47-Sec 01 33 00 - SUBMITTALS.pdf

PDF 60 KB Posted

Attached to
Bristol Borough 2025 CDBG Curb Ramp Program
Solicitation number
US.193830
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

View the file

Other files

File Type Posted
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
25-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
61-Addendum 1.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
58-Location Map.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
45-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTALS

01 33 00-1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Submittal procedures.

2. Construction progress schedules.

3. Product data.

4. Shop Drawings.

5. Samples.

6. Design data.

7. Test reports.

8. Certificates.

9. Manufacturer’s instructions.

10. Manufacturer’s field reports.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 40 00: Quality Control: Manufacturers' field services.

2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.

1.03 REFERENCES

A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.

1.04 SUBMITTAL PROCEDURES

A. Transmit each submittal to Owner’s Engineer. Prior to submission to Owner’s Engineer, the Contractor’s Design Engineer shall review and approve each submittal.

B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.

C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.

D. Apply Contractor and Contractor’s Design Engineer stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project and to coordinate submission of related items.

01 33 00-2

F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.

G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Design Engineer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

K. Submittals not requested will not be recognized or processed.

1.05 CONSTRUCTION PROGRESS SCHEDULES

A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Owner’s Engineer.

B. Revise and resubmit as required.

C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Owner’s Engineer if no preconstruction conference is to be held.

D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.

E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.

G. Indicate estimated percentage of completion for each item of Work at each submission.

H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.

1.06 PRODUCT DATA

A. Product Data For Review:

1. Submitted to Owner’s Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Product Data For Information:

1. Submitted for the Owner’s Engineer’s knowledge as contract administrator or for

OWNER.

01 33 00-3

C. Product Data For Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Owner’s Engineer.

E. Mark each copy to identify applicable Products, models, options, and other data.

Supplement manufacturers’ standard data to provide information specific to this Project.

F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

1.07 SHOP DRAWINGS

A. Shop Drawings For Review:

1. Submitted to Owner’s Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Shop Drawings For Information:

1. Submitted for Owner’s Engineer’s knowledge as contract administrator or for Owner.

C. Shop Drawings For Project Closeout:

1. Submitted for Owner’s benefit during and after project completion.

D. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

E. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Owner’s Engineer.

1.08 SAMPLES

A. Samples For Review:

1. Submitted to Owner’s Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

2. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

B. Samples For Information:

1. Submitted for Owner’s Engineer’s knowledge as contract administrator or for Owner.

C. Samples For Selection:

1. Submitted to Owner’s Engineer for aesthetic, color, or finish selection.

01 33 00-4

2. Submit samples of finishes in colors, textures, and patterns for Owner’s Engineer’s selection.

3. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.

D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

E. Include identification on each sample, with full Project information.

F. Submit the number of samples specified in individual specification sections; one of which will be retained by Owner’s Engineer.

G. Reviewed samples which may be used in the Work are indicated in individual specification sections.

H. Samples will not be used for testing purposes unless specifically stated in the specification section.

1.09 DESIGN DATA

A. Submit for Owner’s Engineer’s knowledge as contract administrator or for Owner.

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.10 TEST REPORTS

A. Submit for Owner’s Engineer’s knowledge as contract administrator or for Owner.

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

1.11 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Owner’s Engineer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Owner’s Engineer.

1.12 MANUFACTURER’S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Owner’s Engineer for delivery to Owner in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.

01 33 00-5

1.13 MANUFACTURER’S FIELD REPORTS

A. Submit reports for Owner’s Engineer’s benefit as contract administrator or for Owner.

B. Submit report in duplicate within 30 days of observation to Owner’s Engineer for information.

C. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

PART 1 GENERAL

File details come from the government source that posted it. Updated .