Bid_25-14._Addenda_4.pdf

PDF 143 KB Posted

Attached to
East Palatka Septic to Sewer Project - Phase IV
Solicitation number
Bid 25-14
Issued by
Polk County, Florida

About this file

This is an Addendum document issued by the Putnam County Procurement Department for Bid 25-14, the East Palatka Septic to Sewer Project - Phase IV, a comprehensive wastewater infrastructure initiative located in the Dunns Creek area of Putnam County, Florida. The project involves construction of 167 individual residential grinder pump stations, approximately 5,728 linear feet of 2-inch HDPE force main piping, 13,281 linear feet of 3-inch HDPE force main piping, and a master pump station serving 323 single-family homes across multiple streets in the area. Addendum #4 revised the bid due date to Wednesday, May 7, 2025, at 2:00 PM EST. The mandatory pre-bid meeting is scheduled for Thursday, April 3, 2025, with written questions due by 2:00 PM on Monday, April 21, 2025, submitted via email to Leigh.Doran@putnam-fl.gov. The public opening of proposals is scheduled for Wednesday, May 7, 2025, with an Intent to Award recommendation scheduled for Monday, May 12, 2025, and presentation to the Putnam County Board of County Commissioners on May 13, 2025. The protest period runs from May 12 through May 15, 2025. The preconstruction conference is scheduled for May 27, 2025, with project completion required within 395 calendar days from the Notice to Proceed, with a final completion date of Friday, June 26, 2026.

The project requires bidders to submit a bid bond equal to 5 percent of the total bid amount. All work must comply with Florida Department of Environmental Protection (FDEP) and Florida Department of Transportation (FDOT) specifications, including directional bores under roadways and driveways along US 17 (SR 15). The FDEP permit for the project is effective from October 29, 2024, and expires on October 28, 2029. The project is funded through local government channels and focuses on converting existing septic systems to centralized sewer infrastructure, with Putnam County Public Works responsible for operation and maintenance of on-lot facilities. Bid documents, construction specifications, and drawings are available online at https://main.putnam-fl.com/?page_id=65#callforbidslink.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PUTNAM COUNTY

PROCUREMENT DEPARTMENT

2509 CRILL AVE, STE 200

PALATKA, FL 32177

Bid 25-14 East Palatka Septic to Sewer Project – Phase IV

Addenda # 4 April 23, 2025

TO ALL BIDDERS SUBMITTING A RESPONSE ON THIS PROJECT

The changes, additions, substitutions, and/or deletions contained in Addenda #4 are hereby made part of the Contract Documents fully and completely for this Bid.

** The bid due date has been changed to Wednesday, May 7, 2025 at 2:00 PM. **

Tentative Schedule:

Issue BID Wednesday, March 26, 2025 Mandatory Pre-Bid Meeting Thursday, April 3, 2025 Written questions due by 2:00 pm Monday, April 21, 2025 *submit via email Leigh.Doran@putnam-fl.gov Proposals Due by 2:00 pm Tuesday, April 29, 2025 Proposals Due by 2:00 pm Wednesday, May 7, 2025 Public Opening of Proposals Tuesday, April 29, 2025 Public Opening of Proposals Wednesday, May 7, 2025 Intent to Award* Monday, May 5, 2029 Intent to Award* Monday, May 12, 2029 Protest Period May 5, 2025 – May 8, 2025 Protest Period May 12, 2025 – May 15, 2025

*The Bid Award in contingent upon acceptance and approval by the Putnam County Board of County Commissioners of the recommended Intent to Award. The recommendation of the Intent to Award is scheduled to be presented at the board meeting on May 13, 2025. May 27, 2025

Preconstruction Conference May 27, 2025 Preconstruction Conference June 10, 2025 Project Completion Date Friday, June 26, 2026

*(395 Days from Pre Construction Meeting/Receipt of Notice to Proceed)

Project Completion Date Friday, June 26, 2026 *(395 Days from Pre Construction Meeting/Receipt of Notice to Proceed) Friday, July 10, 2026