BRDCOM-S3267 Q and A Answers .xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Board Room AV State and local contract opportunity
Solicitation number
BRDCOM-S3267
Issued by
Washoe County, Nevada

About this file

This document is a Bid Q&A spreadsheet for a Board Room Audio/Visual (AV) system procurement by the Nevada State Purchasing Division for the Nevada State Contractors Board, covering locations in Reno and Las Vegas. The project involves replacing a 20-year-old Polycom-based AV system with a new integrated solution, including equipment for board rooms, conference rooms, and lobby areas. The project requires comprehensive AV upgrades with 4K video capabilities, video conferencing integration, Dante audio routing, Crestron control systems, and compatibility with "For The Record" software. Mandatory site visits are scheduled for June 16, 2025, with proposal submissions due by August 21, 2025. The anticipated project completion timeline is flexible, with a desired completion by June 2026, and the State emphasizes minimal disruption to public meetings during system cutover.

The estimated project budget is $225,000, with no specific set-asides for small businesses and no TAA compliance requirements. The procurement allows equipment substitutions and is tax-exempt. Payment terms will follow a Net 30 structure, and no bonds are required. The State will provide secure onsite storage and has existing infrastructure like conduit paths and wall backings. Vendors must provide comprehensive system integration, including network switches, control processors, microphones, speakers, and video conferencing capabilities. The contract includes an initial warranty year with options for three additional years of support, and remote system monitoring is permitted. Vendors must be registered on nevadaepro.com, hold a Nevada business license, and maintain active SAM.gov registration.

View the file

Other files for this state and local contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Q&A for Export Report

Bid Q&A
QUESTION_NBRCREATED_BYQUESTION_SUBJECTQUESTION_TEXTANSWER_TEXT
1RAYK1A-Built DrawingsAre there as-built drawings available for the Las Vegas location?No.
2RAYK1Submission deadlineCan you please verify the submission deadline is 8/21/25?8/21/25 is the deadline.
3WILLGRAYBoard Room AV wiring diagramsAre there current AV wiring diagrams of the existing system?No.
4WILLGRAYBoard Room Existing Polycom 8000The old Polycom 8000 that is being removed is a complete UCC system. What will be used as the UUC appliance? The media PC? How will control be handled?We are open to ideas. We can use a PC and each location with guiidance on how it should be configured.
5WILLGRAYBoard Room sizeHow big is the room? We need to know to properly size the zoom ratios for the cameras.33 ft x 30 ft
6WILLGRAYBoard Room micsHow many microphones are being replaced?Old system has 13 wired and 1 wireless. The nerw system will have 9 at the dias, 4 for witness tables, and 1 at the staff table. Also, the old wireless mic will be replaced with a wireless mic and lavalier.
7WILLGRAYBoard Room mic stylesWhat style microphones are there currently?Wired is Shure MX418D/S
8WILLGRAYBoard Room mixerIs the old mixer ( Make? Model?) being replaced by a DSP?Old mixers are Shure SCM810 and SCM410
9WILLGRAYBoard Room speaker countHow many speakers are in the room?8 in the ceiling and 4 under the dias
10WILLGRAYBoard Room speaker typesAre the speakers flush or surface mounted?Speakers in the ceiling are flush with the tiles. Speakers under the dias are surface mounted.
11WILLGRAYBoard Room tablesThe spec calls out prosecutor and witness tables. Is this an error? Please confirm that the boardroom has these requirements.The prosecutor uses a moveable podium. We usually take a microphone from the dias and place it on the podium. The reason is that during hearings, the dias is not fully occupied. The dias can be fully occupied during board meetings.

There are 2 witness tables for plaintiff and defendant sides of the matter during hearings.

12WILLGRAYBoard Room HDMI portsSame as above statement. Please confirm â??HDMI ports at 9 locations on dais, 2 witness tables, and 1 staff table for owner furnished monitors to display same video sourceâ??. A floorplan would make this easier to visualize.This is confirmed.
13WILLGRAYBoard Room 3.4.4Line 3.4.4 indicates â??Manage cameras and audio of Las Vegas and Reno board rooms from either board roomâ??. Does this statement suggest that we are to design a system that can control remote systems in the other boardroom as in Reno - Las Vegas and vice-versa? If so, please explain further the requirements.This is confirmed. When we used to run just the old Polycom systems at both locations, we could manage the cameras at both locations from either Polycom touch panel. The Polycom provided camera/source for both local and remote sites. We would like similar functionality with the new system.
14WILLGRAYBoard Room TV'sHow are the 4 TVâ??s being utilized? Assuming the NVX will act as a matrix, do we need to provide I/O status and control on the Crestron touch panel for any configuration of source to display?Yes. In the Las Vegas office, we can assign any source to any TV.
15WILLGRAYBoard Room controlIs there a control processor for the Crestron Touch Panels?
a.Model?Not sure. We can provide photos of the Las Vegas equipment rack.
16WILLGRAYBoard Room systemSince the system is changing to an NVX system, are there existing IGMP ethernet switches?No. Switches are needed.
17WILLGRAYBoard Room softwareThe scope indicates â??For The Recordâ?? software, which is court based software. Being the 3rd reference to the judicial system, please clarify the usage in the boardroom.We have the For The Record software. The system needs to integrate with the For The Record computer via Dante.
18WILLGRAYConference room wiring diagramAre there current AV wiring diagrams of the existing system?No.
19WILLGRAYConference room speakersAre the speakers flush or surface mounted?Speakers in the ceiling are flush with the tiles. Speakers under the dias are surface mounted.
20WILLGRAYConference room controllerIs there a control processor for the Crestron Touch Panel?Not sure.
21WILLGRAYLobby wiring diagramsAre there current AV wiring diagrams of the existing system?No.
22WILLGRAYLobby PCWhat is the Media PC supporting/usage?The Media PC runs a continuous presentation. It is often the source mapped to the TV in the lobby.
23WILLGRAYLobby TVThe TV states that it is â??owner furnishedâ??.
a.Are we installing a OFE TV?
b.What is the size?
c.Is there a mount for the TVThe lobby TV exists. It is 65" and mounted to the wall.
24EIDIMGROUPINCLicensesWhat specific audio-visual (AV) licenses or certifications are required for this project?None.
25EIDIMGROUPINCTAA ComplianceAre all AV system components required to be TAA compliant in accordance with FAR 52.225-5?No.
26EIDIMGROUPINCPrevailing WageWill this bid require the payment of prevailing wages?No.
27EIDIMGROUPINCPaymentWill the payment terms for this AV project follow a Net 30 structure, where payment is due 30 days after the invoice date?Yes.
28EIDIMGROUPINCEstimated BudgetWhat is the estimated maximum budget for the AV equipment, installation, and related services for this project?$225,000.00
29EIDIMGROUPINCProject TimelineWhat is the expected timeline for project completion, and is there flexibility for adjusting the completion date?We are flexible. We would like the project to be completed by June 2026 at the latest.
30EIDIMGROUPINCProject MilestoneAre there specific milestones or deadlines that must be adhered to, even with a flexible final date?The schedule of public meetings cannot be interupted. The cutover from the old to new system needs to happen between public meetings.
31EIDIMGROUPINCWorking HoursWhat are the working hours expected for the AV installation team (e.g., 9 AM to 5 PM, Monday to Friday)? Will there be flexibility to work after hours or on weekends if necessary to meet project goals?The office hours are Monday - Friday 7AM - 4PM. Yes, there is flexibility to work after hours and weekends.
32EIDIMGROUPINCMultiple ContractorCan you confirm whether multiple contractors will be operating simultaneously at the job site?We do not expect multiple contractors simultaneiously, unless they are your subcontractors.
33EIDIMGROUPINCSet AsideIs this AV project or contract a set-aside for small, minority-owned, veteran-owned, or women-owned businesses?No.
34EIDIMGROUPINCBondsWill the contractor be required to provide Bid Bonds, Performance Bonds, and Payment
Bonds as part of the AV project? If yes, what will be the amounts or percentage of each bond required?No.
35EIDIMGROUPINCPost-demolitionWho is responsible for all post-demolition finish work (e.g., drywall repair, wall patching, painting, and firestopping) after AV cable routing or device mounting?If not included in the bid, we will find a contractor for the finish work.
36EIDIMGROUPINCStorageWill secure onsite storage be provided for AV equipment, tools, or materials during the installation period?Yes. We have some empty office space available.
37EIDIMGROUPINCLiquidated DamagesIf there are delays in the project, how will labor costs and material prices be adjusted, liquidated damages?We do not anticipate any delays.
38EIDIMGROUPINCExisting AV systemWhat is the current age of the existing AV system?The Polycom and Shure based system is about 20 years old.
39EIDIMGROUPINCSubstitutionsWould you consider allowing substitutions of equipment, provided that the proposed alternatives meet or exceed the specifications and performance of the originally specified items?Yes.
40EIDIMGROUPINCApplicalble Tax RateCould you please confirm if this project includes any applicable taxes? If so, what is the tax rate?We are tax exempt.
41EIDIMGROUPINCCrestron SystemPlease confirm the availability and specifications of the managed network switch that will support the Crestron NVX system. Is it PoE capable? If not, are separate PoE injectors allowed?The network switches for the AV system need to be included in the solution.
42EIDIMGROUPINCAV RackAre AV racks existing, or are vendors required to provide and install new AV racks for both Reno and Las Vegas sites? If existing, please provide photos and available RU (rack unit) space.About 3/4 of a full height 4 post rack is available in the Reno office. Photos were taken during the site visits by the vendor representatives.
43EIDIMGROUPINCPower supplyPlease confirm if sufficient power circuits are available at all AV equipment locations (dais, witness tables, staff table, equipment rooms). If not, will electrical scope be handled by the State or included in vendor pricing?We believe sufficient power is available. If needed, we can have circuits added.
44EIDIMGROUPINCConduitsAre there existing conduit paths or raised flooring between equipment room and the dais/tables/displays? If not, can surface raceways be used, or will the State provide cable pathways?Yes, there are existing conduit paths. The old wiring can be replaced with new wiring. Between rooms, cables can be run above the ceiling grid.
45EIDIMGROUPINCWall reinforcementsAre wall backing reinforcements in place to support 85â?? and 75â?? displays? If not, is vendor responsible for structural support?There are existing wall backing in the board room and lobby. Backing may be needed in the conference rooms.
46EIDIMGROUPINCDisplay OrientationFor 85â?? and 75â?? displays, should orientation be landscape only, or will any display require portrait orientation (e.g., lobby signage)Landscape only.
47EIDIMGROUPINCBYODPlease clarify the required input types and locations for BYOD (e.g., USB-C, HDMI, wireless). Is wireless presentation required (e.g., Barco ClickShare, Mersive Solstice)?We need to provide an HDMI interface for laptop computers giving presentations from the witness tables.
48EIDIMGROUPINCNetwork Video DecoderPlease specify which models of â??Network Video Decoderâ?? are acceptable or preferred for use with the Crestron NVX platform and owner-furnished PCs. Are NVDs required to be Crestron-brand only?We are flexible. Specific brands are not required.
49EIDIMGROUPINCMicrophonesPlease specify the desired Shure microphone model types (e.g., MXA910, MXA920, wireless ULX-D, ceiling/tabled wired). Should microphones include DSP capabilities or integrate with external DSPs (Biamp, QSC, etc.)?Prefer wired Shure MX418D/S, Shure MXW2Z10 wireless mic, Shure MXW1/OZ10 wireless lavalier. Unsure about DSP.
50EIDIMGROUPINCSpeakersPlease specify the performance requirements or preferred brand/model for ceiling speakers (e.g., coverage patterns, speech vs. full-range). Are tile grid ceilings present in both locations?No preference. Grid ceilings are present in board room and conference rooms.
51EIDIMGROUPINCControl processorsAre any redundancies required for critical components such as control processors, network switches, or power supplies?No.
52EIDIMGROUPINCAudio RoutingPlease confirm the required audio routing path for the "legacy PC with For The Record software." Is analog audio sufficient, or is Dante digital audio routing mandatory?Dante is mandatory or provide another solution to bring the audio into the PC that is compatible with ForTheRecord software.
53EIDIMGROUPINCCrestron ProgrammingPlease confirm if the State has existing Crestron programming source code for the Las Vegas site, or will vendor need to reverse engineer to integrate control between sites?Reverse engineering is needed.
54EIDIMGROUPINCRemote System AccessWill the State allow remote system monitoring and control?Yes.
55EIDIMGROUPINCPortsShould vendor provide grommet-mounted HDMI ports or under-table boxes for the HDMI input locations (9 dais, 2 witness, 1 staff)? If not, will existing furniture be reused or modified?Yes. We photo of LV witness table to show preferred method.
56EIDIMGROUPINCTouch Panel LocationsPlease provide the exact desired mounting locations for the 10â?? and 5â?? Crestron touch panels. Should they be wall-mounted, recessed, or table-top-mounted? Power and data availability at each location?Table top mounted Crestron touch panels at staff table in board room, and at each conference room table.
57EIDIMGROUPINCUSB ReceiversAre USB receivers for the wireless keyboard/mouse to be mounted behind the display, or routed back to the media PC? Is there a preferred model or standard (e.g., Logitech, Microsoft)?USB receivers can be mounted behind/near the display. Prefer Logitech.
58EIDIMGROUPINCVedio Conferencing PlatformsIs Microsoft Teams Room (MTR) or Zoom Room appliance mode required, or is general interoperability through BYOD or external PC connection acceptable?We need to connect both the Las Vegas and Reno boardrooms on a regular basis. We are open to learning best practice regarding a pure Crestron solution or also adding Zoom clients. If Zoom room implementation is required, please specify the configuration. Also, during meetings, presentations from the witness tables need to also be visible when Zoom is being used to support remote participation.
59EIDIMGROUPINCWarrantyPlease confirm warranty duration expectations for both equipment and labor. Is 1-year labor standard acceptable, or is an extended warranty contract desired?In addition to standard warranty, we need to be able to subscribe to annual support.
60EIDIMGROUPINCService Response TimeWhat are your required response times for support via email, phone, and onsite service, and how many years of warranty?Live email and phone during normal business hours. 24 hours for onsite. Initial year plus 3 years of support.
61EIDIMGROUPINCConstruction WorkPlease confirm if mounting hardware (e.g., wall backing for displays, ceiling reinforcements for speakers/mics, conduit/raceways) is part of the AV contractorâ??s scope. If structural or construction work is required, will it be subcontracted or provided by the owner?Yes. Mounting hardware is in scope. Other construction work can be provided by us.
62EIDIMGROUPINCDecommissioningShould the AV vendor remove and dispose of legacy equipment, or should the removed equipment be turned over to the owner for storage? If turned over, is there a designated staging area on site?We will retain old equipment. There will be a designated room or area for old equipment.
63EIDIMGROUPINCInstallation TimeCan you provide room-specific installation time windows (business hours only or after-hours/weekend work required)? Are there any noise limitations or security access restrictions?Acitivity with loud noises need to occur outside normal business hours to reduce impacting our business activity and other tenants. The actual cutover from the old to new system needs to occur between scheduled public meetings.
64EIDIMGROUPINCNew Video ConferencingDoes â??implementation of new video conferencing software/hardwareâ?? require full system configuration of Microsoft Teams/Zoom Room licenses, user accounts, and IT policy enforcement, or is the vendor only responsible for hardware readiness and AV integration?We need help to understand what is required to implement the recommended best practice.
65EIDIMGROUPINCTrainingPlease confirm if project staffing must include on-site personnel only, or if remote system programming/configuration staff may be utilized as part of the team.We prefer training to be done in-person. Other work can be done remotely, if desired.
66EIDIMGROUPINCBackground ChecksAre there any requirements for background checks, badges, finger printing or security clearance for vendor staff working in either the Reno or Las Vegas locations?No.