Award Criteria Figure Formula

This document is an award criteria formula used by the County of San Mateo Department of Public Works for evaluating bids on Job Order Contracts for asbestos abatement and hazardous materials management services. The formula establishes a structured methodology for calculating an Award Criteria Figure (ACF) that will determine contract awards across three facility types: general facilities, detention facilities, and OSHPD facilities. Bidders must submit adjustment factors for both normal working hours and other than normal working hours for each facility type. The award calculation requires multiplying the general facilities normal working hours adjustment factor by 40 percent, the general facilities other than normal working hours adjustment factor by 10 percent, the detention facilities normal working hours adjustment factor by 15 percent, the detention facilities other than normal working hours adjustment factor by 10 percent, the OSHPD facilities normal working hours adjustment factor by 15 percent, and the OSHPD facilities other than normal working hours adjustment factor by 10 percent. The county will sum these six weighted calculations to derive the final Award Criteria Figure, which represents the basis for selecting the lowest, responsive, and responsible bidder for each contract. All calculations must be carried to four decimal places to ensure precision in bid evaluation.

The award criteria weighting structure allocates 40 percent of the evaluation to general facilities during normal working hours, 10 percent to general facilities outside normal working hours, 15 percent each to detention and OSHPD facilities during normal working hours, and 10 percent each to detention and OSHPD facilities outside normal working hours. This distribution reflects the county's anticipated distribution of job orders across facility types and operational conditions. The formula ensures that bidders' pricing proposals are evaluated proportionally to the expected allocation of work rather than a simple low-bid approach, allowing the county flexibility to adjust actual job order issuance percentages without obligation to match the stated percentages used for bidding purposes.

View the file

Other files

File Type Posted
Job_Order_Contract_for_Asbestos_Abatement_w_Hazardous_Materials_(JOC_2619_and_JOC_2621)_(Addendum_#1_Revision).pdf PDF
_R_Technical_Specifications_-_Hazardous_Materials_-_Distribution.pdf PDF
_Q_Construction_Task_Catalog®_-_Hazardous_Materials_-_Distribution.pdf PDF
_P_JOC_System_License_and_Fee_Agreement_Sample.pdf PDF
_O_Payment_and_Performance_Bonds_Sample.pdf PDF
_N_Job_Order_Contact_Agreement_SAMPLE.pdf PDF
_M_Contract_Documents_General_Conditions.pdf PDF
_L_Recycling_and_Diversion_of_Debris_from_Construction_and_Demolition_Ordinance_No._4099_Chapter_4.105.pdf PDF
_K_Contractor_Employee_Jury_Service_Ordinance_No.4324_Chapter_2.85.pdf PDF
_J_Contractor's_Declaration_Form_Hazardous_Materials.pdf PDF
_I_Equal_Benefits_Compliance_Ordinance.pdf PDF
_H_Anti-Trust_Laws_Questionnaire_Hazardous_Materials.pdf PDF
_G_EEO_Certification_of_Compliance.pdf PDF
_F_EEO_Contractor_Report_Form_Hazardous_Materials.pdf PDF
_E_EEO_Questionnaire_Hazardous_Materials.pdf PDF
_D_EEO_Program_Supplemental_General_Conditions.pdf PDF
_C_Award_Criteria_Figure.pdf PDF
_B_Bid_Schedule_for_Hazardous_Materials.pdf PDF
_A_Bid_Bond_JOC_2619-2621.pdf PDF
Standard_Contract_Template_-_Over_$200K_DRAFT.docx DOCX document
Standard_Contract_Template_-_Under_$200K_DRAFT.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Award Criteria Figure Formula

Award Criteria Figure Formula percentages are for Bid purposes only. The County is not obligated to issue Job Orders in the stated percentages.

Carry out all Lines to the 4th decimal place.

Line 1. General Facilities

Normal Working Hours Adjustment Factor

1.

Line 2. Multiply Line 1 by 40% = (0.40 x Line 1) 2.

Line 3. General Facilities

Other than Normal Working Hours Adjustment Factor

3.

Line 4. Multiply Line 3 by 10% = (0.10 x Line 3) 4.

Line 5. Detention Facilities

5.

Line 6. Multiply Line 5 by 15% = (0.15 x Line 5) 6.

Line 7. Detention Facilities

7.

Line 8. Multiply Line 7 by 10% = (0.10 x Line 7) 8.

Line 9. OSHPD Facilities

9.

Line 10. Multiply Line 9 by 15% = (0.15 x Line 9) 10.

Line 11 OSHPD Facilities

11.

Line 12 Multiply Line 11 by 10% = (0.10 x Line 11) 12.

Line 13. Add Lines 2, 4, 6, 8, 10 and 12

(This is the Award Criteria Figure)

ACF =