39-Sec 01 55 26 - TRAFFIC REGULATION.pdf

PDF 59 KB Posted

Attached to
Bristol Borough 2025 CDBG Curb Ramp Program
Solicitation number
US.193830
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

View the file

Other files

File Type Posted
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
25-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
61-Addendum 1.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
58-Location Map.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
45-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRAFFIC REGULATION

01 55 26-1

SECTION 01 55 26

TRAFFIC REGULATION

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. This Section involves the Contractor’s obligations relative to maintaining the safe and efficient movement of traffic in the vicinity of construction.

B. Contractor will be required to furnish, erect, and maintain traffic cones, drums, barricades, flashing danger signal lights, directional signs and provide trained and equipped flagmen as required by the Borough to restrict the movement of traffic within the construction areas and to clearly indicate the restrictions well in advance to vehicular traffic.

1.02 SECTION INCLUDES

A. Traffic Control Plan.

B. Notification.

C. Construction parking controls.

D. Flag persons.

E. Flares and lights.

F. Haul routes.

G. Traffic signs and signals.

H. Other Requirements I. Removal.

1.03 RELATED SECTIONS

A. Section 01 11 13 - Summary of Work B. Section 01 31 00 - Coordination and Meetings: Coordination and Project conditions.

C. Section 01 50 00: Construction Facilities and Temporary Controls: Barriers, access roads and parking.

PART 2 - PRODUCTS

2.01 SIGNS, SIGNALS, AND DEVICES

A. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by the authority having jurisdiction.

B. Traffic Control Signals: As approved by the authority having jurisdiction.

C. Traffic Cones and Drums, Flares and Lights: As approved by the authority having jurisdiction.

D. Flagperson Equipment: As required by the authority having jurisdiction.

PART 3 - EXECUTION

3.01 TRAFFIC CONTROL PLAN

A. Contractor shall implement any Traffic Control Plan requirements imposed by the Road Opening Permit issued by the Borough.

3.02 NOTIFICATIONS

A. Contractor shall provide advance notification to any parties so noted in the local municipal Road Opening Permit in accordance with the required time schedule. In any event, the local

01 55 26-2 municipal Police Department shall be notified at least ten (10) days prior to the date Contractor desires to restrict traffic in or along any highways or roads.

B. The Contractor shall notify the following parties at least twenty-four (24) hours in advance of any work within the roadway:

1. Local Municipal Police

2. Local Fire Company

3. Local School District

4. Local Ambulance Service

5. All affected residents

C. Contractor shall obtain advance approval from the authority having jurisdiction (PennDOT, local municipality) should it be necessary to restrict traffic in or along any highways or roads, including temporary closure of a road.

D. At least one lane must be open for traffic during non-working periods and Contractor must be prepared to allow passage of emergency vehicles at any time.

3.03 CONSTRUCTION PARKING CONTROLS

A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Owner's operations.

B. Monitor parking of construction personnel's vehicles. Maintain vehicular access to and through parking areas.

C. Prevent parking on or adjacent to access roads or in non- designated areas.

3.04 FLAG PERSONS

A. Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes.

3.05 HAUL ROUTES

A. Consult with the Owner for routes to be used for haul routes and site access.

B. Confine construction traffic to designated routes.

3.06 TRAFFIC SIGNS AND SIGNALS

A. Install and operate traffic controls to direct and maintain orderly flow of traffic in areas under Contractor’s control, and areas affected by Contractor’s operations.

B. Relocate as Work progresses, to maintain effective traffic control.

3.07 OTHER REQUIREMENTS

A. Maintain access at all times during non-working periods and to the maximum extent feasible during working periods to all driveways and entrances of adjacent properties. In this regard, use and maintenance of steel plates or other decking across the trench may be necessary to reduce to a minimum interference with access to the adjacent properties.

B. Provide safe decking over open trenches in or along highways or roads during non-work periods by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all traffic including truck loads.

3.08 REMOVAL

01 55 26-3

A. Remove equipment and devices when all work, including repaving, has been completed.

B. Repair damage caused by installation.

C. Remove post settings to a depth of 2 feet.

END OF SECTION