This is a Section F (Deliveries or Performance Period of Performance) document from a Draft Request for Proposal for construction services at SLAC National Accelerator Laboratory. The document outlines the contract line items (CLINs) and project timelines for a cleanroom and ultra-pure water system installation project at the Cryomodule Repair and Maintenance Facility (CRMF) building located in Menlo Park, California.
The base scope (CLIN 1) involves installation of a new ISO Class 4 cleanroom inside the existing CRMF building, with a tentative Notice of Award date of March 2027 and a project completion date of June 2028. Option 01 (CLIN 2) covers installation of a new ultra-pure water (UPW) system adjacent to the cleanroom within the same facility, with a two-month completion period from Notice to Proceed should SLAC elect to exercise this option. The project is directly funded by the Department of Energy's Office of Science. The contractor will be required to fabricate the cleanroom according to SLAC-approved design specifications and building inspection office-stamped prints provided by the government. This is a firm fixed price contract structure for general contractor services, with SLAC retaining discretion on whether to exercise the optional UPW system scope.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Supply Chain Management
Section F – Deliveries or Performance
Period of Performance
| CLIN |
| SUPPLIES/SERVICES |
| FROM |
| TO |
| 1 |
| Base Scope: |
Installation of a new cleanroom (ISO4) inside an existing Cryomodule Repair and Maintenance Facility (CRMF) Building.
Award Date (Tentative Date: March 2027)
Notice of Award
(Tentative Award Date: March 2027)
TBD
Tentative Project Completion Date: June 2028)
| 2 |
| Option 01 Scope: |
Installation of a new Ultra-Pure Water (UPW) system next to the cleanroom inside the CRMF Building.
| Notice of Award, if exercised |
| TBD |
2 months from NTP
Option Line Item: SLAC may or may not purchase Option 01 (CLIN 2).
SLAC NATIONAL ACCELERATOR LABORATORY • 2575 SAND HILL ROAD • MENLO PARK • CAlifornia • 94025 • USA Operated by Stanford University for the U.S. Department of Energy
SECTION F (REV. 06/04/12) SLAC-SCM-GEN-032 PAGE 1 OF 1
image1.jpeg
File details come from the government source that posted it. Updated .