C04a Attachment 1 SOW BSC 1240BH26R0013.docx
DOCX document 73 KB Posted
- Solicitation number
- 1240BH26R0013
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for the Blanchard Springs Caverns Tunnel Rehabilitation and Safety Improvements project under USDA Forest Service contract 1240BH26R0013. The project encompasses infrastructure repairs and safety upgrades to the Dripstone and Discovery Trail sections of Blanchard Springs Caverns in the Ozark-St. Francis National Forest. Work includes structural stabilization of tunnel entrances and exits, masonry repairs using existing cavern rock, installation of instrumentation and monitoring equipment, replacement of air lock doors, security doors, suspended ceiling systems, lighting and distribution components, safety handrails, and mine phone systems. All work must comply with attached Golder and JLA Drawings and Specifications, with handrail work disregarded from Golder documents and reflected only in JLA documents. Surface area sinkhole work is excluded from contract scope.
The SOW establishes 11 base bid line items and 5 optional line items, all valued as lump sum (LSQ) payments. Base work includes mobilization, Dripstone cave entrance rehabilitation, masonry repairs, bypass tunnel work, cave exits for both Dripstone and Discovery trails, lighting and handrail replacement for both trails, and mine phone system replacement. Optional items cover additional handrail work in Natural Entrance Area, Stalactiflats, Salamander Pool Room, Giant Flowstone Room, and Heart Attack Hill and Ghost Room. Critical requirements include Forest Service personnel presence during all underground work, mandatory four-hour environmental and archaeological training for all personnel, White-nose Syndrome decontamination protocols compliance, noise limitation (65dB maximum), and staged work with specific seasonal restrictions (winter months for Dripstone entrance work; May through August for Dripstone exit and Discovery trail work). Key deliverables due within 20 days of Notice to Proceed include construction progress schedule, schedule of values, and electronic document submittal service. All contractors must submit product data, shop drawings, and testing reports for concrete, masonry, FRP doors, electrical systems, railings, and lighting components for Contracting Officer approval prior to work commencement.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Government Furnished | 3 |
| 5.0 Deliverables / Schedule | 3 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 4 |
| Attachment | 4 |
PROJECT
BLANCHARD SPRINGS CAVERNS TUNNEL REHABILITATION AND SAFETY IMPROVEMENTS
GENERAL INFORMATION
1.0 Scope of Work
This project includes all labor, equipment, supplies, testing & inspections, and incidentals necessary for the Blanchard Springs Caverns (BSC) Dripstone and Discovery Trail Infrastructure repairs and safety upgrades. All work shall conform to the attached Drawings and Specifications. All work shall be performed by qualified and licensed contractors for all trades applicable. Work includes but is not limited to structural stabilization of tunnel entrance and exits, disposal and removal of existing supports, masonry repairs, Installation of Instrumentation & monitoring equipment, replacement of existing air lock doors at entrance and exits, replacement of existing security doors at entrance and exits, replacement of existing suspended ceiling system, components, and associated ductwork, replacement of existing bypass tunnel door, replacement of existing lighting and distribution system components, replacement of existing safety handrails, and replacement of the existing mine phone system and components.
· Cavern Access & Monitoring Requirements
· Forest personnel must always be present on site with non-Forest personnel and contractors while they are working within the underground portions of the Caverns. Entry and exit into the cavern shall be controlled by US Forest Service personnel. For all non-Forest Service individuals, each entry into and exit from the cavern must be documented.
· All contractor personnel, team members, and monitors will be required to complete a training module prior to first entry into the cavern environment and construction zone (approximately 4 hours). The training will be focused on the Caverns environment, species, and significance and sacred nature of the space in which this construction project will take place.
· The Forest archaeological monitor, or archaeological monitoring services secured by the Forest will be available during all rock displacement activities in the Caverns to ensure archaeological concerns are addressed and workers stay within the approved work area.
· All clothing, footwear, equipment, and other items brought into the cave would be decontaminated according to the USFWS’s White-nose Syndrome Decontamination Protocols posted at https://www.whitenosesyndrome.org/mmedia-education/nationalwnsdecontamination-protocol-u-s. (USDOI FWS 2020)
· Shoe-clean troughs to prevent transport of dust, oil or any foreign material into and out of the cave shall be utilized.
· Structural Rehabilitation Repairs
· Any equipment that emits fossil fuel exhaust shall not be used inside the caverns and must be staged outside of the cavern environment.
· All removed timber supports and associated components must be disposed of offsite and according to jurisdictions having authority.
· Existing cavern rock must be used for all masonry repairs within the cavern.
· Native material originating from within the cavern, such as breakdown, shall not be removed from the cavern. Coordinate with CO for disposal location within the cavern.
· Air Lock Doors
· A temporary noise and containment barrier wall system shall be installed for construction and renovation of the air locks and bypass tunnel. To the maximum extent practicable, barriers shall be pre-assembled outside of the cave and brought into the cave for installation.
· Sound levels shall not exceed 65dB.
· Only one air lock shall be removed and replaced or modified at any one time.
· Lighting & Handrails
· To the maximum extent practicable, existing lighting fixtures, handrails, and wiring shall be replaced with new components within the same footprint of the existing.
· If replacement fixtures require welding or soldering, they must be pre-assembled outside of the cave and brought into the cave for installation.
· An area outside of the air lock shall be designated to modify or assemble replacement fixtures not requiring welding or soldering.
· Mine System Phones
· It is the intent to replace all existing phones and wiring components within the caves. See Drawings.
2.0 Background
· Original metal hand- and guardrails (i.e., safety railing), rock bolts (i.e., threaded steel bars utilized to stabilize jointed or fractured rock layers in mines or tunnels), incandescent lighting fixtures, wiring and air locks are still in place, but have corroded, compromising their functionality and safety. Degraded components of the original air locks at the cavern trail entrance and exit points have created gaps that allow outside air to enter the cavern environment. Utility service lines supporting communication systems within the caverns have also degraded in the humid cavern environment and affect the staff’s ability to reliably communicate to the surface in the event of an emergency.
· In 2015, an inspection completed by the Mine Safety & Health Administration (MSHA) identified potential hazards associated with horizonal tension fractures in the natural rock above the Dripstone trail entrance air lock and tunnel where loose rock had been falling (USDOL MSHA 2015). Temporary mitigation measures (i.e., timber supports) were installed as MSHA recommended. The timber support structure has been inspected regularly by an agency geologist since its installation. The structure continues to function as designed but is showing signs of deterioration. A design for air lock door replacement and renovation of constructed tunnels was completed in 2021 and included in the above scope of work; see Drawings and Specifications for construction.
· In 2023, an engineering firm contracted to assess the condition of existing railing, lighting and electrical components of the Dripstone and Discovery trails and to identify needs for additional railing to meet current requirements concluded the electrical systems do not meet current electrical code requirements and have reached the end of their service life (JLA 2023). Some electrical components pose safety hazards which include delivery of mild electrical shocks to staff changing bulbs and electrical breaker boxes have caught fire. A design to address these deficiencies has been completed and included in the above scope of work; see Drawings for construction.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements / Tasks
3.1 The Contractor is required to closely coordinate with the CO to perform all work per attached Drawings and Specifications and adhere to the requirements referenced in the attached Environmental Assessment, which includes a Memorandum of Agreement among the United States Forest Service & Tribal Stakeholders, and a Biological Opinion completed with the US fish and Wildlife Service.
3.2 Work is divided into 2 sets of plan documents that will be referred to as the Golder Drawings and Specifications for the BSC Tunnel Rehabilitation portion of the project, and the JLA Drawings and Specifications for the BSC Handrail and Lighting portion of the project.
3.2.1 Disregard all handrail work referenced in the Golder Drawings and Specifications. All handrail work and quantities are reflected in the JLA Drawings and Specifications.
3.3 No Surface Area Sinkhole work will be conducted under this contract. Disregard Surface Area Sinkhole work and omit from Bid.
3.3.1 Therefore, Golder Drawing Sheet C-15, page 18 of 18, Specification Section 310000_ Earthwork, and Section 329219_ Seeding will not be utilized.
3.4 Administrative process and procedures outlined in the Golder specifications such as progress schedule, schedule of values, progress payments, substitution procedures, and submittal procedures shall also apply to all JLA portions of the work.
3.5 See Schedule of Items below:
SCHEDULE OF ITEMS:
| Item No |
| Description |
| Method of Measurement |
| Pay Unit |
| Est. Quantity |
| Unit Price |
| Amount Estimated |
| 1 |
| Mobilization |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 2 |
| Dripstone Cave Entrance (Golder) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 3 |
| Masonry Repairs (Golder) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 4 |
| Dripstone Cave Bypass Tunnel (Golder) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 5 |
| Dripstone Cave Exit (Golder) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 6 |
| Discover Cave Exit (Golder) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 7 |
| Dripstone Lighting and Distribution Equipment (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 8 |
| Dripstone Handrails (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 9 |
| Discovery Lighting and Distribution Equipment (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 10 |
| Discovery Handrails Portion of Christmas Tree Room (158' of Type C) & Giant Flowstone Room (51' of Type E) (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 11 |
| Mine Phone System (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
TOTAL ESTIMATED AMOUNT
| Option Item |
| Description |
| Method of Measurement |
| Pay Unit |
| Est. Quantity |
| UNIT PRICE |
| AMOUNT ESTIMATED |
| 12 |
| Natural Entrance Area Handrails (519' of Type B; 140' of Type B w/toeboard; 70' of Type C; 58' of Type G) (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 13 |
| Stalactiflats Handrails (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 14 |
| Salamander Pool Room Handrails (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 15 |
| Giant Flowstone Room Handrails (Exclude portion reflected in Base Item) (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
| 16 |
| Heart Attack Hill & Ghost Room Handrails (JLA) |
| LSQ |
| LS |
| 1 |
| $ . |
| $ . |
TOTAL ESTIMATED OPTION AMOUNT
BLANCHARD CAVERNS PROPOSED RENOVATION SCHEDULE.
| Task Name |
| Recommended Timeframe |
| Restriction |
| Dripstone Cave Entrance - Elevator Room |
| Winter months |
| None |
| Dripstone Cave Entrance - Between Airlock Doors |
| Winter months |
| None |
| Dripstone Cave Entrance - Cave Interface |
| Winter months |
| None |
| Dripstone Cave Bypass Tunnel |
| Winter months |
| None |
| Dripstone Cave Exit - Cave Interface to Airlock |
| May through August |
| None |
| Dripstone Cave Exit - Between Airlock Doors |
| May through August |
| None |
| Dripstone Cave Exit - Airlock Doors to Security Doors |
| May through August |
| None |
| Dripstone Cave Exit - Security Doors to Cave Exit |
| May through August |
| None |
| Dripstone Trail lighting system replacement |
| Any time of year |
| None |
| Dripstone Trail handrail replacement |
| Limit to summer months/ active season |
| September through April |
| Discovery Trail lighting system replacement |
| May through August |
| September through April |
| Discovery Trail handrail replacement |
| May through August |
| September through April |
| Discovery Cave Exit |
| May through August |
| September through April |
Building Reconstruction
Any time of year
None
| VIC Landscaping (excluding tree removal) |
| Spring for planting, any time of year for other work |
| None |
VIC Landscaping tree removal During winter months or if during bat active season, see design criteria
Biologist clearance required
| Roof and Gutter Replacement |
| Any time of year |
| Biologist clearance required |
3.6 Elevator Room & Dripstone Cave Entrance (Golder)
3.6.1 Review Golder Specification 011000 Summary_ 1.02 Summary of Work_ A
3.6.1.1 Note: See Golder Specification 095100 Suspended Tile Ceilings. See JLA Drawing sheet E-101 Elevator Lobby Plan. It is the Forest Service Intent to replace the suspended ceiling system per the JLA Drawing. Coordinate with the CO on any discrepancies.
3.7 Dripstone Bridge (Golder)
3.7.1 Review Golder Specification 011000 Summary_ 1.02 Summary of Work_ B
3.8 Dripstone Cave Bypass Tunnel (Golder)
3.8.1 Review Golder Specification 011000 Summary_ 1.02 Summary of Work_ C
3.9 Dripstone Cave Exit (Golder)
3.9.1 Review Golder Specification 011000 Summary_ 1.02 Summary of Work_ D
3.10 Discovery Cave Exit (Golder)
3.10.1 Review Golder Specification 011000 Summary_ 1.02 Summary of Work_ E
3.11 Dripstone Lighting and Distribution Equipment (JLA)
3.11.1 Full replacement of lighting fixtures, controls, and distribution equipment will be paid for under this item.
3.11.1.1 All associated testing and inspection of services are incidental to this pay item
3.12 Dripstone Handrails (JLA)
3.12.1.1 Full replacement of Handrails per Base Bid Plans and Option Bid Plans. Provide bid amounts for both Base and Option totals. See JLA Drawings.
3.13 Discovery Lighting and Distribution Equipment (JLA)
3.13.1 Full replacement of lighting fixtures, controls, and distribution equipment paid for under this item.
3.13.1.1 All associated testing and inspection of services are incidental to this pay item.
3.13.1.1.1 Drawings were developed consisting of Base Bid Items and Option Items due to uncertainty of future available funding. The Forest Service elected to change the following Option Item to a Base Bid Item after Drawings were already produced. Contractor to include the following Item in Base Bid Quantity
3.13.1.1.1.1 JLA Drawing Sheets E-501 through E-512 are moved from option to Base Bid.
3.14 Discovery Handrails (JLA)
3.14.1.1 Full replacement of Handrails per Base Bid Plans. See JLA Drawings.
3.14.1.1.1 Drawings were developed consisting of Base Bid Items and Option Items due to uncertainty of future available funding. The Forest Service elected to change the following Option Item to a Base Bid Item after Drawings were already produced. Contractor to include the following Item in Base Bid Quantity
3.14.1.1.1.1 JLA DRAWING SHEET C-509 (79 OF 97) CHRISTMAS TREE ROOM
3.14.1.1.1.1.1 Include 158 Linear Feet of Type C railing into Base Bid.
3.15 Mine Phone System (JLA)
3.15.1.1 Full replacement of all phones throughout Dripstone and Discovery sections of the caverns.
3.16 Natural Entrance Area Handrails_ Option Item (JLA)
3.16.1.1 The Natural Entrance Area is part of the Discovery Tour section. Provide bid for full replacement of Handrails per Option Bid Plans. See JLA Drawings.
3.17 Stalactiflats Handrails_ Option Item (JLA)
3.17.1.1 The Stalactiflats room is part of the Discovery Tour section. Provide bid for full replacement of Handrails per Option Bid Plans. See JLA Drawings.
3.18 Salamander Pool Room Handrails_ Option Item (JLA)
3.18.1.1 The Salamander Pool Room is part of the Discovery Tour section. Provide bid for full replacement of Handrails per Option Bid Plans. See JLA Drawings.
3.19 Giant Flowstone Room Handrails_ Option Item (JLA)
3.19.1.1 The Giant Flowstone Room is part of the Discovery Tour section. Provide bid for full replacement of Handrails per Option Bid Plans. Exclude the portion of handrails already accounted for in the Base Bid Line Item (See Contractor Requirements 3.14). See JLA Drawings.
3.20 Heart Attack Hill & Ghost Room Handrails_ Option Item (JLA)
3.20.1.1 The Heart Attack & Ghost Room is part of the Discovery Tour section. Provide bid for full replacement of Handrails per Option Bid Plans. See JLA Drawings.
4.0 Government Furnished
List any government-furnished support, data, property or facilities. Describe government responsibility for reviewing and approving reports and final products generated under the contract. If the contractor will require access to government facilities, identify the facility location and specific area. Identify any federal holidays or other times when access may be restricted.
Insert Government Furnished Here
5.0 Deliverables / Schedule
Key Deliverables
| Item No. |
| Deliverable |
| Objective |
| Due |
| 01 |
| Construction Progress Schedule |
| Submit Project Schedule for review and approval Ref. Golder.013216; 1.04 Submittals |
| Preliminary – 10 days after Notice To Proceed (NTP) |
Final – 20 days after NTP
| 02 |
| Schedule of Values |
| Submit Schedule of Values to adhere to price and payment procedures Ref. Golder.01200; 1.03 & 1.04 |
| Final – 20 days after NTP |
| 03 |
| Electronic Document Submittal Service & Submittal Schedule |
| Submit Project Management Information System for approval and submittal schedule Ref. Golder.013000; 3.01 Ref. Golder. 013000; 3.10 |
| Final – 20 days after NTP |
| 04 |
| Temporary Noise & Contaminant Barriers |
| Submit proposal for barrier system Ref. Golder.015619; 1.04 Submittals |
| Coordinate with CO for submission and approval prior to mobilization to site |
| 05 |
| Temporary Erosion & Sediment Control |
| Submit schedule and construction drawing for temporary & permanent erosion control work if applicable Ref. Golder.015713; 1.03 Submittals |
| Coordinate with CO to identify applicable areas and submit for approval prior to beginning work in associated areas, or per agreed upon timeframes stemming from Pre-Work Meeting. |
| 06 |
| Execution & Closeout Requirements |
| Adhere to Submittal requirements for Administration Requirements Ref. Golder.013000, 1.04 Submittals A & B (To include all product data, testing reports, & shop drawings) |
| Coordinate with CO for submission and approval of all plans prior to beginning work where appropriate or per agreed upon timeframes stemming from Pre-Work Meeting. |
| 07 |
| Concrete Reinforcing, Shotcrete, Maintenance of Unit Masonry, Masonry Mortaring, Stone Masonry |
| Adhere to all submittal requirements for all Concrete and Masonry work Ref. Golder.032000; 1.04 Submittals_ Golder.033713; 1.04 Submittals_ Golder.040120; 1.03 Submittals_ Golder.040513; 1.04 Submittals_ Golder.044300; 1.04 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 08 |
| Fiberglass Reinforced Plastic (FRP) Doors & FRP Resin transfer Molded Door Frames |
| Submit product data, drawings, samples, & O&Ms Ref. Golder.082200; 1.04 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 09 |
| Balanced Door Entrances |
| Adhere to submittal requirements Ref. Golder.084236; 1.05 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 10 |
| Suspended Tile Ceilings |
| Adhere to submittal requirements Ref. Golder.095100; 1.03 Submittals; JLA Drawing E-101 Elevator Lobby Plan (takes precedence) |
| Coordinate with CO for submission and approval prior to start of work |
| 11 |
| Special Wall Surfacing |
| Adhere to submittal requirements Ref. Golder.097700; 1.04 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 12 |
| Cable Tray for Electrical Systems |
| Submit product data & shop drawings Ref. Golder.260536; 1.02 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 13 |
| Instrumentation & Monitoring |
| Adhere to submittal requirements Ref. Golder.310913; 1.02 Submittals |
| Coordinate with CO for submission and approval prior to start of work |
| 14 |
| Ground Support with Rock Bolting & Geosynthetic Mesh |
| Submit drawings and installation procedures and adhere to section 013300 Ref. Golder.313313; 1.03 Submittals |
| Submit at least 30 days prior to planned installation |
| 15 |
| Pipe and Tube Railings |
| Submit product data, shop drawings, and finish samples for each type Ref.JLA.055213; 1.3 & 1.4 |
| Coordinate with CO for submission and approval prior to start of work |
| 16 |
| Division 26 Electrical Components |
| Adhere to all submittal requirements per Ref. JLA.260519; JLA.260526; JLA.260529; JLA.260533.13; JLA.260533.16; JLA.260553, JLA.262416, JLA.262716; JLA.262726, JLA.262813; JLA.262816 |
| Coordinate with CO for submission and approval prior to start of work |
| 17 |
| Lighting |
| Submit Product Data, Certificates, Luminaire Fittings, samples, and drawings per specification Ref. JLA.265000; 1.3-1.7 |
| Coordinate with CO for submission and approval prior to start of work |
| 18 |
| Closeout Submittals |
| Adhere to Submittal requirements for Project Record Documents, Operations & Maintenance (O&M) Data, and Warranties & Bonds Ref. Golder.017800; 1.03 Submittals |
| Project Record Documents – due at the time of final payment |
O&M Data – Prior to Start of Work Warranties & Bonds – 10 days after acceptance & completion per specification.
| 19 |
| Demonstration & Training |
| Coordinate with CO to satisfy submittal requirements Ref. Golder.017900; 1.03 Submittals |
| Coordinate with CO |
6.0 Travel
Identify any travel requirements, locations involved, number of trips (if known), and duration of anticipated travel. Specify responsibility for travel reimbursement, e.g., the contractor or the Government. If the travel will be reimbursed by the Government, discuss the method of reimbursement, e.g., in accordance with Federal/agency travel regulations. State the Government official authorized to approve contractor travel, e.g., the Contracting Officer or Contracting Officer Representative.
Insert Travel Here
7.0 Contractor’s Key Personnel
Describe positions which are considered key to successful performance of the contract and the information required to support key personnel qualifications, e.g., experience which correlates to SOW requirements, education, and past performance on similar projects. Specify if resumes are required and provide resume format if appropriate.
Insert Contractor’s Key Personnel Here
8.0 Security Requirements
Specify security requirements that apply to the contract performance. Specify the level of clearances required and identify positions that are applicable.
Insert Security Requirements Here
9.0 Data Rights
If data is to be produced, furnished, acquired, or used in meeting contract requirements, delineate the respective rights and obligations of the government and the contractor regarding the use, production, and disclosure of that data.
Insert Data Rights Here
10.0 Section 508 – Electronic and Information Technology Standards When information technology is to be acquired, include language describing Section 508 requirements.
Insert Section 508 Here
Attachment
· Environmental Assessment
· Golder Drawings
· Golder Specifications
· JLA Drawings
· JLA Specifications
· Schedule of Items
· Golder Findings & Recommendations Report
· Golder & JLA Work Items Spreadsheet image1.png