B2.07.08_DRAFT-Sec_J_Attachment_08_NTP_Checklist_061424.pdf

PDF 582 KB Posted

Attached to
CRMF SRF Cleanroom and UPW Construction Sources Sought Notification
Solicitation number
SLAC_DRAFT_RFP_369005_CRMF_Cleanroom_Construction
Issued by

About this file

This is a Notice to Proceed Submittals checklist for SLAC National Accelerator Laboratory subcontractors. The document establishes mandatory requirements that subcontractors must submit before receiving authorization to proceed with work on a project.

The checklist requires subcontractors to submit Performance and Payment Bonds with penal sums equal to the Fixed-Fee-Price award for subcontracts valued at $35,000 and over. Approved insurance certificates must be provided for all subcontracts. For subcontracts of $25,000 and over involving design work by the subcontractor, Professional Errors and Omissions Insurance of at least $1,000,000 per claim is required. Subcontracts of $50,000 and over must include Builder's All Risk Insurance covering physical damage to work performed, with coverage equal to the full value of the work at the time of loss or damage, in a form acceptable to the University. Additional submittal requirements include the Statement and Acknowledgment Standard Form (SF1413) for all known sub-subcontractors, copies of the subcontractor's licenses and permits along with those of any known sub-subcontractors, Issue for Construction Set (IFC) Drawings and Specifications, and a project schedule in the format specified by the SLAC Project Manager. The document serves as a template with blank fields for Project name, Purchase Order number, Subcontractor name, SLAC Project Manager, and SLAC Construction Manager information.

View the file

Other files

File Type Posted
B2.03.03_DRAFT-RFP_IFC_Drawings_SLAC_CRMF_Cleanroom.pdf PDF
B2.03.02_DRAFT-RFP_IFC_Specs_SLAC_CRMF_Cleanroom.pdf PDF
B2.07.12_DRAFT-Sec_J_Attachment_12_SBSP_100726.pdf PDF
B2.07.02_DRAFT-Sec_J_Attachment_02_Work_Classification.pdf PDF
B2.07.10_DRAFT-Sec_J_Attachment_10_LCPTracker_AP_091426.pdf PDF
B2.09.00_DRAFT-RFP_Sec_L_Instructions_to_Offerors_RFP_369905.docx DOCX document
B2.07.00_DRAFT-RFP_Section_J_(List of Attachments).docx DOCX document
B2.06.00_DRAFT-RFP_Section_H_(Special_TsCs).docx DOCX document
B2.10.00_DRAFT-RFP_Sec_M_Evaluation_Criteria_RFP_369905.docx DOCX document
B2.07.01_DRAFT-Sec_J_Attachment_01_CWRR_WD.pdf PDF
B2.07.04_DRAFT-Sec_J_Attachment_04_SF1413.pdf PDF
B2.07.05_DRAFT-Sec_J_Attachment_05_SQF.pdf PDF
B2.05.01_Fixed_Price_Construction_March_2024.pdf PDF
B2.07.09_DRAFT-Sec_J_Attachment_09_LCPTracker_NP_091426.pdf PDF
B2.07.07_DRAFT-Sec_J_Attachment_07_Final_Release.docx DOCX document
B2.07.06_DRAFT-Sec_J_Attachment_06_Final_Inspection_Report.docx DOCX document
B2.05.00_DRAFT-RFP_Section_G_(General_TsCs).docx DOCX document
B2.03.00_DRAFT-RFP_Section_C_(Specifications_SOW).docx DOCX document
B2.08.01_DRAFT_RFP_Reps_and_Certs_Supplement.pdf PDF
B2.09.02_DRAFT-Sec_L_Attachment_B_CRMF_Cleanroom_Bid_Breakdown_Draft.xlsx XLSX spreadsheet
B2.03.01_DRAFT-RFP_SOW_CRMF-1.4-SW-224.docx DOCX document
B2.07.11_DRAFT-Sec_J_Attachment_11_LCPTracker_NC_091426.pdf PDF
B2.08.00_DRAFT-RFP_Section_K_(Rep and Certs).docx DOCX document
B2.02.00_DRAFT_RFP_Section_B_(Supplies or Services and Price_Costs).docx DOCX document
B2.01.00_DRAFT_RFP_Section_A_(Subcontract_Form).docx DOCX document
B2.03.04_DRAFT-RFP_Acceptance_Criteria_List_CRMF-1.4-PP-319.docx DOCX document
B2.07.03_DRAFT-Sec_J_Attachment_03_IIPP_Form.pdf PDF
B2.09.3_DRAFT-RFP_Sec_L-Attachment_C_Past_Performance_Questionnaire_Draft.docx DOCX document
B2.04.00_DRAFT-RFP_Section_F_(Deliveries Performance).docx DOCX document
B2.09.01_DRAFT-Sec_L_Attachment_A_SLAC_Question-Clarifications_&_Answer_Log_(RFI).docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLY CHAIN MANAGEMENT

NOTICE TO PROCEED SUBMITTALS

Project:

PO#:

Subcontractor:

SLAC PM:

SLAC CM:

NOTICE TO PROCEED CHECKLIST

Performance & Payment Bonds. Penal sum of Bonds must be equal to the FFP Award for Subcontracts of $35,000 and over.

Approved insurance certificates

Subcontracts of $25,000 and over requiring design by Subcontractor: Professional Errors and Omissions Insurance in the amount not less than $1,000,000 per claim.

Subcontracts of $50,000 and over: Subcontractor shall purchase and maintain at its cost Builder’s All Risk Insurance covering physical damage to the work being performed under this Subcontract in a form acceptable to the University and to the full value of the work at the time of loss or damage.

"Statement and Acknowledgment” Standard Form (SF1413) for all known Sub-Subcontractors.

A copy of the Subcontractor’s licenses and permits, and copies of all known Sub-Subcontractors licenses or permits, if needed, in performance of the Subcontract.

Issue for Construction Set (IFC) Drawings and Specifications.

Project schedule in the specified format as required by the SLAC PM

Notes:

June 14, 2024

Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Text19:
Text20:
Text21:
Text22:
Text23:
Text24:

File details come from the government source that posted it. Updated .