This document contains details for a state and local contract opportunity issued by the State of Florida for the rehabilitation of the Burrell Lock located in Brevard County, Florida. The objective of this $2.5 million water control structure project is to repair the concrete surfaces, reline the lock inflow and outflow pipes, repair and paint the lock mitre gates, provide new mitre gate hydraulic operators, replace the upstream and downstream slide gates and provide new hydraulic operators, replace controls in the control building, and install manatee protection screens. Additional work includes replacing wood fenders, navigation lights, fire extinguisher cabinets, floatation rings, staff gages, signs, lock access gate and ladder, and removal and reinstallation of the manatee detection system. A non-mandatory pre-bid conference will be held on March 26, 2024, at the project site. A bid bond/guaranty is required.
The estimated total construction cost is $2.5 million. No set-asides are mentioned. The project is funded by the State of Florida. Bidders must be able to complete the work within the specified timeline and budget.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| COST SCHEDULE revised Addendum 2 - Copy.xlsx | XLSX spreadsheet | |
| IFB 39422_Addendum 1.pdf | ||
| 39422 BURRELL LOCK REHAB BID dwngs 2024-02-19.pdf | ||
| IFB 39422Final Clean.pdf | ||
| IFB 39422_Addendum 2 .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| COST SCHEDULE | |||||
| BURRELL LOCK REHABILITATION | |||||
| ITEM | ESTIMATED | TOTAL | |||
| NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1 | MOBILIZATION | 1 | LS | ||
| 2 | EROSION/SEDIMENT CONTROL | 1 | LS | ||
| 3 | TEMPORARY DEWATERING BULKHEADS | 1 | LS | ||
| 4 | PUMPING/DEWATERING | 1 | LS | ||
| 5 | REMOVE MANATEE SONAR DETECTION SYSTEM | 1 | LS | ||
| 6 | REMOVE SEDIMENT AND DEBRIS | 50 | CY | ||
| 7 | PRESSURE WASH ALL CONCRETE AND STEEL SURFACES | 12,800 | SF | ||
| 8 | DEMO - LOCK MITRE GATE OPERATORS AND CONTROLS | 4 | EA | ||
| 9 | DEMO - SLIDE GATES, OPERATORS, AND CONTROLS | 4 | EA | ||
| 10 | DEMO - ABANDONED ELECTRICAL BOXES AND CONDUITS | 4 | EA | ||
| 11 | DEMO AND REPLACE - UPSTREAM AND DOWNSTREAM FENDERS | 1 | LS | ||
| 12 | DEMO AND REPLACE - INTERNAL LOCK FENDERS | 1 | LS | ||
| 13 | DEMO AND REPLACE - NAVIGATION LIGHTS | 4 | EA | ||
| 14 | DEMO AND REPLACE - STAFF GAGES | 2 | EA | ||
| 15 | DEMO AND REPLACE - FIRE EXTINGUISHER CABINETS | 4 | EA | ||
| 16 | DEMO AND REPLACE - FLOATATION RINGS | 4 | EA | ||
| 17 | DEMO/SALVAGE LOCK SIGNS - REPLACE/REINSTALL | 1 | LS | ||
| 18 | LOCK MITRE GATE REHABILITATION | 4 | EA | ||
| 18.1 | LOCK GATE STEEL REPAIRS (IF REQUIRED) | 200 | LBS | ||
| 18.2 | LOCK GATE HINGE PINS (IF REQUIRED) | 1 | EA | ||
| 18.3 | LOCK GATE HINGE BEARINGS (IF REQUIRED) | 1 | EA | ||
| 18.4 | LOCK GATE LUMBER COMPONENTS (IF REQUIRED) | 180 | LF | ||
| 19 | CONCRETE - HYDRODEMOLITION OF SURFACES (IF REQUIRED) | 400 | SF | ||
| 20 | CONCRETE - ISOLATED PATCHING (IF REQUIRED) | 30 | CF | ||
| 21 | CONCRETE - REBAR REPAIR (IF REQUIRED) | 30 | LF | ||
| 22 | CONCRETE - CRACK REPAIR (IF REQUIRED) | 200 | LF | ||
| 23 | CONCRETE - SAWCUTTING (IF REQUIRED) | 100 | LF | ||
| 24 | CONCRETE - ERODED SURFACE REPAIR (IF REQUIRED) | 400 | SF | ||
| 25 | CONCRETE - TESTING SERVICES (IF REQUIRED) | 1 | LS | ||
| 26 | CONCRETE - SURFACE COATING | 9,200 | SF | ||
| 27 | CONCRETE - HYDRAULIC CYLINDER PITS | 22 | CY | ||
| 28 | PAINT LOCK FILL AND DISCHARGE PIPES | 4 | EA | ||
| 29 | BLAST AND PAINT EMBEDDED STEEL | 1 | LS | ||
| 30 | NEW HANDRAIL, LOCK ACCESS GATE AND LADDER | 1 | LS | ||
| 31 | NEW WATER LINE | 1 | LS | ||
| 32 | INSTALL LOCK MITRE GATES AND NEW HYDRAULIC OPERATORS | 4 | EA | ||
| 33 | INSTALL NEW SLIDE GATES AND NEW HYDRAULIC OPERATORS | 4 | EA | ||
| 34 | HYDRAULIC POWER UNITS | 4 | EA | ||
| 35 | NEW CONTROLS FOR LOCK GATE AND SLIDE GATE OPERATORS | 1 | LS | ||
| 36 | INSTALL NEW MANATEE PROTECTION SCREENS | 8 | EA | ||
| 37 | REINSTALL MANATEE SONAR DETECTION SYSTEM | 1 | LS | ||
| 38 | AS-BUILT SURVEY | 1 | LS | ||
| 39 | SITE CLEANUP AND DEMOBILIZATION | 1 | LS | ||
| 40 | DAILY OVERFLOW IMPACT FEE | 10 | DAYS | ||
| 41 | SUPPLEMENTAL WORK ALLOWANCE | $150,000 | |||