57-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf

PDF 52 KB Posted

Attached to
Bristol Borough 2025 CDBG Curb Ramp Program
Solicitation number
US.193830
Issued by
Bucks County, Brodheadsville CDP, Pennsylvania

View the file

Other files

File Type Posted
13-Doc 00 73 00 1 - Appendix A cover sht.pdf PDF
49-Doc 00 73 00 5 - Appendix C cover sht.pdf PDF
63-Addendum 1 Doc 00 73 00 2 - Appendix A - Davis Bacon Wage Rates.pdf PDF
27-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
25-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
55-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
17-Sec 32 17 26 - ADA DETECTABLE WARNING SURFACE.pdf PDF
12-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
42-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
50-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
7-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
53-Sec 02 41 16 - DEMOLITION.pdf PDF
10-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
18-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
36-Doc 00 73 00 10 Part 2 Federal Labor Standard Provisions.pdf PDF
40-Doc 00 73 00 3 - Appendix B cover sht.pdf PDF
37-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
22-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
3-Doc 00 43 13 - BID BOND.pdf PDF
26-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
46-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
8-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
20-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
32-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
4-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
61-Addendum 1.pdf PDF
15-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
34-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
51-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
64-2025-08-05 2025 CDBG Curb Ramp Program Preliminary Bid Tab.pdf PDF
9-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
14-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
41-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
24-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
2-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
44-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
21-Doc 00 73 00 2 - Appendix - Davis Bacon Wage Rates.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
47-Sec 01 33 00 - SUBMITTALS.pdf PDF
39-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
6-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
58-Location Map.pdf PDF
62-Addendum 1 Doc 00 45 13.1 - CONTRACTOR RESPONSIBILITY CERTIFICATION (REV).pdf PDF
29-Doc 00 73 00 7 - Appendix D cover sht.pdf PDF
60-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
16-Doc 00 01 10-TOC.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
45-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-1

SECTION 01 50 00

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 GENERAL

1.01 GENERAL

A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).

1.02 SECTION INCLUDES

A. Temporary Utilities: Electricity, lighting, heat, ventilation, communications service, water and sanitary facilities.

B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.

C. Construction Facilities: Access roads, parking, progress cleaning, project signage, and temporary buildings.

1.03 RELATED SECTIONS

A. Section 01 57 13: Soil Erosion and Sediment Control.

B. Section 01 55 26: Traffic Regulation.

C. Section 01 70 00: Contract Closeout: Final cleaning.

1.04 TEMPORARY ELECTRICITY

A. Cost: By Contractor; provide and pay for power service required from utility source.

1.05 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures.

Existing facility use is not permitted. Provide at time of project mobilization.

B. At end of construction, return facilities to same or better condition than originally found.

1.06 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide protection for plants designated to remain. Replace damaged plants.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.07 FENCING

A. Construction: Contractor's option.

B. Provide 6-foot-high fence around construction site; equip with vehicular and pedestrian gates with locks.

1.08 WATER CONTROL

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-2

B. Protect site from puddling or running water.

1.09 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.10 SECURITY

A. Provide security and facilities to protect Work, and Owner's operations from unauthorized entry, vandalism, or theft.

1.11 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Collect and remove waste materials, debris, and rubbish from site daily and dispose off-site.

C. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.12 PROJECT IDENTIFICATION

A. No other signs are allowed without Owner permission except those required by law.

1.13 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Clean and repair damage caused by installation or use of temporary work.

B. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.14 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Owner) to prevent air-borne dust from dispersing into atmosphere.

C. Dust control measures shall be employed when required in the opinion of the Owner’s Engineer at no additional cost to Owner.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION