This is a Contract Agreement between Elbert County, Georgia, and a contractor for roadway resurfacing and reconstruction work. The project involves full-depth reclamation and resurfacing on Ernest Brown Road, Limo Road, and Owens Road, encompassing 3.53 miles of patching and asphaltic concrete resurfacing. Specific work items include placement of approximately 12,550 square yards of full-depth reclamation, 700 tons of recycled asphaltic concrete patching, approximately 2,850 tons of 9.5mm recycled asphaltic concrete topping, and approximately 4,290 tons of 19mm recycled asphaltic concrete, along with roadway striping. The contractor shall commence work within ten days of receiving a written Notice to Proceed and must complete all work within 180 consecutive calendar days. All work must comply with applicable codes, ordinances, rules, regulations, and laws of local authorities. The contract documents include the agreement, exhibits, performance and labor/material payment bonds, notice of award, notice to proceed, Georgia Department of Transportation Standard Specifications, addenda, the contractor's bid, and E-Verify documentation.
Progress payments shall be made monthly, with the contractor submitting payment requests by the 25th of each month for work accomplished and materials furnished or stored on-site. Progress payments will be made at 90 percent of completed work prior to substantial completion, with no retainage applied to requests submitted after 50 percent of work is completed on schedule. The owner will pay approved requests within 30 days of receipt, less retainage and other deductions. Final payment of the contract balance will be made upon acceptance of work. Liquidated damages are set at $500 per day for failure to substantially complete the project within the contract time plus any approved extensions. The contractor must maintain a Georgia business license and is required to indemnify the owner against claims arising from the contractor's negligent performance. Contract documents may only be modified by written consent of the owner.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2 Invitation to Bid.doc | DOC document | |
| 5 ROADWAY TYPICAL ASPH.docx | DOCX document | |
| 3 Instruction to Bidder.doc | DOC document | |
| 6 SEC 400.pdf | ||
| 5_E ss109.pdf | ||
| 5 SPECIAL PROVISIONS FOR FDR_ERNEST BROWN RD.docx | DOCX document | |
| Security and Immigration AFfidavit.doc | DOC document | |
| 4 BID FORM.doc | DOC document | |
| i_9 2027.pdf | ||
| AGREEMENT.doc | DOC document | |
| 6 SEC 652.pdf | ||
| 5_C ss107.pdf | ||
| 5_D ss108.pdf | ||
| 6 SEC 162_165.pdf | ||
| 6 SEC 315.pdf | ||
| 5 SPECIAL PROVISION.docx | DOCX document | |
| 5 ROADWAY TYPICAL ASPH_ERNEST BROWN RD (1).docx | DOCX document | |
| E_verify affidavit.pdf | ||
| 5_F 150.pdf | ||
| 5 PROJECT MAP.pdf | ||
| 5_A104.pdf | ||
| Corporate Certification.doc | DOC document | |
| 5_B ss105.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00500-7
ADVANCE \D 1.80
Contract Agreement
PRIVATE
ADVANCE \D 2.10ADVANCE \D 10.50
SECTION 00500
Contract Agreement THIS AGREEMENT is dated as of the _______ day of ______________ in the year 2026, by and between the Elbert County Georgia (hereinafter called OWNER), and
(hereinafter called CONTRACTOR). OWNER and CONTRACTOR, inconsideration of the mutual covenants hereinafter set forth, agree as follows:
The Project consists of, but is not limited to the following major elements on ERNEST BROWN RD (FULL DEPTH RECLAMATION&RESURFACE), LIMO RD AND OWENS RD.
3.53 miles of patching, 9.5mm/19mm recycled asphaltic concrete resurfacing.
(1.15 miles of FDR on Ernest Brown Rd (Bobby Brown Rd to Owens Rd))
Placement of approximately 12,550 SY of FDR, 700 TN of recycled asphaltic concrete patching, approximately 2,850 TN of 9.5 mm recycled asphaltic concrete topping and approximately 4,290 TN of 19mm recycled asphaltic concrete and roadway striping.
It is understood that the quantities shown are approximates only and subject to either increase or decrease and any increases or decreases are to be paid for at the contract unit prices given, labeled Exhibit A, attached hereto and incorporated herein by reference.
ARTICLE 1 – WORK
CONTRACTOR shall complete all WORK as specified or indicated in the CONTRACT DOCUMENTS. The WORK described previously includes all material, labor, tools, equipment, and any other miscellaneous items necessary to complete the work as described in the Specifications and Construction Drawings. All work shall be completed in accordance with all applicable codes, ordinances, rules, regulations and laws of local authorities having jurisdiction.
ARTICLE 2 – CONTRACT TIME
CONTRACTOR agrees to commence WORK within ten (10) days of a date to be specified in a written “Notice to Proceed” from the OWNER and to fully complete the contract in a total construction time of one hundred and eighty (180) consecutive calendar days.
Time for Completion: OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the WORK is not substantially complete within the time specified above, plus any extension thereof allowed by the OWNER. They also recognize the delays, expense and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by OWNER if the WORK is not substantially complete on time. Accordingly, OWNER and CONTRACTOR understand and recognize that it is impossible to conclusively assess damages to the OWNER for the failure of the CONTRACTOR to substantially complete the project in a timely manner. Therefore, the OWNER and CONTRACTOR have agreed that a reasonable amount of damages for each day that the project remains incomplete after the contract time (as stated above) has expired would be the amount of $500.00.
ARTICLE 3 – CONTRACT PRICE
OWNER shall pay CONTRACTOR for performance of the WORK in accordance with the CONTRACT DOCUMENTS in current funds as follows:
ARTICLE 4 – PAYMENT PROCEDURES
CONTRACTOR shall submit Application for Payment in accordance with these Specifications.
Progress Payments: CONTRACTOR shall furnish to OWNER, no later than the 25th day of each month, a progress payment request for the amount of work accomplished, products furnished, and products stored at the site during the previous month. The progress payment request shall be signed by the CONTRACTOR and be supported by such data as OWNER may reasonably require. ENGINEER shall review and indicate in writing approval of the payment request to the OWNER within ten days after receipt of each progress payment request. The OWNER will, within thirty days after receipt of progress payment request, pay CONTRACTOR based on the approved progress payment request, less the retainage and deductions pursuant to the terms of these CONTRACT DOCUMENTS.
Prior to Substantial Completion, progress payments will be made in an amount equal to:
90% of the WORK completed.
No amount shall be retained on progress payment requests submitted after 50% of the WORK has been completed on schedule. This will not affect the retained amounts on the first 50% of the work which may continue to be held to ensure satisfactory completion of the project. If, after discontinuing retention, OWNER determines that the work is unsatisfactory or has fallen behind schedule, retention may be resumed at the previous level.
If the CONTRACTOR falls behind schedule to the point the time of completion, plus time extensions, has elapsed, then the amount specified for liquidated damages will be deducted from all CONTRACTOR pay requests submitted after the latest time of completion.
Final Payment: Upon acceptance of WORK in accordance with these specifications, OWNER shall pay balance due of Contract Price less payments previously made.
ARTICLE 5 – INDEMNIFICATION
The CONTRACTOR shall indemnify and hold harmless the OWNER and their agents and employees from and against all claims, damages, losses and expenses, including but not limited to attorney’s fees, arising out of or resulting form the performance of the WORK, provided that any such claim, damage, loss, expense or attorney’s fees is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property including the loss of use resulting therefrom, and is caused in whole or in part by any negligent act or omission of the CONTRACTOR, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not the negligent act is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or otherwise reduce any other right or obligation of indemnity which would otherwise exist as to any party or person described in this Clause. In any and all claims against the OWNER or any of their agents or employees, by any employee of the CONTRACTOR, any Subcontractor, anyone directly or indirectly employed by any of them or anyone whose acts any of them may be liable, the indemnification obligation set forth in this paragraph shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the CONTRACTOR or any Subcontractor under workers’ or workmens’ compensation acts, disability benefit acts or other employee benefit acts.
ARTICLE 6 – CONTRACTOR’S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations:
CONTRACTOR has familiarized himself with the nature and extent of the CONTRACT DOCUMENTS, WORK, locality, and with all local conditions and federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the WORK. CONTRACTOR is aware that he must be licensed to do business in the State of Georgia.
CONTRACTOR has studied carefully all reports of investigations and tests of subsurface and latent physical conditions at the site or otherwise affecting cost, progress or performance of the WORK which were relied upon by design ENGINEER in preparation of the Drawings and Specifications.
CONTRACTOR has made or caused to be made examinations, investigations and tests, and studies of such reports and related data, as he deems necessary for the performance of the WORK at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents; and no additional examinations, investigations, tests, reports or similar data are or will be required by CONTRACTOR for such purposes.
CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports, and data with the terms and conditions of the CONTRACT DOCUMENTS.
CONTRACTOR has given OWNER written notice of all conflicts, errors, or discrepancies that he has discovered in the CONTRACT DOCUMENTS and the written resolution thereof by OWNER is acceptable to CONTRACTOR.
ARTICLE 7 – CONTRACT DOCUMENTS
The CONTRACT DOCUMENTS which comprise the entire agreement between OWNER and CONTRACTOR are attached to this Agreement, made a part hereof and consist of the following:
7.1 This Agreement
7.2 Exhibits to this Agreement including the following:
Advertisement for Bidders, Instructions to Bidders, Special Provisions, Bid Form and associated documents
7.3 Performance and Labor and Material Payment Bonds
7.4 Notice of Award
7.5 Notice to Proceed
7.6 Georgia Department of Transportation Standard Specifications for Construction of Roads and Bridges, latest Edition
7.7 Addenda , inclusive. (Issued dates)
7.8 CONTRACTOR’S Bid
7.9 Documentation submitted by CONTRACTOR prior to Notice of Award
7.10 Any modifications, including Change Orders, duly delivered after execution of Agreement.
7.11
E-VERIFY FORM
There are no CONTRACT DOCUMENTS other than those listed above in the Article 7. The CONTRACT DOCUMENTS may only be altered, amended or repealed by expressed written consent of OWNER.
ARTICLE 8 – MISCELLANEOUS
Terms used in this Agreement which are defined in the General Conditions shall have the meanings indicated in the General Conditions.
No assignment by a party hereto of any rights under or interests in the CONTRACT DOCUMENTS will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but without limitation, moneys that may become due and moneys that are due, may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge the assignor from any duty or responsibility under CONTRACT DOCUMENTS.
OWNER and CONTRACTOR each binds himself, his partners, successors, assigns and legal representatives to the other party hereto, his partners successors, assigns and legal representatives in respect to all covenants, agreements, and obligations contained in the CONTRACT DOCUMENTS.
The term Special Conditions as used in the General Conditions or elsewhere in the CONTRACT DOCUMENTS, refers to the “Supplementary General Provisions”.
The Supplementary General Provisions are intended to supplement, rather than replace, the General Conditions, except where the Supplementary General Provisions are in direct conflict with the General Conditions, the Supplementary General Provisions shall control.
ARTICLE 9 – PROVISIONS FOR TERMINATION OF CONTRACT
If through any cause, other than an “Excusable Delay”, CONTRACTOR shall fail to fulfill its obligations under this Contract in a timely and proper manner, or if CONTRACTOR shall violate any of the covenants, agreements, conditions or obligations of the CONTRACT DOCUMENTS; OWNER may terminate this Contract. In such event, OWNER may take over the WORK and prosecute the same to completion, by Contract or otherwise, and CONTRACTOR and his sureties shall be liable to OWNER for any additional cost incurred by OWNER in its completion of the WORK and they shall also be liable to OWNER for liquidated damages for any delay in the completion of the WORK as provided below.
Liquidated Damages for Delay: If the work is not completed within the time stipulated, therefore, including any extension of time for excusable delays as herein provided, CONTRACTOR shall pay to OWNER as fixed and agreed, liquidated damages for each working day of delay, until the work is completed, and CONTRACTOR and his sureties shall be liable to OWNER for this amount.
Excusable Delays: The right of CONTRACTOR to proceed shall not be terminated nor shall CONTRACTOR be charged with liquidated damages for any delays in the completion of the work due:
9.1 To any acts of the Government, including controls or restrictions upon or requisitioning of materials, equipment, tools, or labor by reason of war, National Defense, or any other national emergency;
9.2 To causes not reasonably foreseeable by the parties to this Contract at the time of the execution of the Contract which are beyond the control and without the fault or negligence of CONTRACTOR, including, but not restricted to, acts of a public enemy, acts of another CONTRACTOR in the performance of some other contract with OWNER, fires, floods, epidemics, quarantine, freight embargoes, and weather of unusual severity such as hurricanes, tornados, and cyclones;
9.3 To acts of OWNER which cause delays, and;
Provided, however, that CONTRACTOR promptly notified OWNER within ten days in writing of the cause of the delay. Upon receipt of such notification, OWNER shall ascertain the facts and the cause and extent of the delay. If upon the basis of the terms of this Contract, the delay is properly excusable, OWNER shall extend the time for completing the WORK for a period of time commensurate with the period of excusable delay.
IN WITNESS WHEREOF, the parties hereto have signed this Agreement. All portions of the CONTRACT DOCUMENTS have been signed or identified by OWNER and CONTRACTOR.
OWNER
BY: ___________________________________________
TITLE: Elbert County Commission Chairman
ATTEST: ______________________________________
Clerk
(Seal)
CONTRACTOR
BY: ___________________________________________
TITLE: ________________________________________
ATTEST: ______________________________________
Corporate
Secretary/Partner/Notary
(Seal) NOTE: Attest for a corporation must be by the corporate secretary; for a partnership by another partner; for an individual by a Notary.
ADDRESSES FOR GIVING NOTICE
OWNER:
CONTRACTOR:
Elbert County
45 Forest Avenue
Elberton, GA 30635
Phone:
706 283-2000
Phone:
END OF SECTION