C04_Attachment 5 Boiler 3 - Specifications.pdf
PDF 2 MB Posted
- Attached to
- WRRC Boiler Upgrades Federal contract opportunity
- Solicitation number
- 1232SA26R0033
About this file
This is a technical specifications document for Boiler 3 as part of the WRRC Boiler Upgrades solicitation (1232SA26R0033) issued by the Department of Agriculture Agricultural Research Service. The document establishes the detailed technical requirements and performance standards that the replacement boiler must meet to satisfy the upgrade project objectives.
The specifications define the boiler's operational parameters, including capacity requirements, efficiency standards, pressure ratings, and safety compliance measures necessary for installation at the facility. The document outlines performance expectations, material specifications, and design requirements to ensure the replacement unit integrates properly with existing systems and meets all applicable federal and industry standards. Contractors responding to this solicitation must ensure their proposed equipment fully complies with these technical specifications to be considered responsive to the requirement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_1232SA26R0033_Amd_0002.pdf | ||
| RFI-AE Responses.docx | DOCX document | |
| 33PLMs-1-20-26-4384058_R1257169.pdf | ||
| 8LEADs-1-20-26-4384048_R1257169.pdf | ||
| Sol_1232SA26R0033_Amd_0001.pdf | ||
| C04_Sol_1232SA26R0033.pdf | ||
| C04_Attachment 3 Boiler 2 - Specifications.pdf | ||
| C04_Attachment 8 Schedule of Pricing.xlsx | XLSX spreadsheet | |
| C04_ Attachment 1 Boiler 1 - Specifications.pdf | ||
| C04_Attachment 6 Boiler 3 - Drawing Binder.pdf | ||
| C04_Attachment 7 Wage Determination CA20260018.pdf | ||
| C04_Attachment 2 Boiler 1 - Drawings Binder.pdf | ||
| C04_Attachment 4 Boiler 2 - Drawings Binder.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WRRC BOILER UPGRADES
CONTRACT #3
SPECIFICATIONS
A/E CONTRACT: 12905B24D0002
A/E TASK ORDER: 12905B25F0033
WESTERN REGIONAL RESEARCH CENTER (WRRC)
Albany, CA
Prepared For:
U.S. DEPARTMENT OF AGRICULTURE
Agricultural Research Service
Prepared By:
THE JOHNSON-McADAMS FIRM, P.A.
Greenwood, Mississippi
February 20, 2026
WRRC Boiler Upgrades Contract #3 1525NO3
TASK ORDER #: 12905B25F0033
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 01 01/20 WARRANTY OF CONSTRUCTION
01 00 11 06/20 GENERAL PARAGRAPHS
01 00 21 01/20 CONTRACTOR QUALITY CONTROL
01 01 00 February 29, 2024 GENERAL REQUIREMENTS
01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS
01 33 00 08/18 SUBMITTAL PROCEDURES
01 35 26 01/20 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 50 00 01/20 PROJECT CLOSEOUT
01 57 50 10/19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 05/22, CHG 2: 08/24 COMMON PIPING FOR HVAC
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 11 20 05/20 FACILITY GAS PIPING
23 21 23 08/17 HYDRONIC PUMPS
23 52 46.00 20 05/15, CHG 3: 08/18 LOW PRESSURE WATER HEATING BOILERS
(OVER 800,000 BTU/HR OUTPUT)
DIVISION 26 - ELECTRICAL
26 05 13 08/25 MEDIUM-VOLTAGE CABLES
26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 13 13 11/21 METAL-CLAD SWITCHGEAR
26 20 00 05/25, CHG 1: 08/25 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 05/22 AGGREGATE BASE COURSE
DIVISION 33 - UTILITIES
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS Page 2
SECTION 01 00 01
WARRANTY OF CONSTRUCTION
01/20
PART 1 GENERAL
1.1 WARRANTY OF CONSTRUCTION
1.1.1 General
In addition to any other warranties set out elsewhere in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the project. The final acceptance of the project can only be determined by the Contracting Officer and the Contractor will be notified in writing of the official final acceptance. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. In addition, the Contractor shall remedy at his own expense any damage to Government owned or controlled real or personal property, when that damage is the result of the Contractor's failure to conform to contract requirements or any such defect of equipment, material, workmanship, or design. The Contractor shall also restore any work damaged in fulfilling the terms of this clause. The Contractor's warranty with respect to work repaired or replaced hereunder will run for one year from the date of such repair or replacement.
1.1.2 Notification and Compliance
The Government shall notify the Contractor in writing within a reasonable time after the discovery of any failure, defect, or damage. Should the Contractor fail to remedy any failure, defect, or damage described in paragraph 1.1.1 above within a reasonable time after receipt of notice thereof, the Government shall have the right to replace or repair and have the cost billed to the Contractor.
1.2 EXPRESSED WARRANTY
In addition to the other rights and remedies provided by this clause, all subcontractors', manufacturers', and suppliers' warranties expressed or implied, respecting any work and materials shall, at the direction of the Government, be enforced by the Contractor for the benefit of the Government. In such case, if the Contractor's warranty under paragraph
1.1.1 above has expired, any suit directed by the Government to enforce a subcontractor's, manufacturer's, or supplier's warranty shall be at the expense of the Government. The Contractor shall obtain any warranties which the subcontractors, manufacturers, or suppliers would give in normal commercial practice. If so directed by the Contracting Officer, the Contractor shall require any such warranties to be executed in writing to the Government.
1.3 LATENT DEFECTS
The Warranty specified herein shall not limit the Government's rights with respect to latent defects, gross mistake, or fraud.
SECTION 01 00 01 Page 1
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 00 01 Page 2
SECTION 01 00 11
GENERAL PARAGRAPHS
06/20
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.1.1 Work To Be Done
The work to be done consists of furnishing all labor, materials, and equipment and performing all work in strict accordance with these specifications for the modification to the WRRC facility located in Albany, CA as indicated in all of the construction documents. The Contractor is responsible for protecting and storing the equipment prior to turnover to the government. Any damage to the existing equipment shall be repaired or equipment replaced at no additional cost to the Government.
1.1.2 Location
The site of work is at the USDA Western Regional Research Center, 800 Buchanan Street, Albany, CA 94710.
1.1.3 Principal Features of Work
Replacement of existing Natural Gas Condensing Boilers and Pumps serving the West Annex Building (WAB) located at the Western Regional Research Center (WRRC). The project also includes installation of zone controllers, thermostats, and electronic control valves on various existing heating water coils located throughout the WAB.
1.2 SITE VISIT
USDA WRRC will conduct a single pre-bid site inspection for all interested contractors that will be coordinated with Thomas Goebel. Site visit access requirements will be issued to responsive contractors.
Contact:
U.S. Department of Agriculture, ARS Attn: Thomas Goebel Western Regional Research Center (WRRC) Albany, CA 94710 thomas.goebel@usda.gov 1-510-559-6331
1.3 COORDINATION OF WORK
1. Work space and space available for storing materials shall be subject to the approval of the Contracting Officer. Do not store materials and equipment in other than assigned areas.
2. Execute work so as to interfere as little as possible with normal functioning of the facility, including operations of utility services and any existing equipment, and with work being done by others. All interruptions shall be coordinated and scheduled a minimum of (2) full weeks in advance.
SECTION 01 00 11 Page 1
3. Minimize interference of construction activities with the flow of traffic by keeping roads, walks and entrances to grounds, to parking areas and to occupied areas of buildings clear of construction materials, debris, construction equipment and vehicles except where noted on plans or in specifications. Provide unobstructed access to areas required to remain in operation.
4. The Contractor shall complete all work within 365 consecutive calendar days after Notice to Proceed. Within 14 calendar days after Contract Award, the Contractor shall provide the Government with a detailed schedule of dates on which the Contractor plans to accomplish the work. In addition, the Contractor shall notify the Contracting Officer 20 days in advance of starting work. A planned work schedule shall be submitted to the Contracting Officer for approval. The schedule shall include a detailed description of the methods and equipment to be used for each operation and the sequence of operations. This schedule shall be updated monthly and submitted to the Contracting Officer for approval.
5. The Contractor shall take all measures and provide all material necessary for protecting existing equipment, property, and ongoing operations in affected areas of construction against dust, noise and debris.
6. Power sources for the Contractor's operations will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of the Government's facilities. Water sources will be available and supplied by the Government to the Contractor as long as its use does not interfere with the operations of any building. The Contractor is responsible for extending utility sources to his work locations. Such extensions shall be removed after work is completed, to the satisfaction of the Contracting Officer.
7. All references in the specifications to the Contracting Officer and Contracting Officer's Representative shall constitute referrals initially to the Contracting Officer's Representative.
8. Contractor shall provide sanitary facilities for use by his employees and the employees of his subcontractors working on job site.
1.4 DRAWINGS
All dimensions shown of existing work and all dimensions required for work that is to be connected with existing work shall be verified by the Contractor by actual field measurements. Any work at variance with that specified or shown on the drawings, shall not be performed by the Contractor until the Contractor has received approval in writing from the Contracting Officer.
1.5 MATERIAL SAFETY DATA SHEETS (MSDS)
Material Safety Data Sheets must be submitted to the Contracting Officer prior to the commencement of any work with any substance that may be considered hazardous.
1.6 UTILITIES OR STRUCTURAL ITEMS CONFLICTING WITH PROPOSED CONSTRUCTION
In the event the Contractor finds an area where existing utilities or
SECTION 01 00 11 Page 2 structural items conflict with proposed construction, the Contracting Officer shall be notified immediately. The Contractor shall then propose a method of solving the problem. Work shall not resume in the problem area until the Contractor has received written approval from the Contracting Officer. There shall be no additional cost to the Government.
1.7 ACCEPTANCE OF WORK
1. Final inspection will not be made until the contract work is completed. The Contractor shall notify in writing the Contracting Officer fifteen working days prior to the date on which the work will be ready for final inspection.
2 Final inspection and acceptance of the work shown by the drawings and specifications forming a part of this contract shall not be binding or conclusive on the Government if it shall be shown that (1) the Contractor has willfully or through collusion with persons or firms engaged in the performance of the contract supplied inferior materials, equipment, or workmanship, or (2) the Contractor has otherwise departed from the terms of the contract.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 00 11 Page 3
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 00 11 Page 4
SECTION 01 00 21
CONTRACTOR QUALITY CONTROL
01/20
PART 1 GENERAL
1.1 GENERAL
This section covers the quality control inspection, sampling, and testing of all materials, services, and workmanship required to be performed by the contract drawings, specifications, and other contract requirements.
The Contractor shall perform all quality control inspection, sampling, and testing required by this contract and shall review and certify that each submittal is correct and in strict conformance with the contract drawings and specifications for all shop drawings and lists of materials, fixtures, and equipment. All work performed under this contract shall be in strict accordance with procedures and requirements detailed on the plans and specifications.
1.1.1 Certificate of Compliance
Upon completion of the contract work and prior to final acceptance, the Contractor shall submit to the Contracting Officer a certificate of compliance which states that all materials, equipment, design, and workmanship incorporated in the work are in strict compliance with contract drawings and specifications except for approved deviations. The certificates of compliance shall be signed and dated by both the manufacturer's representative and the Contractor. Based upon this certificate of compliance and other contract requirements, the Contractor shall be responsible for correcting at his expense any defects, omissions, and deviations (other than those previously approved) which are detected during the contract period or during the one-year warranty period as defined in Section 01 00 01 , WARRANTY OF CONSTRUCTION.
1.2 INSPECTION
The Contractor shall inspect all materials, services, and workmanship to assure conformance with contract requirements.
1.3 REVIEW AND APPROVAL OF SHOP DRAWINGS, SUBMITTALS, MATERIALS, FIXTURES,
AND EQUIPMENT
1. Prior to submission to the Government for approval, the Contractor shall review and certify that all shop drawings, submittals, lists of materials, fixtures, and equipment as called for under the various headings of these specifications are correct and in strict compliance with the contract drawings and specifications. These drawings, submittals and lists shall be accurate, complete, and adequately detailed. The top copy of data comprising each item listed on the transmittal form shall be identified as having received the quality control inspector's approval by being so stamped, signed and dated.
Approval of shop drawings, submittals, materials, fixtures, and equipment by the Contracting Officer will not relieve the Contractor of the responsibility for any errors which may exist and the Contractor shall be responsible for the satisfactory construction of all work. All samples of materials submitted as required by these specifications shall be properly identified and labeled for ready identification, and upon being approved, stored at the site of the
SECTION 01 00 21 Page 1 work for jobsite use until all work has been accepted by the Contracting Officer. The Contractor shall provide four (4) sets of all shop drawings.
2. All proposed deviations required by the Contractor shall be noted in the "Remarks" column of the Form. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the shop drawing. The Government reserves the right to rescind inadvertent approval of shop drawings containing unnoted deviations.
1.4 DAILY RECORDS
The Contractor shall maintain a daily record of quality control measures performed for each shift of Contractor or Subcontractor operations on an appropriate format. These records shall provide factual evidence that continuous quality control inspections have been performed, including but not limited to the following: job progress, problems encountered;
problems resolved; type and number of inspections; results of inspections or tests including all computations; nature of defects; causes for rejection; safety violations; proposed remedial action; and corrective action taken. These records shall cover both conforming and defective items and shall include a statement that all supplies and materials incorporated in the work are in full compliance with the terms of the contract. The Contractor shall maintain a current record of all inspections and shall furnish to the Contracting Officer on a daily basis, legible copies of all inspection records for his permanent retention. The daily records of inspections shall cover all work placement subsequent to the previous report and shall be verified by the Contractor's designated representative.
1.5 RECURRING DEFICIENCIES
If recurring deficiencies in an item or items being inspected by the Contractor indicate that the inspection system is not providing adequate quality control, the Contractor shall take such corrective measures as deemed necessary by the Contracting Officer.
1.6 CONFLICTS
In the event of a difference of opinion between the Contractor and the Contracting Officer, the Contracting Officer shall govern.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 00 21 Page 2
SECTION 01 01 00
GENERAL REQUIREMENTS
February 29, 2024
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E84 (2024) Standard Test Method for Surface Burning Characteristics of Building Materials
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018; ERTA 1-2 2018) Standard for Portable Fire Extinguishers
NFPA 30 (2024) Flammable and Combustible Liquids Code
NFPA 51B (2024) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2026) National Electrical Code
NFPA 101 (2024) Life Safety Code
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926 Safety and Health Regulations for Construction
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
WORK SEQUENCING PLAN
1.3 GENERAL INTENTION
A. Contractor shall completely prepare the site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by the contract documents.
SECTION 01 01 00 Page 1
B. All employees of the general contractor and subcontractors shall comply with ARS's site-specific security management program, as identified by the ARS Location Manager, at all times on ARS property, and shall be restricted from unauthorized access.
C. Prior to commencing work:
1. The General Contractor shall provide proof that an OSHA certified "competent person" (CP) 29 CFR 1926 .20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
2. The General Contractor and Tradesmen shall receive an On-site Safety briefing from the location Facilities Manager or designated representative.
D. Training:
1. All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Construction Safety course and /or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training.
2. Submit training records of all such employees to the Contracting Officer for approval before the start of work.
1.4 PROJECT COORDINATION
A. Construction Project Schedule: See contract, FAR 52.236-15 Schedules for Construction Contracts. The Contractor will not begin work on site until the construction project schedule has been approved by the Contracting Officer. The Contractor shall submit one electronic copy of the updated construction project schedule with each progress payment request.
B. Contract Inspector's Daily Report: Contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day.
The Contract Inspector's Daily Report is to be submitted at the beginning of work each day for the previous day's work and shall be maintained throughout the term of the contract.
C. Formal Meetings: Any meeting (deemed formal by the contractor, the Contracting Officer Representative (COR) or the Contracting Officer will have the minutes of said meeting prepared by the contractor with copies provided to the COR and Contracting Officer within twenty-four (24) hours of meeting time. The minutes will include Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives).
Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provided hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number.
Issues discussed will also include an action/completion date.
1.5 SUBMITTALS - GENERAL
A. All submittals referenced by the procurement documents including but not limited to Plans, Specifications, Statements of Work (SOW), SECTION 01 01 00 Page 2
Supplemental Information, etc. shall be submitted electronically to the Contracting Officer (CO), Construction Officer Representative (COR) and Project Architect (A/E).
B. All material sample submittals referenced by the procurement documents including but not limited to Plans, Specifications, Statements of Work (SOW), Supplemental Information, etc. shall be provided to the Contracting Officer (CO), Construction Officer Representative (COR) and Location Manager/Facilities Manager (LM/FM).
C. Contractor shall provide documentation that submitted materials comply with current Buy America Act (BAA) requirements.
D. Contractor shall utilize products listed in the USDA "BioPreferred Program" to the greatest extent possible.
E. All items submitted shall be accompanied by the SUBMITTAL LOG appended to the GENERAL SPECIFICATIONS.
1. The Contractor shall maintain one (1) log for all submittals and shall update the information as required by Construction Progress.
1.6 SAFETY SUBMITTALS
A. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer.
Safety Plan shall describe how the Contractor and/or sub- contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub- contractor equipment, supplies, tools, and chemical products are to be always under the control of the Contractor, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor are subject to confiscation and will be reported to the Contracting Officer.
B. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on the attachment "DAILY INSPECTION FORM", and the form is to be signed and submitted to the Contracting Officer.
C. Contractor shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any ARS staff exceed 75 dB. Contractor shall provide to the COR with copies to the Contracting Officer a written weekly update of the test results in addition to the proposed work for the subsequent two weeks (a two week "look- ahead")involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.
SECTION 01 01 00 Page 3
D. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week "look-ahead" update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor's Competent Person shall provide the COR with a copy to the Contracting Officer written weekly documented safety inspection results.
E. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.
1.7 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The General Contractor shall provide a site-specific security plan that defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Contractor Personnel:
1. The required Contractor Personnel information and the security application procedures vary depending upon the project worksite location. Each Task Order Request for Proposal (RFP) will contain the contact information for the Location Monitor, who will be able to provide the Contractor Personnel information and security application procedures required for the specific site.
C. Security Procedures:
1. Contractor's employees shall not enter the project site without being in conformance with location's security plan. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the "regular hours" as defined in the contract, The Contractor shall give a ten (10) day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of ARS premises is allowed without written permission of the Contracting Officer.
4. ARS reserves the right to close or shut down the project site and order the Contractor's employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the Contracting Officer.
D. Document Control:
1. The Contractor is responsible for safekeeping of all drawings, SECTION 01 01 00 Page 4 project manuals and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. These documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
3. All paper waste or electronic media such as CD's and diskettes shall be shredded and destroyed in a manner acceptable to the ARS.
E. Motor Vehicle Restrictions:
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted as required by the ARS specific location before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies and Contractor must be on site to receive all deliveries.
2. Separate permits shall be issued for Contractor and its employees for parking in designated areas only.
1.8 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
ASTM E84 Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
NFPA 10 Standard for Portable Fire Extinguishers
NFPA 30 Flammable and Combustible Liquids Code
NFPA 51B Standard for Fire Prevention During Welding, Cutting and Other Hot Work
NFPA 70 National Electrical Code
NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926 . Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to the Contracting Officer for review for compliance with contract requirements. Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the contractor's competent person per OSHA requirements. This briefing shall include information on the construction limits, ARS safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of ARS equipment, etc. Documentation shall be provided to
SECTION 01 01 00 Page 5 the Contracting Officer that individuals have undergone contractor's safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police, and other emergency response forces in accordance with NFPA 241 .
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241 . For small facilities with less than 20 feet exposing overall length, separate by 10 feet.
E. Temporary Heating and Electrical: Install, use, and maintain installations in accordance with 29 CFR 1926 , NFPA 241 and NFPA 70 .
F. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Contracting Officer.
G. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to the Contracting Officer.
H. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926 , NFPA 241 and NFPA 10.
I. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926 , NFPA 241 and NFPA 30 .
J. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions 48 hours in advance and coordinate with the Location Manager and Contracting Officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the Contracting Officer. Parameters for the testing and results of any tests performed shall be recorded by the General Contractor and copies provided to the Contracting Officer.
K. Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with the Contracting Officer.
L. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with the Contracting Officer.
Designate contractor's responsible project- site fire prevention program manager to coordinate permit hot work. Contractor shall comply with current WRRC Safety, Health, and Environmental Management (SHEM) Hot Work Permit Standard Operating Procedure.
M. Fire Hazard Prevention and Safety Inspections: Inspect entire construction area daily. Coordinate with, and report findings and corrective actions weekly to the COR with a copy to the Contracting Officer. See USDA Standard Forms for Daily Inspection Form.
N. Smoking: Smoking is prohibited everywhere on site.
SECTION 01 01 00 Page 6
O. Dispose of waste and debris in accordance with NFPA 241 . Remove from buildings daily.
P. Perform other construction, alteration, and demolition operations in accordance with 29 CFR 1926 .
1.9 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C. Working space and space available for storing materials shall be as determined by the Contracting Officer.
D. Workers are subject to rules of the Location applicable to their conduct which shall be provided by the Contracting Officer.
E. Execute work to interfere as little as possible with normal functioning of Location as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure are not permitted in buildings that are occupied during construction except as permitted by the Contracting Officer where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the ARS in quantities sufficient for not more than two (2) workdays.
3. Where access by ARS personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements.
F. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the ARS operations will not be hindered. Contractor shall permit access to ARS personnel through construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by ARS so that operations will continue during the construction period.
G. Utilities Services: Existing utility services for ARS shall be maintained at all times. Provide temporary facilities, labor, materials, SECTION 01 01 00 Page 7 equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior written approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Contracting Officer's prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, Two weeks advanced notice and again 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of ARS. Interruption time approved by ARS may occur at other than Contractor's normal working hours.
4. In case of a contract construction emergency, service will be interrupted on approval of the Contracting Officer. Such approval will be confirmed in writing as soon as practical.
H. To minimize interference of construction activities with flow of ARS traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
I. Coordinate the work for this contract with other construction operations as directed by Contracting Officer. This includes the scheduling of traffic and the use of roadways, as specified in paragraph
1.11, USE OF ROADWAYS.
1.10 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the Contracting Officer or their designated representative, of areas of the building in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed, to the COR with a copy to the Contracting Officer.
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and Contracting Officer.
SECTION 01 01 00 Page 8
1.11 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re- installation and reuse. Store such items in locations as directed by Contracting Officer.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from ARS property.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the ARS during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on ARS property and, when authorized by the Contracting Officer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense.
1.13 AVAILABILITY AND USE OF UTILITY SERVICES
A. See contract, FAR Clause 52.236-14, Availability and Use of Utility Services.
1.14 TESTS
A. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
1.15 CONSTRUCTION WASTE MANAGEMENT
A. Responsibilities. The contractor shall employ processes that ensure the generation of as little waste as possible and shall avoid the
SECTION 01 01 00 Page 9 generation of waste due to the following:
1. Over-packaging.
2. Error.
3. Poor planning, layout.
4. Over ordering.
5. Breakage.
6. Mishandling.
7. Contamination.
8. General weather damage, excluding extreme acts of nature (i.e.
tornados, hurricanes, flash floods, blizzards, etc.).
B. Procedures.
1. Of the inevitable waste that is generated, as many of the waste materials as economically feasible shall be reused, salvaged or recycled.
2. Waste disposal in landfills shall be minimized to the greatest extent possible.
3. Waste Diversion Goals.
i Demolition, Major Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
ii Interior Remodeling: Minimum 10% of total project waste shall be diverted from landfill.
iii. The following waste categories, at a minimum, shall be diverted from landfill:
a) Green waste (biodegradable landscaping materials).
b) Soil.
c) Inert material (concrete, asphalt, masonry).
d) Clean dimensional wood, palette wood.
e) Engineered wood products: plywood, particle board, I-joists, etc.
f) Cardboard, paper, packaging.
g) Asphalt roofing materials.
h) Insulation.
i) Gypsum board.
j) Carpet and pad.
SECTION 01 01 00 Page 10
k) Paint.
l) Plastics: ABS, PVC.
m) Beverage containers.
C. Description of Work.
1. Includes:
i. Waste Management Plan development and implementation.
ii. Meetings to discuss goals, issues and training for the Waste Management Plan.
iii. Techniques to minimize waste generation.
iv. Sorting and separation of waste materials.
v. Reuse of salvaged materials on site.
vi. Salvage of existing materials and items for reuse or resale.
vii. Recycling of materials that cannot be reused or sold.
viii. Record keeping of receipts and records of salvaged, recycled or land filled materials.
2. Related Elements:
i. Alternates.
ii. Construction Waste Management.
iii. Site Demolition.
iv. Site Clearing.
v. Slope Protection/Erosion Control.
vi. Asphalt Concrete.
vii. Crushed Stone Paving.
viii. Portland Cement Concrete Paving.
ix. Valve Boxes.
x. Storm Sewers.
xi. Chain Link Fences and Gates.
xii. Walk, Road and Parking Appurtenances.
xiii. Miscellaneous Landscaping Materials.
xiv. Concrete, Concrete Formwork, and Concrete Reinforcement.
SECTION 01 01 00 Page 11
xv. Cast-in-Place Concrete.
xvi. Unit Masonry.
xvii. Structural Steel.
xviii. Steel Roof Deck/Steel Floor Deck.
xix. Cold Formed Metal Framing.
xx. Metal Fabrications.
xxi. Rough and Finish Carpentry.
xxii. Engineered Structural Wood.
xxiii. Plastic Lumber.
xxiv. Building Insulation.
xxv. Modified Bitumen Roofing.
xxvi. Metal Doors.
xxvii. Wood and Plastic Doors and Frames.
xxviii. Metal Support Systems.
xxix. Gypsum Wallboard.
xxx. Acoustical Treatment.
xxxi. Resilient Flooring.
xxxii. Tile and Carpet.
xxxiii. Painting.
xxxiv. Toilet Compartments.
xxxv. Louvers and Vents.
xxxvi. Signage and Graphics.
xxxvii. Ductwork and Ductwork Accessories
D. Definitions.
1. Class III Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.
2. Clean: Untreated and unpainted; uncontaminated with adhesives, oils, solvents, mastics and like products.
3. Construction and Demolition Waste: Includes all non-hazardous resources resulting from construction, remodeling, alterations, repair and demolition operations.
SECTION 01 01 00 Page 12
4. Dismantle: The process of parting out a building in such a way as to preserve the usefulness of its materials and components.
5. Disposal: Acceptance of solid wastes at a legally operating facility for the purpose of land filling (includes Class III landfills and inert fills).
6. Inert Backfill Site: A location, other than inert fill or other disposal facility, to which inert materials are taken for the purpose of filling an excavation, shoring or other soil engineering operation.
7. Inert Fill: A facility that can legally accept inert waste, such as asphalt and concrete exclusively for the purpose of disposal.
8. Inert Solids/Inert Waste: Non-liquid solid resources including, but not limited to, soil and concrete that does not contain hazardous waste or soluble pollutants at concentrations in excess of water-quality objectives established by a regional water board and does not contain significant quantities of decomposable solid resources.
9. Mixed Debris: Loads that include commingled recyclable and non-recyclable materials generated at the construction site.
10. Mixed Debris Recycling Facility: A solid resource processing facility that accepts loads of mixed construction and demolition debris for the purpose of recovering re-usable and recyclable materials and disposing non-recyclable materials.
11. Permitted Waste Hauler: A company that holds a valid permit to collect and transport solid wastes from individuals or businesses for the purpose of recycling or disposal.
12. Recycling: The process of sorting, cleansing, treating, and reconstituting materials for the purpose of using the altered form in the manufacture of a new product. Recycling does not include burning, incinerating or thermally destroying solid waste.
i. On-site Recycling. Materials that are sorted and processed on site for use in an altered state in the work, i.e., concrete crushed for use as a sub-base in paving.
ii. Off-site Recycling. Materials hauled to a location and used in an altered form in the manufacture of new products.
13. Recycling Facility: An operation that can legally accept materials for the purpose of processing the materials into an altered form for the manufacture of new products. Depending on the types of materials accepted and operating procedures, a recycling facility may or may not be required to have a solid waste facility permit or be regulated by the local enforcement agency.
14. Re-Use: Materials that are recovered for use in the same form, on-site or off-site.
15. Return: To give back reusable items or unused products to vendors for credit.
16. Salvage: To remove waste materials from the site for resale or
SECTION 01 01 00 Page 13 re-use by a third party.
17. Source-Separated Materials: Materials that are sorted by type at the site for the purpose of reuse and recycling.
18. Solid Waste: Materials that have been designated as non-recyclable and are discarded for the purposes of disposal.
19. Transfer Station: A facility that can legally accept solid waste for the purpose of temporarily storing the materials for re-loading onto other trucks and transporting them to a landfill for disposal or recovering some materials for re-use or recycling.
E. Guides: No preference is given to the recycles listed below; they are listed for the convenience of the contractor.
1. Dirt/clean fill.
2. Green/landscaping waste.
3. Concrete, asphaltic concrete.
4. Cardboard, paper, packaging.
5. Clean dimensional wood, palette wood.
6. Usable palettes.
7. Metals from banding, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized sheet steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze.
8. Carpet and pad.
9. Gypsum board.
10. Paint.
11. Insulation.
12. Asphalt shingles.
13. Beverage containers.
F. Submittals.
1. Waste Management Plan. Prior to any waste removal, the Contractor shall submit their Waste Management Plan to the ARS. The Plan shall contain the following:
i. Analysis of the estimated job site waste to be generated, including types and quantities.
ii. Proposed alternatives to land filling. Contractor shall prepare a list of each material proposed to be salvaged, re-used, or recycled during the course of the project.
iii. Methods handling of materials to be recycled.
SECTION 01 01 00 Page 14
2. On Site:
i. Materials separation
ii. Materials storage
iii. Materials protection, where applicable
3. Off site:
i Provide name of mixed debris recycling facility; include list of materials to be recycled.
ii. Procedures. A description of the means to be employed in recycling the above materials consistent with requirements for acceptance by designated facilities.
iii. Landfill Options. The name of the landfill(s) where trash will be disposed of.
a) Meetings. Contractor shall conduct Construction Waste Management meetings. Meetings shall include the Subcontractor, the Project Manager and representatives as designated by the Contracting Officer.
At a minimum, waste management goals and issues shall be discussed at pre-bid meetings, pre-construction meetings and regular job-site meetings.
b) Transportation. A description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated facilities, or whether mixed materials will be collected by a waste hauler and removed from the site) and destination of materials.
c) Waste Management Plan Implementation.
(i) Manager. The contractor shall designate an on-site party (or parties) responsible for instructing workers and subcontractors and overseeing and documenting results of the Waste Management Plan for the project.
(ii) Distribution. The contractor shall distribute copies of the Waste Management Plan to the Contracting Officer and Location Manager.
(iii) Instruction. The contractor shall provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse and return methods to be used by all parties at appropriate stages of the project.
(iv) Separation Facilities. The contractor shall lay out and label a specific area to facilitate separation of materials for reuse, salvage, recycling, and return. Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination or mixing of materials.
(v) Hazardous Wastes. Hazardous wastes shall be separated, stored, and disposed of according to local, state and federal regulations.
4. Reports: The Contractor shall submit (monthly, quarterly, at end of
SECTION 01 01 00 Page 15 job) a Waste Management Progress Report. The report shall contain the amount (in tons or cubic yards) of material land filled from the project, the identity of the landfill, the total amount of tipping fees paid at the landfill and the total disposal cost. Include legible copies of manifests, weight tickets, receipts and invoices.