This statement of work and related federal contract opportunity are for fire protection system upgrade projects at the Binghamton Federal Building and Courthouse in Binghamton, New York. The statement of work details a project to install a new building-wide fire sprinkler system and replace the existing fire alarm system across approximately 75,074 square feet. Relatedly, the federal contract opportunity posted by the General Services Administration seeks construction services including removing and replacing the fire alarm system while also expanding the sprinkler system throughout the entire building. Offerors are required to adhere to all security requirements and guidelines for building access. The selected contractor will provide onsite supervision at all times work is being performed, including afterhours work as needed.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration Public Buildings Service
Binghamton Federal Building and Courthouse
Statement of Work:
Project: Binghamton Fire sprinkler and alarm Location: Binghamton Federal Building and Courthouse, Binghamton, NY Date: 12/17/2019
1. Scope of Work:
The Contractor shall provide all labor, materials, equipment, tools, management, and full time on site supervision required by contract documents to install a building wide fire sprinkler and fire alarm system inclusive of the de-activation then removal of the existing fire alarm system once the new system has been fully commissioned and placed in service at the Binghamton Federal building and Courthouse, Binghamton, NY. Base interior work shall include, but is not limited to, construction of protection for artwork, new sprinkler system, new fire alarm system, demo of existing fire alarm system, and testing. Exact work description is identified and indicated in the Contract Documents. The contractor shall comply with the projects design specifications and drawings. The work will be constructed under a single prime contractor who is to adhere to all security requirements and guidelines for building access. The contractor is also to provide onsite supervision at all times work is being performed, including afterhours work as needed.
The total project area is approximately 75,074 SF.