this SOW. All load handling equipment (LHE) operations are required to be completed in accordance with EM 385-1-1, Chapter 16. The requirements apply to all LHE with a hoisting or lifting capacity over 2,000 lbs. (907.2 kg). LHE includes cranes, derricks, hoists, and power-operated equipment (excavators, forklifts, rough terrain equipment) when used with rigging that can raise, lower, and horizontally move a suspended load.

3.1.1 The contractor shall ensure hot work permits are obtained from fire department in accordance with EM385-1-1.

3.2 Building 365 Baghouse:

3.2.1 The contractor shall provide all necessary lifts, labor, and a service truck to complete the Building 365 baghouse repairs.

3.2.2 The contractor shall provide and install 84 new cartridge filters and one (1) new Air Actuator. Used cartridge filters shall be placed in Government-supplied receptables for disposal by the Government.

3.2.3 The contractor shall repair actuator tubing and install one (1) one inspection port in the exhaust stack of the Building 365 system.

3.3 Building 366 Baghouse

3.3.1 The contractor shall provide all necessary lifts, labor, and a service truck to complete the Building 366 baghouse repairs.

3.3.2 The contractor shall provide and install 480 new cartridge bag filters, cages, clamps, gaskets, and venturis. Used bag filters shall be placed in Government-supplied receptables for disposal by the Government.

3.3.3 The contractor shall provide and replace the filter for the Mikropul dust collector.

4.0 Security

The Contractor shall comply with the Security requirements of NSWCCRANEINST 5510.1A and NSWCCRANEINST 5530.1A. Government escorts may be required depending on the classification of the building or location and the work required. Foreign national visitors will require special approvals prior to visiting the Command and require Government escorts.

4.1 The Contractor personnel shall provide personal identifying information in advance of any personnel that will be traveling to NSWC Crane Indiana to the Government point of contact.

Must be an authorized employee of the contractor. Employee must be a U.S. Citizen with proper identification. The Contractor personnel will be required to work in Government spaces and may require Government escort. The Contractor is required to coordinate with the Government the dates that access will be required for any work efforts five days in advance.

The Government reserves the right to deny access for any request.

4.2 The Contractor personnel shall physically access government facilities and installations for purpose of the work to be performed within government spaces. Individuals supporting these efforts shall comply with the latest security regulations applicable to the Government facility/installation.

4.2.1 Depending on the facility, contractor personnel shall present a proper form of identifications(s) and vehicle proof of insurance or vehicle rental agreement. Employee must be a U.S. Citizen with proper identification.

4.2.2 All Contractor personnel engaged in work while on government property shall be subject to inspection of their vehicles at any time by the government and shall report any known or suspected security violations to be local host Security Department.

5.0 Occupational Safety, Health and Environmental Requirements

The contractor shall be responsible for ensuring the safety of all company employees, other working personnel, and Government property. The contractor is solely responsible for compliance with the Occupational Safety and Health Act (OSHA) (Public Law 91-596) and the resulting applicable standard, OSHA Standard 29 CFR 1910 (general), and for the protection, safety and health of their employees and any subcontractors assigned to perform work under this Purchase Order. These regulations apply to all related work, as defined in the regulations. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.

6.0 Technical Point of Contact

Name: Marty Terry

Telephone: 812-854-8407

Email: marty.s.terry2.civ@us.navy.mil mailto:marty.s.terry2.civ@us.navy.mil