The file's text, extracted by GovTribe without its formatting.
Instructions
| 1. General Instructions |
| Do not modify the structure of this Excel file. |
| Offeror shall only enter data in the green-shaded cells. All other cells and tabs have calculated fields or contain data entered by FDIC. |
| For the purposes of this pricing workbook, Offeror shall assume 1 FTE is equal to 1920 hours annually. |
| 2. "BASE PoP and KPs" Tab |
| The FDIC has pre-populated the BASE Period of Performance of 6 mothns based on anticipated need. The FDIC understands that long lead items may impact the contemplated timeframe. |
| The offeror may propopse a BASE Period of Performance based on long lead items. |
| The FDIC has pre-populated four of the five Key Personnel labor categories and hours based on anticipated need for the BASE Period. |
| The offeror may propose key personnel in addition to the Program Manager, Solution Architect, Installer/Engineer, and Programmer KPs; however, the total FTEs for the KPs must add up to 4.0. |
| 3. "CLIN 1 D&CONST" Tab |
| Enter the period of performance dates and total price for design and, for each room, construction. |
| 4. "CLIN 2 AV BR," "CLIN 3 AV 6021," "CLIN 4 AV 6015," and "CLIN 5 AV CTROL SPACE" Tabs |
| For the corresponding rooms in the Tabs, enter the details for all of the HwSw (Hardware, Software, Licence, Services, Shipping) and Installation (Equipment, Services, Shipping). |
| 5. "CLIN 6," "CLIN 7," "CLIN 8," and "CLIN 9" Tabs |
| For the corresponding rooms in the Tabs, enter the details for the technology integration furniture. Any furniture used to camoflouge technology (e.g. TV lift) should be included in the Tabs at Item 4. |
| 6. "CLIN 10" Tab |
| The FDIC has pre-populated the two Key Personnel labor categories and hours based on anticipated need for the Operations and Maintenance Option Periods. |
| The offeror may propose key personnel in addition to the Installer/Engineer and Programmer KPs; however, the total FTEs for the KPs must add up to 2.0. |
| Enter the details for all of the Option Periods (Hardware, Software, Licence, Services, Shipping). |
| 7. "CLIN 11" Tab |
| FDIC may procure future FFP goods and services. Because the exact scope of these goods and services are not currently defined, Offerors are not required to provide estimates. |
| In order to determine the potential total cost of awarding the Contract, FDIC will use a model. |
| The calculations for the totals included on this tab (based on Hardware/Software, Installation, Construction, and Furniture) are for evaluation purposes only and are the same for all Offerors. |
| 8. "Summary Price" Tab |
| This tab does not require Offeror input. It displays the summary charges for each CLIN. |
| The proposed CLIN pricing along with the FFP Model pricing will constitute the overall evaluated price (OEP). This computation will be for evaluation purposes only. |
&"Source Sans Pro SemiBold"&12&K000000 CONTROLLED//FDIC INTERNAL ONLY&1#_x000D_
Summary
| CLIN | ITEM | TYPE | BASE | OP1 | OP2 | OP3 | OP4 | Total |
| 1 | Construction | FFP | $ - 0 | | | | | $ - 0 |
| 2 | Board Room | FFP | $ - 0 | | | | | $ - 0 |
| 3 | Conference Room A (6021) | FFP | $ - 0 | | | | | $ - 0 |
| 4 | Conference Room B (6015) | FFP | $ - 0 | | | | | $ - 0 |
| 5 | Control Space | FFP | $ - 0 | | | | | $ - 0 |
| 6 | Optional Furniture Board Room (Construction) | FFP | $ - 0 | | | | | $ - 0 |
| 7 | Optional Furniture Conference Room A (6021) (Construction) | FFP | $ - 0 | | | | | $ - 0 |
| 8 | Optional Furniture Conference Room B (6015) (Construction) | FFP | $ - 0 | | | | | $ - 0 |
| 9 | Optional Furniture Control Space (Construction) | FFP | $ - 0 | | | | | $ - 0 |
| 10 | Optional Operations and Maintenance (O&M) | FFP | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 11 | Optional Future Incremental Improvements (FII) | FFP | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| | | | | | | TOTAL: | $ - 0 |
| BASE | From Contract Award to Solution Acceptance |
| OP1 | From Solution Acceptance to Solution Acceptance + 1 year |
| OP2 | From OP1 End to OP1 End + 1 Year |
| OP3 | From OP2 End to OP2 End + 1 Year |
| OP4 | From OP3 End to OP3 End + 1 Year |
BASE PoP and KPs
| | Period of Performance for Base | |
| (if different than 6 months) | Number of months from Award | | |
| | Base Period of Performance | 6 |
| Anticipated Program Manager, Solution Architect, Installer/Engineer, and Programmer Key Personnel Labor Categories for All Rooms for CLINs 2-5 | Average Monthly FTEs |
| Program Manager | 1.00 |
| Solution Architect | 1.00 |
| Installer/Engineer | 1.00 |
| Programmer | 1.00 |
Total 4.00
CLIN 1 D&CONST
BRC Modernization - CLINs 1-5 Design & Construction (D&CONST) (FFP)
| | CLIN | Type - Room(s) | Period of Performance | |
| (i.e. 1/1/2023 - 12/31/2023) | Total Charges for Period | | | | |
| | 1 | Design - All Rooms | | |
| | 2 | Construction - Board Room | | |
| | 3 | Construction - Conference Room A (6021) | | |
| | 4 | Construction - Conference Room B (6015) | | |
| | 5 | Construction - Control Space | | |
| | | | TOTAL: | $ - 0 |
| | | | ` | |
CLIN 2 AV BR
| | | BRC Modernization - CLIN 2 Board Room (BR) Audio Video (FFP) | | | | | | |
| Item Number | Area | | | | | | | |
| (HwSw = Hardware/Software | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| | | | | | | | | $0.00 |
| SubTotal (HwSW) | $0.00 |
| SubTotal (Installation) | $0.00 |
| Total | $0.00 |
CLIN 3 AV 6021
| | | BRC Modernization - CLIN 3 6021 Audio Video (FFP) | | | | | | | | |
| Item Number | Area | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| SubTotal (HwSW) | $0.00 |
| SubTotal (Installation) | $0.00 |
| Total | $0.00 |
CLIN 4 AV 6015
| | | BRC Modernization - CLIN 4 6015 Audio Video (FFP) | | | | | | | | |
| Item Number | Area | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| SubTotal (HwSW) | $0.00 |
| SubTotal (Installation) | $0.00 |
| Total | $0.00 |
CLIN 5 AV CTRL SPACE
| | | BRC Modernization - CLIN 5 Control Space Audio Video (FFP) | | | | | | | | |
| Item Number | Area | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| | | | | | | | | | | $0.00 |
| SubTotal (HwSW) | $0.00 |
| SubTotal (Installation) | $0.00 |
| Total | $0.00 |
RL CLIN 1 AV BR
| Area | PC INSTL | PC HWSW | Purchase Type | | HARDWARE | SOFTWARE | LICENSE |
| HwSw | EQUIPMENT | HARDWARE | GOODS | | GOODS | GOODS | PERPETUAL (one-time) |
| Installation | SERVICES | SOFTWARE | WARRANTY | | WARRANTY | | SUBSCRIPTION (annual) |
| SHIPPING | LICENSE | MAINTENANCE | | | | |
| | SERVICES | SUPPORT | | | | |
| | SHIPPING | | | | | |
| | | | BOTH | SERVICES | SHIPPING | |
| | | | | SUPPORT | | |
| | | | | EQUIPMENT | | |
| | | | | GOODS | | |
| | | | | WARRANTY | | |
CLIN 6
| | BRC Modernization - Optional CLIN 6 Board Room (BR) Furniture (FFP) | | | | | | | | | |
| Item Number | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | | | | | | | | | Total | $0.00 |
CLIN 7
| | BRC Modernization - Optional CLIN 7 Conference Room A (6021) Furniture (FFP) | | | | | | | | | |
| Item Number | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | | | | | | | | | Total | $0.00 |
CLIN 8
| | BRC Modernization - Optional CLIN 8 Conference Room B (6015) Furniture (FFP) | | | | | | | | | |
| Item Number | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | Furniture | | | | | | | | | $0.00 |
| | | | | | | | | | Total | $0.00 |
CLIN 9
| | BRC Modernization - Optional CLIN 9 Control Space Furniture (FFP) | | | | | | | | | |
| Item Number | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | Furniture_CS | | | | | | | | | $0.00 |
| | | | | | | | | | Total | $0.00 |
RL CLIN 6
| Furniture |
| Technology Integration Table |
| Technology Integration Podium |
| Technology Integration Furniture (other) |
| Furniture CR |
| Technology Integration Workstation |
| Technology Integration Furniture (other) |
CLIN 10
| Anticipated Installer/Engineer and Programmer Key Personnel Labor Categories for Operations and Maintenance | Average Monthly FTEs |
| Installer/Engineer | 1.00 |
| Programmer | 1.00 |
| | | | Total | 2.00 | | | | | | | |
| | | BRC Modernization - Optional CLIN 10 Operations and Maintenance (FFP) | | | | | | | | | |
| Item Number | Option Period | Purchase Category | Purchase Type | Description | Manufacturer | Part # | Qty | Serial # | Period of Performance | | |
| (i.e. 1/1/2023 - 12/31/2023) | Est. Unit Cost | Est. Total Cost | | | | | | | | | | |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | | $0.00 |
| | | | | | | | | | | Total | $0.00 |
RL CLIN 10
| Option Period | Purchase Category | Purchase Type | HARDWARE | SOFTWARE | LICENSE | SHIPPING | SERVICES |
| OP1 | HARDWARE_OM | GOODS | MAINTENANCE | MAINTENANCE | MAINTENANCE | | SUPPORT |
| OP2 | SOFTWARE_OM | WARRANTY | | | | | |
| OP3 | LICENSE_OM | MAINTENANCE | | | | | |
| OP4 | SHIPPING_OM | SUPPORT | | | | | |
| SERVICES_OM | | | | | | |
CLIN 11
| BRC Modernization - Optional CLIN 11 Future Incremental Improvements (FFP) | | |
| Option Period | Description | Cost |
| 1 | FFP Model Calculation for Evaluation Purposes Only | $0.00 |
| 2 | FFP Model Calculation for Evaluation Purposes Only | $0.00 |
| 3 | FFP Model Calculation for Evaluation Purposes Only | $0.00 |
| 4 | FFP Model Calculation for Evaluation Purposes Only | $0.00 |
| TOTAL: | $0.00 |
RL CLIN 11
| 20% of total Hardware/Software, Installation, Construction, and Furniture | OP1 |
| (12 months) | OP2 | |
(12 months at 3% escalation) OP3 (12 months at 3% escalation) OP4 (12 months at 3% escalation) $0.00 $0.00 $0.00 $0.00 $0.00
| Amount per month across 48 months |
| $0.00 |