42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf

PDF 52 KB Posted

Attached to
Bristol Borough 2025 CDBG Curb Ramp Program
Solicitation number
US.193830
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

View the file

Other files

File Type Posted
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
25-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
61-Addendum 1.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
58-Location Map.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
45-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL AND EQUIPMENT

01 60 00-1

SECTION 01 60 00

MATERIAL AND EQUIPMENT

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Products.

2. Transportation and handling.

3. Storage and protection.

4. Product options.

5. Substitutions.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 21 13: Instructions to Bidders.

2. Section 01 40 00: Quality Control.

1.03 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.04 TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to assure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

1.05 STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers’ instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

01 60 00-2

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of Products to permit access for inspection. Periodically inspect to assure Products are undamaged and are maintained under acceptable condition.

1.06 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following Article.

1.07 SUBSTITUTIONS

A. Instructions to Bidders specify time restrictions for submitting requests for Substitutions during the bidding period to requirements specified in this section.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

5. Will reimburse Owner and Owner’s Engineer for review or redesign services associated with re-approval by authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one (1) proposed Substitution.

2. Submit Shop Drawings, Product data, and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.

3. Owner’s Engineer will notify Contractor in writing of decision to accept or reject request.

G. For each equipment item in which the manufacturer was listed on the Bid Form, Owner’s Engineer reserves the right to require Contractor to use the equipment item of the listed manufacturer.

01 60 00-3

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

File details come from the government source that posted it. Updated .