4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf

PDF 56 KB Posted

Attached to
Bristol Borough 2025 CDBG Curb Ramp Program
Solicitation number
US.193830
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

View the file

Other files

File Type Posted
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
25-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
61-Addendum 1.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
58-Location Map.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
45-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

POLYMER MODIFIED ASPHALT JOINT AND CRACK SEALING

32 01 17.61-1

SECTION 32 01 17.61

POLYMER MODIFIED ASPHALT JOINT AND CRACK SEALING

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Asphaltic Joint and Crack Sealing

1.02 DESCRIPTION OF WORK

A. This work is the cleaning and sealing of pavement surface joints associated with the removal and replacement of concrete curb and curb ramps with polymer modified asphalt.

PART 2 PRODUCTS

2.01 ASPHALT CEMENT PG 64-22

A. Obtain material meeting the requirements of PennDOT Bulletin 25 from a producer listed in Bulletin 15.

1. Quality Control Section 01 40 00

2. Certification

a. General

1) When a bituminous material tank is filled, submit a copy of the required test results to the MTD for verification of compliance with Department specifications.

2) Specify the type of material, tank number, and company lot number of the certificate for cross-reference to the bill of lading.

3) Have a responsible company official sign the certificate.

4) Obtain a verification sample from each batch. A batch is a tank completely filled, partially filled, or refilled with a blend of residual and new material.

5) Test one-half (1/2) sample and forward the results to the MTD. Forward the remaining one-half (1/2) sample to the MTD for testing. The MTD will evaluate quality control on the basis of three (3) consecutive verification samples.

b. Levels of Certification

1) Use the same levels of certification as specified in PennDOT Publication 408, Section 701.1(b)2, except substitute the word “batch” for the word “silo.”

c. Handling and Transportation, Section 01 60 00

1) Furnish the vendor’s bill of lading for each shipment (one copy retained by the vendor and one copy included with the shipment to the project). Use a form acceptable to the MTD, containing the following information:

a) Statement that material has been testing and meets Department specifications.

b) Class of Material

c) Tank Number

d) Company Batch Number

e) Date of Shipment

f) Producer’s Name and Location

g) Name and Location of Consignee, (Bituminous Concrete Plant or

Maintenance District)

h) Mix or Application Temperatures, Minimum and Maximum

POLYMER MODIFIED ASPHALT JOINT AND CRACK SEALING

32 01 17.61-2

i) Viscosity at 140F

j) Penetration at 77F

k) Trailer Number

l) Specific Gravity of Asphalt Cement at 77F

m) Statement that the material is compatible with job aggregate E-4, E-5, E-10, E-11, E-12, MC-400, and MC-800

n) Percent Bitumen Residue by Weight (for liquid bituminous materials only)

o) Quality of Material

p) Statement that the shipment container was determined to be reasonably free of contamination immediately prior to loading

PART 3 EXECUTION

3.01 GENERAL

A. Provide a mixture of asphalt cement and reclaimed granulated rubber, combined to the specified proportions, or furnish a premixed composition as specified in Section 469.2(c) or (d).

3.02 MIXING PROCEDURES

A. Combine the PG 64-22 and reclaimed granulated rubber to obtain a mixture having proportions of two (2 lbs) pounds of RGR per gallon of asphalt cement. Blend the PG 64-22 and reclaimed granulated rubber in an oil-jacketed double wall kettle (indirect hating) equipped with agitator and two (2") inch hot asphalt pump. Provide separate thermometers for oil bath. Heat and agitate the mixture with the temperature range of 350F - 380F for thirty

(30) minutes. Do not allow the operating temperature in the kettle to exceed 400F.

B. For premixed material, as specified in Section 469.2(c) or (d), obtain the safe heating temperature range and recommended pouring temperature from the manufacturer’s shipping container. Place the material within this temperature range, and as close as possible to the recommended pouring temperature. Maintain a safe heating temperature. Do not maintain any single batch of material at the pouring temperature for more than four (4) hours. Reheat only in accordance with manufacturer’s recommendations.

3.03 SURFACE PREPARATION

A. Apply sealer only after joints and adjacent pavement surfaces are clean, dry, and free of any loose material and debris. Clean the pavement for four (4") to six (6") inches on either side of the joint. Air blast joints immediately prior to sealing. Use a compressed air stream of at least 100 psi measured at the source, or use a hot compressed air lance for cleaning and drying damp cracks in the bituminous pavements. Care should be taken to ensure that damage to the surrounding pavement area from overheating does not occur. Seal joints (1/8) to one (1") inch wide with polymer modified asphalt.

3.04 SEALING

A. Apply polymer modified asphalt to prepared joints, level with the pavement surface, using a wand followed by a standard “V” shaped asphalt squeegee. Leave no more than 1/8 inch buildup. Do not place sealer when the air temperature is below 40F or above 90F, unless otherwise permitted by the Engineer if the hot compressed air lance used can sufficiently warm the crack to ensure adhesion between the pavement and the sealer. Do not place bituminous overlay within seventy-two (72) hours of sealing unless permitted by Engineer.

END OF SECTION