This document is a Response to Clarifying Questions #3 for Invitation to Bid #2026-78 issued by Clackamas County, on behalf of Water Environment Services, regarding refurbishment of the Tri-City Water Resource Recovery Facility (WRRF) aeration basins. The clarifying questions document addresses two inquiries submitted by interested bidding firms: a discrepancy regarding the quantity of slide gates specified in Drawing 320-D-3001 Keynote 1, and a request for additional information on concrete repair and injection details. The county confirmed that each basin contains four 24" by 24" slide gates and twelve 12" by 12" slide gates (noting a correction from the original drawing notation), positioned along the influent side of each basin opposite the flush valve side. Regarding the concrete repair inquiry, the county stated that no additional information beyond the bid documents is available. This clarifying questions response was issued on November 9, 2026, prior to the bid submission deadline of November 10, 2026 at 2:00 PM Pacific Time.
The scope of work encompasses basin cleaning and structural repairs, replacement of 16 zonal air flow control assemblies, diffuser membrane head replacements in three basins, air piping modifications, valve replacements, installation of four access hatches, and SCADA system upgrades across four conventional activated-sludge aeration basins. Work is scheduled in two phases, with Aeration Basins 1 and 2 substantially complete by September 30, 2027, and Aeration Basins 3 and 4 by September 30, 2028, occurring during summer shutdown seasons with strict operational constraints including maintaining maximum two basins offline simultaneously and limiting air flow interruptions to 30 minutes. The engineer's estimate is $3.7 million with a contract completion requirement of 700 days from commencement and liquidated damages of $2,290 per day for missed milestone dates. Bid security of 10% and performance and payment bonds of 100% each are required. Prevailing wage requirements apply under Oregon Revised Statutes, and the county encourages bids from Minority, Women, and Emerging Small Businesses (M/W/ESB) with Good Faith Effort requirements mandating prime contractors contact at least three M/W/ESB subcontractors for each subcontracted division.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID #2026-78
Tri-City Water Resource Recovery Facility (WRRF) Aeration Basin Improvements (“BID”)
RESPONSE TO CLARIFYING QUESTIONS #3
November 9, 2026
Note that these are questions submitted by interested firms to the above referenced solicitation.
The below answers are for clarification purposes only and in no way alter or amend the BID as published.
1. Drawing number 320-D-3001, Keynote 1 (KN1) states that each basin has (4) 24” x 24” slide gates and (12) 10” x 10” slide gates. However, the drawing shows (3) 24” x 24” and (13) 10” x 10” slide gates. Please confirm the quantity of slide gates for each basin.
Answer: Confirmation of KN1: the quantity is confirmed as stated in Keynote 1: Each Basin has four (4) 24" by 24" slide gates and twelve (12) 12" by 12" slide gates.
Correction to KN1: these gates are along the influent side of each basin, which is opposite the flush valve side of each basin.
2. I wanted to see if Jacobs Engineering had any details available that relate to the concrete repair and injection for the Tri – City water project.
Answer: No further information is available beyond the information provided in the Bid Documents.
End of Clarifying Questions #3