C04_Attachment 2 - Loleta Design Specs.pdf

PDF 540 KB Posted

Attached to
Loleta Water System Upgrades Federal contract opportunity
Solicitation number
12445526Q0132
Issued by
Department of Agriculture Forest Service

About this file

Summary: Section C Specifications for Loleta Recreation Area Water System Improvements – Phase 1

This document is a comprehensive technical specification for a water system improvement project at Loleta Recreation Area, a USDA Forest Service facility located in Marienville, Pennsylvania. The project scope includes installation of new water distribution piping, a well house structure, water treatment systems, electrical service, selective demolition, and site restoration. Key work items encompass a new pole-building well house with corrugated metal exterior, well modifications with pitless adapter installation, 1-inch and 2-inch HDPE water lines and 4-inch PVC water line installation, gravity storage tanks (305 gallons each), campground spigot assemblies, valve boxes, pressure testing, chlorination, water quality testing, and commissioning. The project runs from September 21, 2026 through December 11, 2026, with the upper campground loop closed to public access during construction.

The contract requires specific products including Norwesco 305-gallon water storage tanks, Haws 6252EHLF spigots, Wayne Dalton Model 8300 overhead garage doors, and NSF 61 certified potable water components throughout. Mobilization costs cannot exceed 10 percent of total contract bid price. All work must comply with current National Electric Code, International Building Code, American Concrete Institute standards, and Pennsylvania DEP regulations. The contractor must conduct certified concrete testing, hydrostatic pressure testing in the presence of the Contracting Officer's Representative, and submit two water quality test samples taken at least 24 hours apart meeting Pennsylvania MCL standards. Final deliverables include operation and maintenance manuals in both hard copy and PDF formats, as-built drawings, and on-site commissioning with hands-on training for Forest Service personnel. All invoices must be submitted via the federal Invoice Processing Platform with certified payrolls submitted at least one week prior to payment requests.

View the file

Other files for this federal contract opportunity

Other files attached to Loleta Water System Upgrades, newest first.
File Type Posted
12445526Q0132 Amendment 0001 - Extension.pdf PDF
PreBid_SignIn.pdf PDF
C04_Attachment 1 - Schedule of Items.xlsx XLSX spreadsheet
C04_Attachment 5 - Wage Rate Heavy.pdf PDF
12445526Q0132 - Loleta Water Systems Improvements.pdf PDF
C04_Attachment 4 - Wage Rate Building.pdf PDF
C04_Attachment 3 - Loleta Design Drawings.pdf PDF
C04_Attachment 1 - Schedule of Items.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C

SPECIFICATIONS FOR

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS – PHASE 1

DATED 2-11-2025

(revised 6-22-2026)

TABLE OF CONTENTS

SECTION PAGE

011000 - SUMMARY 1

011400 - WORK RESTRICTIONS 3

012700 – MEASUREMENT AND PAYMENT 5

013100 – PROJECT MANAGEMENT AND COORDINATION 11

013300 – SUBMITTAL PROCEDURES 13

014000 – QUALITY CONTROL 17

014200 – REFERENCES 20

015000 – TEMPORARY FACILITIES AND CONTROLS 24

017000 – EXECUTION REQUIREMENTS 26

017320 – SELECTIVE DEMOLITION 29

017700 – CLOSEOUT PROCEDURES 32

033000 – CAST-IN-PLACE AND PRECAST CONCRETE 35

133300 – POLE BUILDING STRUCTURES 38

221114 – WATER DISTRIBUTION 44

260500 – BASIC ELECTRICAL MATERIALS AND METHODS 55

329200 – TURF AND GRASSES 59

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 1 of 61

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 PROJECT IDENTIFICATION

A. Project Name and Location: Loleta Recreation Area Water System Improvements – Phase 1.

From the Marienville Ranger District Office located at 131 Smokey Lane, Marienville, PA 16239, travel southwest on PA-66 for 1.6 miles. Turn slight left onto South Forest Street for 0.7 miles.

South Forest Road becomes Loleta Road just before the West Millstone Road and Loleta Recreation Area will be on the left. The campground entrance is signed. GPS coordinates of the campground are N 41.401944 and W 79.081111. The Marienville Ranger District Office has a phone number of 814-927-6628 and the Allegheny National Forest Supervisors Office has a phone number of 814-728-6100.

B. Project Summary Description: The project includes the installation of new water distribution piping, spigots, valves, concrete work, well house, modification of existing electrical service, selective demolition and other project supplemental items. Work includes, but is not limited to, the following:

1. Mobilization to site.

2. Selective demolition.

3. Furnish & install new well house.

4. Furnish & install all new water piping & fixtures in new well house.

5. Furnish & install 1” HDPE water line.

6. Furnish & install 2” HDPE water line.

7. Furnish & install 4” PVC water line.

8. Furnish & install valve box.

9. Furnish & install spigot assembly.

10. Furnish & install drain.

11. Well modifications.

12. Electrical allowance - to meter.

13. Electrical work - from meter.

14. Pump yield test.

15. Pressure testing.

16. Chlorination of water system

17. Well water quality testing

18. Site restoration / turf establishment

19. Commissioning of new work

C. Government or Owner refers to the USDA Forest Service. Contracting Officer (CO) refers to the person assigned by the USDA Forest Service to administer the Contract. Soon after Contract award, the Contracting Officer will designate a Contracting Officers Representative (COR).

1.2 REQUIREMENTS OF THE OFFER’S PROPOSAL

A. The Government DRAWINGS and SPECIFICATIONS are the basis for this Contract.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 2 of 61

B. Those products listed in the SPECIFICATIONS are preferred products, chosen for compatibility, longevity, durability and quality. Equal or better alternatives submitted by the OFFEROR will be considered, but must be approved by the CO/COR prior to use in the Project.

Bidders are cautioned assumed equal or better alternatives may not be accepted by the Government and the selected Contractor will be required to provide the Work as specified.

PART 2 – PRODUCTS (Not Applicable)

PART 3 – EXECUTION (Not Applicable)

END OF SECTION 011000

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 3 of 61

SECTION 011400 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 CONTRACTOR USE OF PREMISES

A. The Government will conduct a pre-construction survey with the Contractor to review and document the existing project conditions prior to construction.

B. No work is permitted without written authorization on Government Holidays or weekends.

C. The Contractor shall limit use of the premises to the work in areas indicated.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Schedule deliveries to minimize on-site storage of material and equipment.

3. Repair damage caused by construction operations. Take precautions to protect the public during the construction period.

4. Limited space on the premises is available for the Contractor's storage and related activities, as staked/designated by the Government.

5. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or salvaged as Government property, shall become the property of the Contractor and shall be promptly removed from the site.

1.3 GOVERNMENT OCCUPANCY AND TIME FRAME

A. Cooperate with the Government's representatives during construction operations to minimize conflicts and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government operations.

B. It is highly recommended the Contractor have submittals approved, materials with long lead times purchased and have the electrical service coordinated to start work as soon as possible to meet the project deadlines.

1. The upper loop of the campground will be closed to the public for Contractor’s full use starting on September 21, 2026 through December 11, 2026 during which time the Contractor shall have full access of the upper campground for the work of this contract.

This time frame is the only contract time frame in which the Contractor can perform work at the site.

C. Once the Contractor has started working at the site, the Contractor shall work without delay, shall not miss days conducive to accomplishing acceptable quality work or other unacceptable

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 4 of 61 reasons so the Project is completed in the most expeditiously amount of time. All of the work, including the COR receiving two TC – test results (paper or electronic lab test forms, NOT VERBAL) from samples taken at least 24 hours apart, water quality testing, O&M manuals, winterizing the portion of the water system the Contractor built, final cleaning, etc., shall be completed no later than the Contract Completion date.

PART 2 - PRODUCTS (Not Applicable) & PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011400

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 5 of 61

SECTION 012700 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings entitled “Loleta Recreation Area Water System Improvements – Phase 1” and applicable provisions of the Solicitation/Contract including but not limited to: Section B - Schedule of Items, Section C - Statement of Work, Section G - Contract Administration Data/Invoices and Payments and Section I - Contract Clauses.

1.2 SUMMARY

A. This Section includes:

1. Measurement and payment criteria applicable to the work performed.

2. Administrative and procedural requirements necessary to prepare and process Applications for Payment.

3. Defect assessment and non-payment for rejected work.

4. General description of work included under each pay item.

B. Related Requirements:

1. Invoice Processing Platform (IPP) System: All invoices are to be submitted via the electronic IPP System. The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in communications from USDA and Treasury. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website: https://www.ipp.gov. Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors to establish your account.

Offeror must have an established account prior to commencement of work.

2. Certified Payrolls: Certified payrolls for construction work must be submitted to the CO/COR for review at regular intervals as work progresses. At least one week prior to Contractor requesting payment via IPP, all certified payrolls related to the subject pay request work must have been received by the CO/COR. Incomplete or inaccurate payroll submittal will result in rejection of the IPP invoice. Contractor and all subcontractors, through the contractor, shall furnish all certified payrolls covering payments to laborers and mechanics for on-site work. Payroll hourly rates and fringe benefits must be in accordance with the established Wage Determination for the project.

1.3 AUTHORITY

A. The Contracting Officer’s Representative (COR) will take all measurements and compute quantities accordingly.

1.4 METHOD OF MEASUREMENT OF QUANTITIES

A. Linear Measurement: Measured by the linear dimension, (i.e. LF = lineal foot), at the item centerline or mean chord. Measurement will be made to the nearest given linear unit.

B. Each (EA): Measured by the number of individual items of work completed.

https://www.ipp.gov/ https://www.ipp.gov/vendors/enrollment-vendors

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 6 of 61

C. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the Contract, including all necessary materials, equipment, and labor to complete the job. They will not be measured.

D. Actual Quantities (AQ): These quantities denote completed units of work, as described in the Contract, including all necessary materials, equipment, and labor, to complete the job. They will be measured in the field.

E. Designed Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the quantity of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

1. As a result of changes in the work authorized by the Contracting Officer.

2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities, which cause a pay item to change by 15 percent or more.

3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

1.5 PAYMENT

A. Pay Request Documentation from Contractor: Contractor must submit the following documentation to the CO/COR for review and approval at least seven (7) days prior to requesting a payment via IPP.

1. All Certified Payroll forms from the general contractor (including payrolls from all sub-contractors) for work covered by the pay request.

2. A completed Schedule of Items form for work covered by the pay request, indicating the percent complete for each line item in the Schedule of Items.

3. Written Quality Control testing results if applicable to items in the payment request.

B. Payment Includes: Full compensation for all required labor, products, tools, equipment, plant, transportation, services, and incidentals; erection, application, or installation of an item of the Work; overhead and profit.

1. "Incidentals" are to be considered as an additional obligation to the other work required for the item(s). Incidental work is not payable directly, but is to be considered included in the contract price for the item(s) of work specified.

2. All work not specifically identified as a separate bid item is "Incidental".

C. The accepted quantities will be paid for at the contract unit price for each item as shown in the Schedule of Items.

D. Payment will not be made for any of the following:

1. Products or construction placed beyond the lines and levels of the required work.

2. Products or construction determined as unacceptable before or after placement.

3. Products wasted or disposed of in a manner that is not acceptable.

4. Products remaining on hand after completion of the Work.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 7 of 61

5. Loading, hauling, and disposing of rejected products.

E. DESCRIPTION OF ITEMS

The following information describes what specific items of work are included in each bid item.

1. MOBILIZATION

a. Description of work: This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work for the Project Work. The cost of premiums paid for performance and payment bonds are considered incidental to this item and will not be paid for separately. The maximum price bid for this mobilization may not exceed 10% of the total contract bid price.

b. Measurement: Lump Sum (LSQ)

2. SELECTIVE DEMOLITION

a. Description of work: This work shall consist of, but is not limited to the complete removal of the existing valve box, all remaining PVC gravity water line to the existing valve box, two (2) campground spigots with associated valves/posts/drains, ~6’ x 6’ concrete slab between sites 7 & 8, any existing water line piping from the existing system encountered that requires removal to properly install new water line piping per this contract, asphalt road cutting to allow for new water line installation and any other incidental demolition work required to complete the project. This includes proper disposal of all materials off Government property. Submittals for demolished material disposal are included.

b. Measurement: Lump Sum (LSQ)

3. FURNISH & INSTALL NEW WELL HOUSE

a. Description of work: This work shall consist of all submittals, materials, labor and equipment to furnish and install the new well house, complete in place. This includes, but not limited to, preparation grading for the 6” gravel pad, placement of the gravel pad and compaction, touch up paint work, adjusting doors/hinges/threshold and installing FS keyed locks and any other incidental item or task to install the new well house completely as shown on the Drawings.

b. Measurement: Lump Sum (LSQ)

4. FURNISH & INSTALL ALL NEW WATER PIPING & FIXTURES IN WELL HOUSE

a. Description of work: This work shall consist of all submittals, materials, labor and equipment to furnish and install all water piping and fixtures in the new well house.

This includes, but not limited to, submittals, all galvanized iron piping (GIP), PVC piping, HDPE piping, transition fittings, water meter, valves, drains, pipe supports, sample taps, chlorination port, gravity storage tanks and cement blocks, float, pump controls and any other incidental item or task to install all new water piping and fixtures for a complete turnkey system as shown on the Drawings. The FS will provide the salvaged chlorine pump and solution tank for the Contractor to install.

b. Measurement: Lump Sum (LSQ)

5. FURNISH & INSTALL 1” HDPE WATER LINE

a. Description of work: This work shall consist of all submittals, materials, labor and equipment to furnish and install new 1” HDPE water line as shown on the Drawings.

This includes, but not limited to, excavation, backfill, asphalt patching, new HDPE

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 8 of 61 pipe, transition fittings, marker posts, warning tape, tracer wire, and any other incidental item or task to install the new water line as shown on the Drawings.

b. Measurement: Linear Foot (DQ)

6. FURNISH & INSTALL 2” HDPE WATER LINE

equipment to furnish and install new 2” HDPE water line as shown on the Drawings.

This includes, but not limited to, excavation, backfill, asphalt patching, new HDPE pipe, transition fittings, marker posts, warning tape, tracer wire, and any other incidental item or task to install the new water line as shown on the Drawings.

b. Measurement: Linear Foot (DQ)

7. FURNISH & INSTALL 4” PVC WATER LINE

a. Description of work: This work shall consist of all submittals, materials, labor and equipment to furnish and install new 4” PVC water line as shown on the Drawings.

This includes, but not limited to, excavation, backfill, new PVC pipe, transition fittings, warning tape, tracer wire and any other incidental item or task to install the new water line as shown on the Drawings. Measurement of this pay item is made along the centerline of the pipe starting at the underground ell at the storage tank and ending at the 4” transition fitting in the valve box.

b. Measurement: Linear Foot (DQ)

8. FURNISH & INSTALL VALVE BOX

equipment to furnish and install a new valve box as shown on the Drawings. This includes, but not limited to, excavation, aggregate base coarse, concrete valve box sections, mastic joint material, core drilling, plugging all annual spacings around piping, all interior fittings and piping, cement blocks and shims, aluminum hatch, backfill, warning tape, tracer wire, valve wrenches and any other incidental item or task to install the new valve box structure as shown on the Drawings.

b. Measurement: Lump Sum (LSQ)

9. FURNISH & INSTALL SPIGOT ASSEMBLY

a. Description of work: This work shall consist of all submittals, materials, labor and equipment to furnish and install a new spigot assembly. This includes, but not limited to, excavation, spigot post assembly, water piping, fittings, flow reducer, spigot, post cap, concrete slab and base material, backfill, warning tape, tracer wire, marker post, spigot valve box, 10 feet of 1” HDPE piping and any other incidental item or task to install the new spigot and spigot valve box assembly as shown on the Drawings.

b. Measurement: Each (DQ)

10. FURNISH & INSTALL DRAIN

equipment to furnish and install a new screened drain valve. This includes, but not limited to, excavation, ball valve, screened outlet, warning tape, tracer wire, marker post and any other incidental item or task to install a new screened drain valve assembly as shown on the Drawings.

b. Measurement: Each (DQ)

11. WELL MODIFICATIONS

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 9 of 61 equipment to modify the existing well. This includes, but not limited to, removing the existing drop pipe and submersible pump, extending the well casing, flushing the well, adding a pitless adapter, cleaning and inspecting the drop pipe and submersible pump and motor, installing the removed drop pipe and submersible pump, connecting to the new HDPE water line to the well house, adding a new well cap and any other incidental item or task to modify the existing water well to meet the State of Pennsylvania applicable regulations and the contract Drawings/Specifications. This also includes submitting to the State and to the COR the modified well log indicating the new modifications.

b. Measurement: Lump Sum (LSQ)

12. ELECTRICAL WORK ALLOWANCE – TO METER

a. Description of work: This work shall consist of all submittals, permits, coordination with United Electric Cooperative, Inc., materials, labor and equipment needed to install all electrical components (primary and service) from pole number 18143 as shown on the Drawings to the meter at the new well house. This includes, but not limited to, the electrical permit, coordination with the electrical company to get electricity to the well house including any transformers, routing of new underground service line as shown on the Drawings, new electric meter, excavation, backfill, all conduit, conductors, warning tape, tracer wire, mounting and attaching hardware, and any other incidental item or task to install electrical power to the well house electrical meter. Since this work will be quoted by the Power Company and is not known at the time of the design, a place holder allowance has been included in the Schedule of Items for $10,000.00. The Contractor will be paid the actual amount charged by the Power Company + 20% (for coordination, overhead, profit, etc.) for a total bid item. The Contractor shall provide to the COR the actual invoice from the Power Company prior to invoicing the Government. This bid item has already been included on the Schedule of Items and shall not be changed by the Contractor.

b. Measurement: Lump Sum (LSQ)

13. ELECTRICAL WORK – FROM METER

a. Description of work: This work shall consist of all submittals, permits, materials, labor and equipment needed to install all electrical components from the well house meter to the rest of the electrical work for the project. This includes all work related to the submersible well pump and the well house interior components. This includes, but not limited to, the electrical permit, excavation, backfill, all conduit, conductors, warning tape, tracer wire, well controls, wiring and conduit from the well pump to the well house controls, mounting and attaching hardware, connection to the new well house panel, connection to the float, lighting fixtures, grounding rod system and any other incidental item or task to install the electrical system for a complete turn key system.

b. Measurement: Lump Sum (LSQ)

14. PUMP YIELD TEST

a. Description of work: This work shall consist of all submittals, materials, labor and equipment needed to complete the pump yield test.

15. PRESSURE TESTING

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 10 of 61 equipment needed for the pressure testing of the water system installed by the Contractor. This includes the well, all new water lines, well house, spigots, all valves and drains. Repairs and repeat tests will be at the Contractor’s expense.

b. Measurement: Lump Sum (LSQ)

16. CHLORINATION OF WATER SYSTEM

a. Description of work: This work shall consist of all submittals, materials, labor and equipment needed for the chlorination of the entire water system installed by the Contractor. This includes the well, all new water lines, well house, spigots, all valves and drains. This also includes flushing of the system after 24 hours chlorine contact time, proper disposal/neutralizing super chlorinated water as per SDWA and obtaining required TC negative test results. Re-chlorination and repeat tests will be at the Contractor’s expense.

b. Measurement: Lump Sum (LSQ)

17. WELL WATER QUALITY TESTING

a. Description of work: This work shall consist of all submittals, materials, labor and equipment needed for the complete testing of the well water quality as per the Specification Section 221114 Water Distribution. This includes providing written sample results and clearly indicating if results meet MCL for the State of Pennsylvania.

b. Measurement: Lump Sum (LSQ)

18. SITE RESTORATION / TURF ESTABLISHMENT

a. Description of work: This work shall consist of all submittals, materials, labor and equipment needed for ALL top soil placing, final grading, seeding and mulching, site cleanup, grading of surrounding areas disturbed by Contractor and or as shown on the Drawings, removal of excess material, cleaning of paved surfaces and all other activities related to leaving the project site in a condition equal to or better than the original condition.

b. Measurement: Lump Sum (LSQ)

19. COMMISSIONING OF NEW WORK

a. Description of work: This work shall consist of all Operation and Maintenance

Manuals, as-built drawings and the complete demonstration and training of Forest Service and the Campground Concessionaire personnel of the proper Operation and Maintenance of the new water system using the Contractor supplied Operation and Maintenance Manuals.

PART 2 - PRODUCTS (Not Applicable)

PART 3 – EXECUTION (Not Applicable)

END OF SECTION 012700

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 11 of 61

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations to provide an efficient and orderly installation of each part of the Work.

1.3 CONSERVATION

A. Use best management practices for the conservation of energy, water and materials during construction operations.

1.4 SPILL AND EROSION CONTROL

A. Spill and Erosion Control Plans: Develop plans to minimize erosion. Develop plans to provide for containment of hazardous materials and unplanned spills.

1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. In addition to meeting the requirements of FAR 52.236-6 for an on-site Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for performance of the Work.

1.6 CONFERENCES AND MEETINGS

A. Pre-construction Conference: The Contracting Officer or Contracting Officer’s Representative will schedule a pre-construction conference before starting construction at a time and place agreeable and convenient to both the Contractor and Government and will review responsibilities and personnel assignments in accordance with FAR 52.236-6 Preconstruction Conference.

B. Progress Meetings: Progress meetings at the Project Site shall be conducted at regular intervals.

Dates of meetings shall be coordinated with preparation of the payment request in accordance with FAR 52.232-5 Payments Under Fixed-Price Construction Contracts.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 12 of 61

1. Agenda: Include topics for discussion as appropriate to the status of the Project. Include review of the Contractor's Construction Schedule and of the present and future needs of each entity present.

2. Schedule Updating: If the progress of the work falls behind the approved Contractor’s Construction Schedule, the Contractor shall submit a supplementary schedule for approval by the Contracting Officer in accordance with FAR 52.236-15 Schedules for Construction Contracts.

1.7 SUBMITTALS

A. Spill and Erosion Control Plans shall be submitted within 5 calendar days after Notice to Proceed.

B. Staff Names: Within 5 calendar days after Notice to Proceed, submit a list of principal staff assignments, including the Superintendent and other primary personnel. Identify individuals by name, duties and responsibilities, home address, and business/cell and home (in case of emergencies after hours) telephone numbers. Post copies of this list in the temporary field office (if present).

C. Construction Schedules shall be submitted as directed in FAR 52.236-15 Schedules for Construction Contracts. THE CONTRACTOR SHALL SUBMIT A CONSTRUCTION

SCHEDULE TO THE COR AT THE PRE-CONSTRUCTION CONFERENCE.

PART 2 - PRODUCTS (Not applicable)

PART 3 - EXECUTION

3.1 GENERAL COORDINATION PROVISIONS

A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.

B. Construction in Progress: Keep construction in progress, adjoining materials in place, and clean during handling and installation. Apply protective enclosures or coverings for protection from damage or deterioration.

C. Completed Construction: Clean completed construction and provide maintenance to prevent damage, soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components to assure operability without damage.

D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period.

END OF SECTION 013100

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 13 of 61

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section and FAR 52.236-21 include requirements for Shop Drawings, as defined by

FAR 52.236-21 and Designs. Shop drawings and Designs may include drawings, specifications, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data furnished by the Contractor to explain in detail specific portions of the work required by the Contract.

B. This section includes requirements for Samples, if any. Samples may include mailed samples, field samples or mock-ups of full-size physical examples erected on-site or elsewhere.

C. This section includes requirements for Product Data. Product Data includes any manufacturer products’ (used in this project) standard catalogs, manuals, pamphlets and other printed materials, and includes but is not limited to the following: product specifications and installation instructions, color charts and catalog cuts, rough-in diagrams and templates, wiring diagrams, performance curves, operational range diagrams, mill reports, test reports, shop drawings and code approvals. THE CONTRACTOR MUST CLEARLY INDICATE

ON THE SUBMITTED MATERIALS WHICH PRODUCT THEY ARE PROVIDING.

FOR EXAMPLE – A PUMP CURVE WITH 5 PUMPS SHOWN ON THE SAME PAGE

SHALL HAVE THE PUMP BEING SUPPLIED CLEARLY INDICATED AS SUCH.

D. This section includes other quality assurance submittals such as certifications of compliance or conformance, manufacturer's instructions and field reports, any permits received, test reports, lab or test results, etc.

1.2 GENERAL SUBMITTAL REQUIREMENTS

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities and with the schedule.

1. Allow 15 calendar days each for submittal review, corrections following the initial review and re-submittal review before activities scheduled after the submittal approval.

2. Incomplete submittals will be returned to the Contractor with no further review. Delays due to incomplete or rejected submittals will not be excused with no compensation in the form of monetary or time being provided to the Contractor.

3. When the Contractor desires to submit for approval a product for an “approved equal”, the Contractor MUST provide documentation of the original specified product and the Contractor proposed product in a side-by-side comparison, such as a table, which clearly demonstrates the Contractor proposed product meets or exceeds the originally specified product. If this comparison is not done the first time it is submitted, the proposed product will be rejected AND THE CONTRACTOR WILL HAVE TO PROVIDE THE

SPECIFIED PRODUCT. THE GOVERNMENT WILL NOT REVIEW A

SECOND PROPOSAL SUBMITTAL. If the proposed product comparison shows it may meet the specification requirements but is missing some minor information, the COR will contact the Contractor for further information ONE TIME to obtain the missing information. If the information is not received, then the proposed product will be rejected

AND THE CONTRACTOR WILL HAVE TO PROVIDE THE SPECIFIED

PRODUCT.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 14 of 61

4. Submittal Transmittal: Transmit each submittal from the Contractor to the Government by use of one transmittal form per submittal. Sequentially number transmittal forms (i.e.

1, 2, 3, etc.). Mark revised submittals with original number and sequential alphabetic suffix, (i.e. 1-A, 2-A, 3-A, etc.) Transmittal format to be approved by CO, and shall include the following information on the transmittal form.

a. Project name and Forest Service contract number.

b. Date.

c. Name, address and telephone number of firm or entity that prepared the submittal

d. Names of subcontractor, manufacturer, supplier, etc. as applicable.

e. Category and description of submittal.

f. Section of Specifications or Drawing sheet number the Submittal is representing.

g. Certification by Contractor stating that submittal complies with the Contract, or statement of deviations from the requirements of the Contract.

h. CLEARLY INDICATE ON THE SUBMITTAL INFORMATION THE

PRODUCT BEING SUBMITTED IF THE INFORMATION SHEETS

CONTAIN MORE THAN ONE SELECTION, OPTION, ETC. FAILURE TO

CLEARLY INDICATE WHAT IS BEING PROPOSED FOR ACCEPTANCE

WILL RESULT IN NO REVIEW BY THE GOVERNMENT AND THE

SUBMITTAL WILL BE REJECTED.

i. Signature of transmitter.

j. Space to record Contractor's review and approval markings, and for Government response.

B. Submit 3 hardcopies of each submittal to the COR for review unless otherwise stated. One copy will be returned to the Contractor and two copies will be retained, one for the COR and one for the Inspector.

C. Electronic file submittal (email, thumb drive, etc.) will be acceptable in lieu of hardcopies when appropriate. However, the files shall be in PDF format, one submittal per file, be of high quality (not upside down, pages mixed up, not-legible, black and white when it should be color, etc.) and the files shall be named as to what submittal it is and the version of the submittal (such as a resubmittal).

1.3 SHOP DRAWINGS AND DESIGNS

A. Submit originally prepared information, drawn accurately to scale.

B. Submittals: Submit three blue-line or black-line prints of each drawing submittal. One print will be marked with action taken and returned. Distribution: When submittal is approved, the Contractor shall prepare and submit three final copies.

C. Shop drawings shall be done in AutoCAD format. Upon final approval the drawings (dwg format) shall be sent on a thumb drive or via email to the COR.

D. Specifications shall be done in Microsoft Word format and a copy sent on a thumb drive or via email to the COR.

1.4 PRODUCT DATA

A. Collect Product Data into a single submittal for each system or element of construction.

Mark each copy to show specific product choices and options applicable to the project.

Product Data shall include the following information, where applicable:

1. Manufacturer's printed recommendations.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 15 of 61

2. Compliance with recognized trade association standards.

3. Compliance with recognized testing standards.

4. Applicability of testing agency labels and seals.

5. Notation of dimensions verified for fit by field measurements.

6. Notation of coordination requirements.

B. Preliminary Submittal: Prior to submittal of complete Product Data, submit a preliminary single copy of that part of Product Data when selection of options is required, such as for color charts. Preliminary submittal will be returned, with selection noted, for the Contractor's use in subsequent submittals.

C. Submittals: Unless otherwise indicated, submit 3 copies of each Product Data submittal. Two copies will be retained, and the remaining copy will be marked with action taken and returned.

D. Electronic file submittal (email, thumb drive, etc.) will be acceptable in lieu of hardcopies when appropriate. However, the files shall be in PDF format, one submittal per file, be of high quality (not upside down, pages mixed up, not-legible, black and white when it should be color, etc.) and the files shall be named as to what submittal it is and the version of the submittal (such as a resubmittal).

E. Material and Product substitution shall be in accordance with FAR 52.211-6 and Section 013300-1.2.A.3.

1.5 SAMPLES

A. Submit full-size, fully fabricated samples, cured and finished in the manner specified, if required. Samples shall be physically identical to the material or product proposed for use.

B. Preliminary Submittal: Where color, pattern, texture or similar characteristics are to be selected from a manufacturer's range of standard choices, submit a preliminary single set sample of available choices when required by the CO.

1.6 OTHER QUALITY ASSURANCE SUBMITTALS

A. Submit other quality assurance submittals in compliance with requirements in the individual specification sections.

1.7 REVIEW ACTION ON SUBMITTALS

A. Except for submittals for the record or for information or for another purpose where no action and return is required, the Government will review submittals and mark returned copies to indicate action taken within a maximum time period of 15 calendar days.

B. Submittals that do not contain an appropriate marking of approval by the Government shall not be used for construction.

PART 3 - EXECUTION (Not applicable)

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 16 of 61

END OF SECTION 013300

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 17 of 61

SECTION 014000 - QUALITY CONTROL

PART 1 - GENERAL

1.1 SUMMARY

A. This section, FAR 52.246-1 Contractor Inspection Requirements and FAR 52.246-12 Inspection of Construction include requirements for quality control services to verify quality assurance requirements specified elsewhere in the Contract.

B. The Government reserves the right to conduct independent tests.

C. This section includes, but not limited to, requirements for quality control services such as soil density compaction, concrete mix and strength testing, water and/or sewer line pressure tests, bedding and sand gradation tests per local DOT, electrical inspections, etc.

D. The quality control services include tests and related actions, including reports, performed by the Contractor, independent agencies or governing authorities.

1.2 RESPONSIBILITIES

A. Contractor Responsibilities: The Contractor shall provide for tests, inspections and other quality control services where specified in the Contract or when required by authorities having jurisdiction. Costs for these services are included in the Contract price. The Contractor shall maintain complete inspection records and make them available to the Government.

B. The Contractor is responsible for all survey work associated with this project unless specified elsewhere.

C. The Contractor shall employ and pay for a qualified independent testing agency (Agency) to perform the quality control services unless the COR and Contractor agree to other arrangements.

D. Retesting: The Contractor is responsible for retesting, including repeated inspections and other services, where results of the initial tests, inspections or other quality control services indicate noncompliance with the requirements of the Contract.

E. Associated Services: The Contractor shall cooperate with others performing required tests, inspections and other quality control services, shall provide access to the work, and shall furnish incidental labor and facilities necessary to facilitate inspections and tests.

F. Take adequate quantities of representative samples of materials that require testing or assist the Agency in taking samples.

1. Deliver samples to testing laboratories.

2. Provide security and protection of samples and test equipment at the Project site.

G. The Agency/Contractor shall provide qualified personnel to perform required inspections and tests.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 18 of 61

H. The Agency shall notify the Government and the Contractor of irregularities or deficiencies observed in the Work during performance of their services.

I. The Agency is not authorized to change requirements of the Contract or approve or accept any portion of the Work. The Agency shall not perform any duties of the Contractor.

1.3 QUALIFICATIONS OF INDEPENDENT TESTING AGENCIES

A. A qualified independent testing Agency shall be an accredited entity engaged to perform tests or inspections, and to report on and, if required, to interpret results of those tests or inspections.

1.4 SUBMITTALS

A. Reports: The Contractor shall submit a certified written report, in duplicate, of each test, inspection or other quality control service to the Government.

B. Written reports shall include but not be limited to the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making the test or inspection.

6. Designation of the work and test method.

7. Identifications of product and specification section.

8. Complete test or inspection data.

9. Test results and an interpretation of test results.

10. Ambient conditions at the time of sample taking and testing.

11. Comments or professional opinion on whether tested or inspected Work complies with

Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting.

C. Permits, Licenses, and Certificates: For the Government's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1. An electrical permit is required for this project that the Contractor shall pay for and obtain.

2. Contractor shall coordinate and pay for work by United Electric Cooperative, Inc. to install the Primary and Service line to the new well house.

3. A water system permit from PA DEP “Noncommunity Water System Application” has been obtained by the Government in which the Contractor shall fully comply.

4. No Soil and Erosion Control Permit is required for this project.

5. Contractor is required to contact PA One Call at 811 for this project.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 19 of 61

END OF SECTION 014000

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 20 of 61

SECTION 014200 - REFERENCES

PART 1 - GENERAL

1.1 DEFINITIONS

A. General Explanation: Specification language often includes terms that are defined elsewhere in the Contract including the Construction Clauses. Certain terms are defined in this section.

These definitions or explanations are not necessarily complete or exclusive but are general for the Work and may be explained more explicitly in other sections.

B. "General Conditions" refer collectively to the Construction Contract Clauses, Labor Standards and the U.S. Department of Labor Wage Decision bound into the specifications.

C. "Indicated" refers to graphic representations, notes or schedules on the Drawings, or to requirements elsewhere in the Specifications or other Contract Documents. Terms such as "shown", "noted", "scheduled" and "specified" have the same meaning as "indicated" and are used to further help locate the reference, but no limitation on location is intended except as specifically stated.

D. Where "directed", "authorized", "selected", "approved", or a similar term is used in conjunction with the Contractor's submittals, applications, requests and other activities, and the specifications state that an individual other than the Contracting Officer (CO) shall provide this action, it is understood that only the CO has this authority unless the individual stated is so authorized in writing by the CO.

1. When the individual is so authorized by the CO, the Contractor may still appeal the action to the CO.

2. The CO’s decision will be final.

3. In no case shall the CO action be interpreted as releasing the Contractor from responsibility to fulfill the requirements of the Contract.

E. "Regulations" include laws, ordinances, statutes and lawful orders issued by authorities having jurisdiction, as well as rules, conventions and agreements within the construction industry that control performance of the Work.

F. "Project site" refers to the space available to the Contractor for performance of the Work, either exclusively or in conjunction with others performing other work.

G. "Furnish" means to supply and deliver to the Project site, ready for unloading, unpacking, assembling, installation and similar operations.

H. "Install" describes operations at the Project site, including unloading, temporary storage, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning and similar operations.

I. "Provide" means to furnish and install, complete in place and ready for full use.

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 21 of 61

J. "Cutting" refers to removal of material by cutting, sawing, drilling, coring, breaking, chipping, grinding, excavating and similar operations.

K. "Patching" refers to restoration of a surface to its original completed condition by filling, repairing, refinishing, closing and similar operations.

L. "Installer" is the Contractor, or another entity engaged by the Contractor, either directly or indirectly through subcontracting, to perform a particular construction operation at the Project site, including installation, erection, application and similar operations. Installers shall be skilled in the operations they perform.

M. "Testing agency" or "testing laboratory" is an independent entity engaged to perform specific inspections or tests, either at the Project site or elsewhere, and to report the results of those inspections and tests.

N. "Notice to Proceed" is the CO’s notification by letter to the Contractor to proceed with the Contract, activating the time period for construction and establishing the completion date.

1.2 CODES AND STANDARDS

A. Applicability of Standards: Unless the Contract includes more stringent requirements, applicable construction industry standards have the same force and effect, to the extent referenced, as if bound or copied directly into the Contract. Such standards are made a part of the Contract by reference.

B. Codes: The Work shall be performed in compliance with the latest editions of the following codes: ACI, IBC, IMC, IPC and NEC.

C. The Contractor shall comply with the Forest Service Health and Safety Code Handbook, FSH

6709.11 available at: fsh - 6709.11 Code Field Issuances (usda.gov)

D. Conflicting Requirements. Where compliance with two or more standards is specified, comply with the most stringent requirement. Refer uncertainties, and requirements that are different but apparently equal, to the CO in writing for a decision before proceeding.

E. Abbreviations: Names and titles of standards are frequently abbreviated. Abbreviations and acronyms used in the Contract mean the recognized name of a trade association, standards-producing organization, authority having jurisdiction or other entity applicable to the context of the particular provision. Except as otherwise indicated, refer to the current editions of the following publications for abbreviations:

1. "Encyclopedia of Associations: National Organizations of the U.S.", published by Gale Research.

2. "National Trade and Professional Associations of the United States", published by Columbia Books.

3. "Means Illustrated Construction Dictionary - New Unabridged Edition" published by R.S.

Means Company, Inc.

https://www.fs.usda.gov/cgi-bin/Directives/get_dirs/fsh?6709.11

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 22 of 61

F. Abbreviations: Names and titles of standards are frequently abbreviated. Abbreviations and acronyms used in the Contract mean the associated names. The following names may be referenced in the Contract:

1. AASHTO - American Association of State Highway and Transportation

2. ACI - American Concrete Institute

3. ADA – Americans with Disabilities Act

4. ADAAG – Americans with Disabilities Act Accessibility Guidelines

5. AI - Asphalt Institute

6. AISC - American Institute of Steel Construction

7. AITC - American Institute of Timber Construction

8. ALSC – American Lumber Standard Committee

9. ANSI - American National Standards Institute

10. ASME – American Society of Mechanical Engineers International

11. ASTM - American Society for Testing and Materials

12. AWPA - American Wood-Preservers' Association

13. AWS - American Welding Society

14. AWWA - American Water Works Association

15. CABO - Council of American Building Officials

16. CFR - Code of Federal Regulations

17. CRSI - Concrete Reinforcing Steel Institute

18. CS - Commercial Standard (U.S. Dept. of Commerce)

19. CSI - Construction Specifications Institute

20. DOT – Department of Transportation

21. EIA - Electronic Industries Association

22. EPA - Environmental Protection Agency

23. FS - Federal Specification (Publications available from GSA)

24. FP-14 – Standard Specifications for Construction of Roads and Bridges on Federal

Highway Projects

25. GSA - General Services Administration

26. IBC – International Building Code

27. IFC – International Fire Code

28. IMC – International Mechanical Code

29. IPC – International Plumbing Code

30. ICBO – International Conference of Building Officials

31. MCAA – Mechanical Contractors Association of America

32. MSS-Manufacturers Standardization Society of the Valve and Fittings Industry Inc.

33. NECA – National Electrical Contractors Association

34. NEMA - National Electrical Manufacturers Association

35. NEC – National Electrical Code

36. NFPA - National Fire Protection Association

37. OSHA - Occupational Safety and Health Administration (U.S. Dept. of Labor)

38. PCA - Portland Cement Association

39. PCI – Precast/Prestressed Concrete Institute

40. SDWA – Safe Drinking Water Act

41. SSPC - Steel Structures Painting Council - The Society for Protective Coatings

42. UFAS – Uniform Federal Accessibility Standards

43. UL - Underwriters Laboratories Inc.

44. USDA - U.S. Department of Agriculture

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 23 of 61

END OF SECTION 014200

LOLETA RECREATION AREA WATER SYSTEM IMPROVEMENTS - PHASE 1 - DATED 2-11-2025 24 of 61

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 SUMMARY

A. Provide temporary utilities, support facilities, sanitary facilities, dumpster, site protection, and controls required for construction activities in accordance with this specification and FAR 52.236-10 Operations and Storage Areas. Provide project work signs and secured areas to direct safe construction operations.

1.2 QUALITY ASSURANCE

A. Comply with industry standards, codes, and with applicable laws and regulations.

3.1 TEMPORARY UTILITIES

A.