C006483 Addendum 2.pdf

PDF 141 KB Posted

Attached to
Substation Radiator Replacements Phase 2
Solicitation number
ITB-07014
Issued by
Orange County, Florida

About this file

This document is an Addendum No. 2 issued by the Central Florida Tourism Oversight District for the Substation Radiator Replacements Phase 2 project, Bid #C006483. The addendum provides clarification that the contractor is responsible for supplying new fan brackets for all fans, regardless of whether a new fan is being installed or an existing fan is being re-installed. The project scope includes installing Owner-furnished radiators for specific transformers at the Epcot and Theme Park locations, performing certified lab testing of oil, replacing all radiators, and disposing of the removed radiators. The total quantity of radiators to be replaced is thirty (30).

The project is located within the state of Florida, specifically in Orange County and Lakeland City. No additional details are provided regarding pricing terms, set asides, incumbents, funding requirements and sources, or any other salient information.

View the file

Other files

File Type Posted
C006483 Addendum 1.pdf PDF
C006483 EXHIBIT B (REVISED 11.15.23).xlsx XLSX spreadsheet
C006483 MFMP ITB Flyer.pdf PDF
C006483 Addendum 3.pdf PDF
C006483 ITB.pdf PDF
C006483 EXHIBIT C (REVISED 11.15.23).xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 2

Issue Date: November 16, 2023

Title: Substation Radiator Replacements Phase 2

Bid #: C006483

To: All Bidders

Issued By: Central Florida Tourism Oversight District Richard Parente, Senior Procurement Analyst rparente@oversightdistrict.org

(689) 254-3539

NOTICE TO ALL BIDDERS

This addendum shall be made part of the ITB and shall be binding as if part of the original documents. Bidders should acknowledge receipt of this Addendum No. 2 in the appropriate space provided of the EXHIBIT D - Bid Submittal Affidavit.

It is the Bidder’s responsibility to identify all addendums before placing a bid.

PART B. QUESTIONS/RESPONSES

Question 1: For clarification, what brackets are the Contractor supplying as identified in the previous addendum?

Response 1: Contractor is to supply new fan brackets for all fans regardless of whether a new fan is being installed or an existing fan is being re-installed. The brackets are sold separately from the fans.