50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf
PDF 45 KB Posted
- Attached to
- Bristol Borough 2025 CDBG Curb Ramp Program
- Solicitation number
- US.193830
- Issued by
- Bucks County, Brodheadsville CDP, Pennsylvania
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NARRATIVE CONSTRUCTION SCHEDULE
01 32 16-1
SECTION 01 32 16
NARRATIVE CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work Of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date for the design phase and construction phase. The schedule for the construction phase shall identify the order of completing each intersection. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Owner’s Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
Activity description & location;
Duration of activity, in working days; and Start and finish calendar dates of activities.
D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION