Bid Schedule Summary: Job Order Contract for Hazardous Materials
This Bid Schedule document outlines the pricing structure for Job Order Contracts (JOC) 2619, 2620, and 2621 for hazardous materials work. The contract encompasses work performed across multiple facility types: General Facilities, Detention Facilities, OSHPD Facilities (hospitals and in-patient medical facilities), and other locations. Bidders must submit Adjustment Factors that will be applied to unit prices from the Construction Task Catalog® to determine the cost of individual job orders. The contract differentiates between work performed during Normal Working Hours and Other Than Normal Working Hours across each facility category, requiring bidders to provide six separate Adjustment Factors corresponding to these conditions.
The Adjustment Factor shall include all labor, materials, equipment, supervision, overhead, profit, and incidentals necessary to complete work in accordance with contract documents. Award determination will be based on the Award Criteria Figure carried to four decimal places using conventional rounding methodology. Bids will be rejected as non-responsive if Other Than Normal Working Hours Adjustment Factors are not equal to or greater than Normal Working Hours Adjustment Factors, and if Detention Facilities and OSHPD Facilities Adjustment Factors are not equal to or greater than General Facilities Adjustment Factors. These escalation requirements ensure appropriate compensation for higher-risk and extended-hour work environments.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
Job Order Contract for Hazardous Materials JOC 2619, 2620 and 2621
The Adjustment Factor shall include all labor, materials, equipment, supervision, overhead, profit, and incidentals necessary to complete the Work in accordance with the Contract Documents. When submitting Job Order Price Proposals related to specific Job Orders, the Bidder shall utilize one or more of the Adjustment Factors applicable to the Work being performed. The Award Criteria Figure, carried out to four
(4) decimal places, will be used to determine the low bidder. Use conventional rounding methodology (i.e., if the number in the 5th decimal place is 0-4, the number in the 4th decimal remains unchanged; if the number in the 5th decimal place is 5-9, the number in the 4th decimal is rounded upward).
BID SCHEDULE:
General Facilities Normal Working Hours: Work performed during Normal Working Hours, in General Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
General Facilities Other than Normal Working Hours*: Work performed during Other Than Normal Working Hours, in General Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
Detention Facilities** Normal Working Hours: Work performed during Normal Working Hours, in Detention Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
Detention Facilities Other than Normal Working Hours*: Work performed during Other Than Normal Working Hours, in Detention Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
(cont’d on page 2)
OSHPD Facilities** Normal Working Hours: Work performed during Normal Working Hours, in OSHPD Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
OSHPD Facilities Other than Normal Working Hours*: Work performed during Other Than Normal Working Hours, in OSHPD Facilities, in the quantities specified in individual Job Orders for the Unit Price sum specified in the Construction Task Catalog® multiplied by the Adjustment Factor of:
* Bids will be rejected, as non-responsive if the ‘Other than Normal Working Hours’ Adjustment Factors are not equal to or greater than the ‘Normal Working Hours’ Adjustment Factors.
** Bids will be rejected as non-responsive if the Detention Facilities and OSHPD Facilities Adjustment Factors are not equal to or greater than the General Facilities Adjustment Factors. Detention Facilities Adjustment Factors apply when Work is performed within a secured area Detention Facilities and Juvenile Justice Centers. OSHPD Facilities Adjustment Factors apply when Work is performed within a hospital and/or In-Patient Medical Facility. General Facilities Adjustment Factors apply for all other locations.