C04h Attachment 8 Estim Quant 1240BH26R0013.xlsx

XLSX spreadsheet 33 KB Posted

Attached to
GAOA Blanchard Springs Caverns Tunnel Rehabilitation in Ozark-St. Francis NF
Solicitation number
1240BH26R0013
Issued by

About this file

This is an Engineer's Estimate of Probable Cost document detailing bid items and quantities for the Blanchard Springs Caverns Tunnel Rehabilitation project under USDA Forest Service solicitation 1240BH26R0013. The project encompasses structural stabilization, safety upgrades, and infrastructure replacement across the Dripstone and Discovery Trail systems within the Ozark-St. Francis National Forest. The estimate is organized into three major work categories: mining/tunneling, lighting, and handrails, with associated electrical distribution and controls.

The mining and tunneling scope includes rockbolt installation (totaling 382 units of 6-foot and 8-foot epoxy-coated threaded rebar), geosynthetic mesh installation (approximately 5,690 square feet), shotcrete application (27 cubic yards), airlock and security door replacement across multiple cave entrances and exits, suspended ceiling demolition, utility relocation, scaling and power washing, instrumentation installation, and bypass tunnel work. The lighting and handrail scope encompasses removal and replacement of existing fixtures across multiple cave chambers and areas, installation of various guardrail types (Types A through I totaling approximately 13,500 linear feet), PVC sheathed MC cable installation (approximately 22,000 linear feet), electrical distribution equipment upgrades including panelboards and disconnects for both Dripstone and Discovery areas, and new lighting control systems with programming and startup. The project assumes continuous work with caverns closed to the public during construction; Discovery Trail work is restricted to May 1 through September 1 annually due to bat species constraints. Units of measure include lump sum (LS), each (EA), square feet (SF), cubic yards (CY), and linear feet (LF).

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MiningTunneling Bid Items

Item No.Item DescriptionUnitQuantity
Dripstone Cave Entry
Dripstone Cave Entry - Elevator Room
Demolition of suspended ceilingLS1
Move Utilities/ducts prior to rockbolting and scalingLS1
Scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA27
8 ft long #5 epoxy coated threaded rebar rockbolt and resinEA20
Geosynthetic meshSF740
Dripstone Cave Entry - Between Airlock Doors
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA42
Geosynthetic meshSF660
Demolish existing airlock doors and install 2 sets of new doors/framesLS1
Airlock door bulkhead inspection and repairsLS1
Airlock doors and framesEA2
Dripstone Cave Entry - Airlock Doors to Cave Interface
Demolition of existing timber and beam support, scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA18
8 ft long #5 epoxy coated threaded rebar rockbolt and resinEA7
Geosynthetic meshSF400
5-inch thick shotcrete application to one wallLS1
Fiber reinforced shotcreteCY3
Install instrumentationLS1
Dripstone Cave Bypass Tunnel
Scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA220
8 ft long #5 epoxy coated threaded rebar rockbolt and resinEA28
Geosynthetic meshSF3615
Demolish existing door and install new door/frameLS1
Bypass door bulkhead inspection and repairsLS1
Door and FrameEA1
Install instrumentationLS1
Dripstone Cave Exit
Dripstone Cave Exit - Cave Interface to Airlock Doors
Scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA38
8 ft long #5 epoxy coated threaded rebar rockbolt and resinEA7
Geosynthetic meshSF710
Install instrumentationLS1
Dripstone Cave Exit - Between Airlock Doors
Scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA24
Geosynthetic meshSF400
Demolish existing airlock doors and install 2 sets of new doors/framesLS1
Airlock door bulkhead inspection and repairsLS1
Airlock doors and framesEA2
Dripstone Cave Exit - Airlock Doors to Security Doors
Demolition of steel beam and plate roofing, scaling, power wash, and cleanLS1
Install rockboltsLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA18
8-inch thick shotcrete applicationLS1
Fiber reinforced shotcreteCY24
Demolish existing security doors and install new doors/framesLS1
Security door bulkhead inspection and repairsLS1
Security doors and framesEA1
Dripstone Cave Exit - Security Doors to Cave Exit
Demolish pipe and chain link cover, scaling, power wash, and cleanLS1
Install rockbolts and meshLS1
6 ft long #5 epoxy coated threaded rebar rockbolt and resinEA15
Geosynthetic meshSF265
Discovery Cave Exit
Demolish existing airlock doors and install 2 sets of new doors/framesLS1
Airlock door bulkhead inspection and repairsLS1
Airlock doors and framesEA2
Demolish existing security doors and install new doors/framesLS1
Security door bulkhead inspection and repairsLS1
Security doors and framesEA1
Notes:
1. SF - square foot
2. CY - cubic yard
3. EA - each
4. AC - acre
5. LS - lump sum
6. LF - linear foot
Assumptions: Continuous work allowed, Caverns will be closed to the public during construction. Discovery Trail work can only be done between May 1 and September 1 each year due to bat species constraints.

Golder Associates Inc. &"-,Bold"&12Engineer's Estimate of Probable Cost Blanchard Springs Caverns Tunnel Rehabilitation USDA Forest Service

Rev. 0 &P of &N &D

LightingHandrail Bid Items

Item No.Item DescriptionUnitQuantity
Mobilization and Demobilization
Dripstone - Entrance Tunnels and Rubble Piles
Handrails
Remove Existing RailingsLF160
Type A - Guide Rail with Midrail and PostsLF42
Type B - Toe-Guardrail with Guardrail infill w/ ToebedLF66
Type C - Guardrail with Infill and HandrailLF17
Type D - Wall Mounted HandrailLF18
Type G - Guardrail with Double HandrailLF17
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA38
AREA, AREA AMB, AREA BL, AREA Y & EEA5
FL, FL BL, FL Y, FLMEA22
B - TUNNEL WEATHR PROOF 4' LINEAR STRIP LIGHTEA3
BE - TUNNEL WP LINEAR 4' STRIP LIGHT w/EMERGENCY BATTERYEA2
FLLEA3
FLXLEA1
WEA2
RAILING LIGHTLF33
PVC SHEATHED MC CABLE #10 AWGLF1160
VISITORS CENTER TELEPHONE INCL SIGNAL WIRE / RELAYSEA2
Dripstone - Cathedral Room I
Handrails
REMOVE EXISTING RAILINGSLF913
TYPE A - GUIDE RAIL WITH MIDRAIL & POSTSLF88
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF10
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF544
TYPE D - WALL MOUNTED HANDRAILLF3
TYPE G- GUARDRAIL WITH HANDRAILLF248
TYPE G- GUARDRAIL WITH DOUBLE HANDRAILLF3
TYPE H- HANDRAIL WITH MIDRAILLF17
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA167
AREA, AREA AMB, AREA BL, AREA Y & EEA28
FL, FL BL, FL Y, FLMEA85
FL BWEA7
FLLEA4
SP, SPLEA18
WEA25
PVC SHEATHED MC CABLE #10 AWGLF3340
Dripstone - Cathedral Room II
Handrails
REMOVE EXISTING RAILINGSLF1137
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF101
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF500
TYPE D - WALL MOUNTED HANDRAILLF1
TYPE G- GUARDRAIL WITH HANDRAILLF525
TYPE I- GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF10
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA106
AREA, AREA AMB, AREA BL, AREA Y & EEA15
FL, FL BL, FL Y, FLMEA80
FL BWEA1
FLAMBEA2
FLLEA1
WEA7
PVC SHEATHED MC CABLE #10 AWGLF2120
Dripstone - Connecting Tunnel
Handrails
REMOVE EXISTING RAILINGSLF271
TYPE A - GUIDE RAIL WITH MIDRAIL & POSTSLF252
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF7
TYPE D - WALL MOUNTED HANDRAILLF12
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA3
AREA, AREA AMB, AREA BL, AREA Y & EEA3
RAILING LIGHTEA249
PVC SHEATHED MC CABLE #10 AWGLF1520
Dripstone Coral Room Entrance
Handrails
REMOVE EXISTING RAILINGSLF236
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF50
TYPE D - WALL MOUNTED HANDRAILLF114
TYPE G- GUARDRAIL WITH HANDRAILLF62
TYPE I- GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF10
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA30
AREA, AREA AMB, AREA BL, AREA Y & EEA3
FL, FL BL, FL Y, FLMEA16
WEA11
PVC SHEATHED MC CABLE #10 AWGLF600
Dripstone Coral Room
Handrails
REMOVE EXISTING RAILINGSLF1075
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF438
TYPE G- GUARDRAIL WITH HANDRAILLF566
TYPE H- HANDRAIL WITH MIDRAILLF16
TYPE I- GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF55
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA139
AREA, AREA AMB, AREA BL, AREA Y & EEA32
FL, FL BL, FL Y, FLMEA78
FL BWEA5
FLAMBEA3
FLLEA4
FLXLEA1
SP, SPLEA6
WEA10
PVC SHEATHED MC CABLE #10 AWGLF2780
Dripstone Exit Tunnel
Handrails
REMOVE EXISTING RAILINGSLF273
TYPE D - WALL MOUNTED HANDRAILLF15
TYPE G- GUARDRAIL WITH HANDRAILLF258
GATESEA1
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA20
WEA20
PVC SHEATHED MC CABLE #10 AWGLF400
Discovery - Entrance Room and Discovery Room
Handrails
REMOVE EXISTING RAILINGSLF1118
TYPE B- GUARDRAIL WITH GUARDRAIL INFILL W/ TOE BRDLF36
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF513
TYPE D - WALL MOUNTED HANDRAILLF152
TYPE F- GUIDERAIL VARYING HEIGHTLF8
TYPE G- GUARDRAIL WITH HANDRAILLF383
TYPE I- GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF26
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA143
AREA, AREA AMB, AREA BL, AREA Y & EEA4
FL, FL BL, FL Y, FLMEA20
FL BWEA20
FLAMBEA4
FLXMLEA4
FLXLEA4
SP, SPLEA1
WEA86
PVC SHEATHED MC CABLE #10 AWGLF2860
Discovery - Stick Room, First and Second Barren
Handrails
REMOVE EXISTING RAILINGSLF688
TYPE B - GUARDRAIL WITH GUARDRAIL INFILLLF156
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF146
TYPE G- GUARDRAIL WITH HANDRAILLF386
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA62
AREA, AREA AMB, AREA BL, AREA Y & EEA5
FL, FL BL, FL Y, FLMEA12
FL BWEA18
FLAMBEA1
FLXMLEA1
SP, SPLEA2
WEA23
PVC SHEATHED MC CABLE #10 AWGLF1240
Discovery - Campsite
Handrails
REMOVE EXISTING RAILINGSLF40
TYPE A - GUIDE RAIL WITH MIDRAIL & POSTSLF6
TYPE B - GUARDRAIL WITH GUARDRAIL INFILLLF2
TYPE G- GUARDRAIL WITH HANDRAILLF32
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA17
AREA, AREA AMB, AREA BL, AREA Y & EEA1
FL, FL BL, FL Y, FLMEA4
FL BWEA9
WEA3
PVC SHEATHED MC CABLE #10 AWGLF340
Discovery - Natural Entrance Area
Handrails
REMOVE EXISTING RAILINGSLF1309
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF533
TYPE B- GUARDRAIL WITH GUARDRAIL INFILL W/ TOE BRDLF202
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF278
TYPE G- GUARDRAIL WITH HANDRAILLF148
TYPE G- GUARDRAIL WITH DOUBLE HANDRAILLF126
TYPE I- GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF22
GATE PREMIUMEA4
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA80
AREA, AREA AMB, AREA BL, AREA Y & EEA1
FL, FL BL, FL Y, FLMEA10
FL BWEA9
UW EEA2
UWFL AMBEA1
UWFLEA11
UWFLLEA1
UWFL BWEA15
UWFLMEA5
WEA25
PVC SHEATHED MC CABLE #10 AWGLF1600
Discovery - Stalactiflats
Handrails
REMOVE EXISTING RAILINGSLF241
TYPE B - GUARDRAIL WITH GUARDRAIL INFILLLF31
TYPE D - WALL MOUNTED HANDRAILLF48
TYPE G- GUARDRAIL WITH HANDRAILLF162
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA31
AREA, AREA AMB, AREA BL, AREA Y & EEA2
FL, FL BL, FL Y, FLMEA10
FL BWEA15
SP, SPLEA4
PVC SHEATHED MC CABLE #10 AWGLF620
Discovery - Salamander Pool Room
Handrails
REMOVE EXISTING RAILINGSLF481
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF84
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF53
TYPE F - GUIDERAIL VARYING HEIGHTLF22
TYPE G- GUARDRAIL WITH HANDRAILLF322
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA31
AREA, AREA AMB, AREA BL, AREA Y & EEA1
FL, FL BL, FL Y, FLMEA13
FL BWEA11
FLAMBEA1
FLMXLEA5
PVC SHEATHED MC CABLE #10 AWGLF620
Discovery - No Name Room and Wind Tunnel
Handrails
REMOVE EXISTING RAILINGSLF486
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF123
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF85
TYPE G- GUARDRAIL WITH HANDRAILLF278
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA52
AREA, AREA AMB, AREA BL, AREA Y & EEA4
FL, FL BL, FL Y, FLMEA11
FL BWEA3
FLAMBEA3
WEA31
PVC SHEATHED MC CABLE #10 AWGLF1,040
Discovery - Christmas Tree Room
Handrails
REMOVE EXISTING RAILINGSLF305
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF158
TYPE G- GUARDRAIL WITH HANDRAILLF147
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA15
AREA, AREA AMB, AREA BL, AREA Y & EEA1
FL, FL BL, FL Y, FLMEA7
FLAMBEA3
UWFLEA1
FLMXLEA1
STRING (100' STRING, 20 BULBS PER)EA2
PVC SHEATHED MC CABLE #10 AWGLF300
Discovery - Giant Flowstone Room
Handrails
REMOVE EXISTING RAILINGSLF1,088
TYPE A - GUIDE RAIL WITH MIDRAIL & POSTSLF3
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF107
TYPE B- GUARDRAIL WITH GUARDRAIL INFILL W/ TOE BRDLF37
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF403
TYPE E - GUARDRAIL WITH GUARDRAIL INFILLLF51
TYPE F - GUIDERAIL VARYING HEIGHTLF61
TYPE G- GUARDRAIL WITH HANDRAILLF426
GATE PREMIUMEA2
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA66
AREA, AREA AMB, AREA BL, AREA Y & EEA1
FL, FL BL, FL Y, FLMEA13
FL BWEA23
FLAMBEA1
FLLEA11
WEA17
PVC SHEATHED MC CABLE #10 AWGLF1,320
Discovery - Heart Attack Hill and Ghost Room
Handrails
REMOVE EXISTING RAILINGSLF867
TYPE B- GUARDRAIL WITH GUARDRAIL INFILLLF9
TYPE C - GUARDRAIL WITH INFILL AND HANDRAILLF50
TYPE G- GUARDRAIL WITH HANDRAILLF612
TYPE I - GUIDERAIL W/ HANDRAIL VARYING HEIGHTLF196
Lighting
REMOVE EXISTING LIGHT FIXTURES & DISPOSEEA158
AREA, AREA AMB, AREA BL, AREA Y & EEA7
FL, FL BL, FL Y, FLMEA19
FL BWEA26
FLAMBEA9
SPXLEA10
WEA87
PVC SHEATHED MC CABLE #10 AWGLF3,160
Dripstone - Distribution Equipment
ELECTRICAL DISTRIBUTION
SAFE OFF & REMOVE PANELBOARDSEA6
SAFE OFF & REMOVE DISCONNECTEA4
REMOVE FEEDERSLF892
NEW PANELBOARDS - 60AEA2
NEW PANELBOARDS - 30AEA1
ADD FOR GROUNDINGEA3
SERVICE RATED - NEW DISCONNECTS - 150AEA1
NEW DISCONNECTS - 150AEA1
NEW DISCONNECTS - 60AEA1
NEW DISCONNECTS - 30AEA1
FEEDER REPLACEMENT - CONDUITS TO BE REUSEDLF892
MISC ELECTRICAL
DUPLEX RECEPTACLE, WPEA11
TELEPHONE CABINETEA4
Discovery - Distribution Equipment
ELECTRICAL DISTRIBUTION
SAFE OFF & REMOVE PANELBOARDSEA14
SAFE OFF & REMOVE DISCONNECTEA1
REMOVE FEEDERSLF3,065
NEW PANELBOARDS - 50AEA6
NEW PANELBOARDS - 30AEA4
ADD FOR GROUNDINGEA4
NEW DISCONNECTS - 150AEA2
NEW DISCONNECTS - 50AEA2
TRANSFORMER 200AEA2
TRANSFORMER 150AEA2
FEEDER REPLACEMENT - CONDUITS TO BE REUSEDLF3,065
MISC ELECTRICAL
DUPLEX RECEPTACLE, WPEA15
TELEPHONE CABINETEA9
Dripstone - Lighting Controls
NEW LIGHTING CONTROLS
PROGRAMMING / STARTUPLS1
BELDEN 9841 WIRE IN 1/2" PVC CONDUITLF2,644
RELAY, 2/E603EA9
CS' - ASSUME LUMENLINK PRO, 1/E603EA13
Discovery - Lighting Controls
NEW LIGHTING CONTROLS
EQUIPMENT / FRONT ENDLS1
BELDEN 9841 WIRE IN 1/2" PVC CONDUITLF7,920
RELAYEA19
CONTROL PANELEA31
Notes:
1. SF - square foot
2. CY - cubic yard
3. EA - each
4. AC - acre
5. LS - lump sum
6. LF - linear foot
Assumptions: Continuous work allowed, Caverns will be closed to the public during construction. Discovery Trail work can only be done between May 1 and September 1 each year due to bat species constraints.

Golder Associates Inc. &"-,Bold"&12Engineer's Estimate of Probable Cost Blanchard Springs Caverns Tunnel Rehabilitation USDA Forest Service

Rev. 0 &P of &N &D