B08_Section_J_Attachment_01_KNRI257081_Specifications_Div01.pdf
PDF 25 MB Posted
- Solicitation number
- 140P2026R0086
About this file
This is a Specifications document (Division 01) for the Knife River Indian Village National Historic Site Elbee Bend Bank Stabilization project under solicitation number 140P2026R0086. The document establishes general contracting requirements and specifications for construction work related to bank stabilization activities at the historic site, managed by the National Park Service under the Department of the Interior.
The specifications outline standard construction practices, quality assurance requirements, and compliance mandates for the project. Key requirements include adherence to applicable federal, state, and local regulations; proper documentation and record-keeping throughout construction; coordination with National Park Service personnel; and environmental protection measures consistent with site preservation objectives. The document addresses contractor responsibilities for site management, safety compliance, material testing and verification, and quality control procedures. Contractors must demonstrate capability to perform specialized work in a sensitive historic site environment while maintaining archaeological and cultural resource protections. The specifications establish baseline technical and administrative requirements that contractors must meet to be considered responsive to this solicitation, with additional detailed specifications likely contained in subsequent divisions of the specification set.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KNIFE RIVER INDIAN VILLAGES
NATIONAL HISTORIC SITE
STANTON, ND
KNIFE RIVER ELBEE BEND BANK STABILIZATION
KNRI 257081
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
April 8, 2025
468 184187
TABLE OF CONTENTS
DIVISION 01: GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items Supplement: Contract Price Schedule 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 32 33 Photo Documentation 01 33 23 Submittal Procedures Supplement: Submittal List 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention (SWPP) 01 67 00 Product Requirements 01 71 13 Mobilization and Demobilization 01 71 23 Construction Surveying and Staking 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 90 00 Acceptance of Work
Division 01 Supplements: ND Game and Fish Department ANS Inspection Checklist Project Waste Management Plan Worksheet Closeout and Operation & Maintenance Requirements January 13, 2025 Archeological Protection Plan
DIVISION 31: EARTHWORK
31 11 00 Clearing and Grubbing 31 14 13 Topsoil Stripping and Stockpiling 31 22 16.15 Temporary and Permanent Access Roads and River Crossing 31 23 00 Earthwork (Excavation and Fill) 31 23 19.01 Dewatering 31 25 00 Erosion and Sedimentation Controls 31 37 00 Riprap and Bedding 31 50 00 Excavation Support and Protection
DIVISION 32: EXTERIOR IMPROVEMENTS
32 15 00 Aggregate Surfacing 32 91 13 Topsoil and Wetland Topsoil 32 92 19 Seeding
Division 32 Supplement: Table 1. Ecological Screening Values for Soil
APPENDIX
A. Geological Investigation Field Report for Knife River - Elbee Bend Bank Stabilization
Project, Knife River Indian Villages National Historic Site, Stanton, ND, January 6, 2022, prepared by U.S. Army Corps of Engineers Omaha District
B. Geotechnical Recommendations Report for Knife River - Elbee Bend Bank Stabilization Project, Knife River Indian Villages National Historic Site, Stanton, ND, October 22, 2024 prepared by Stantec Consulting Services Inc.
C. Permit Conditions affecting the construction process for Knife River - Elbee Bend Bank Stabilization Project, Knife River Indian Villages National Historic Site, Stanton, ND.
End of Table of Contents
DIVISION 01: GENERAL REQUIREMENTS
KNRI 257081 01 11 00 - 1
112723 SUMMARY OF WORK
Knife River Indian Villages National Historic Site – PMIS 257081
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Under Other Contracts
3. Contractor Use of Site
4. Public Use of Site
5. Conduct of Operations
6. Work Restrictions
7. Special Construction Requirements
8. Soils Investigation Report
9. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Knife River Indian Villages National Historic Site, Elbee Bend, Stanton, ND. The project work occurs one and a half miles north of Stanton, ND on County Road 37 in the Knife River Elbee Bend.
The location also be described as one mile north of the Visitor Center, east of County Road 37, north of the Gravel Parking Lot (North of Awatixa Village – Sakakawea Site) and south of the NPS Equipment Boneyard.
B. The Work consists of:
1. Site preparation (clearing and grubbing, topsoil salvage), erosion control, temporary river crossing, excavation, installation of rock, grading, material blending, material import, stockpiling of excess material, compaction, safety, quality control, seeding and restoration.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate Construction Contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this Contract with work performed under separate contracts.
B. Preceding Work: Tree removals. Selected trees were cut by NPS Staff and stumps will not need to be removed by Contractor.
KNRI 257081 01 11 00 - 2
1.4 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to
Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling
Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Materials: (NOT USED)
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to the existing Gravel Parking Lot (North of Awatixa Village – Sakakawea Site), and additional staging locations shown on the Drawings or as directed by the Contracting Officer. Protection of existing surface is the responsibility of the Contractor. Any damage to the existing gravel parking lot or staging areas shall be repaired and the site restored to pre-project conditions at no cost.
C. Parking: Confine parking to Gravel Parking Lot (North of Awatixa Village – Sakakawea Site).
D. Stockpiling: Confine stockpiling to locations shown on drawings, and additional staging locations mutually acceptable to the Contractor and the Contracting Officer.
E. Protection of Archeological Resources:
1. The project is located in a significant and multi-component archeological site.
2. The Contractor shall refer to Section 01 35 13.22 Archeological Protection and the 2025
Archeological Protection Plan which is included in the Contract Documents.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
KNRI 257081 01 11 00 - 3
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials. The private drives along County Road 37 north of the Visitor Center must always remain open.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
H. Construction Camp: Establishment of a camp within park will not be permitted.
I. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
J. Bridge Restrictions: Contractor is responsible to comply with any applicable bridge restrictions.
1.6 PUBLIC USE OF SITE
A. The Gravel Parking Lot (North of Awatixa Village – Sakakawea Site) will be closed to the public during construction.
1.7 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m.
to 6 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend and Federal Holiday Hours: No work shall be performed on the weekends or federal holidays without Contracting Officer’s prior approval including the Fridays before Easter, Memorial Day, Labor Day, and Thursday July 3, 2025.
2. Early Morning Hours: Subject to Contracting Officer’s approval.
KNRI 257081 01 11 00 - 4
B. The North Dakota Game and Fish Department requires that any in-water, or near-water, work avoids the April 15 — June 1 time frame to allow for undisturbed seasonal fish movement.
C. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1. Smoking will be permitted in designated areas as approved by the Contracting Officer.
2. Smoking is not permitted while working or operating equipment.
3. Contractor shall provide a wildlife proof disposal container for cigarette butts. Cigarette butts shall not be disposed of on the ground.
4. Smoking shall not be permitted when fire danger is high as determined by Park personnel and regulation.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Provide and maintain portable toilets and other temporary sanitation facilities that are bear resistant.
B. Install tree protection and temporary fencing to protect trees impacted by Construction, but not designated for removal by the Contracting Officer. Tree protection shall be completed in accordance with the Drawings.
1.10 SOILS INVESTIGATION REPORT
A. The report Geological Investigation Field Report for Knife River - Elbee Bend Bank Stabilization Project, Knife River Indian Villages National Historic Site, Stanton, ND, January 6, 2022, prepared by U.S. Army Corps of Engineers Omaha District is available with this package.
B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.
1.11 ADDITIONAL REPORTS
A. The report Geotechnical Recommendations Report for Knife River - Elbee Bend Bank Stabilization Project, Knife River Indian Villages National Historic Site, Stanton, ND, October 22, 2024 prepared by Stantec Consulting Services Inc. is available with this package.
B. In case of conflict between report and drawings or specifications, drawings and specifications govern.
KNRI 257081 01 11 00 - 5
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01 11 00
KNRI 257081 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
Knife River Indian Villages National Historic Site – PMIS 257081
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
KNRI 257081 01 26 01 - 2
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General
Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
KNRI 257081 01 26 01 - 3
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General
Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project. Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
KNRI 257081 01 26 01 - 4
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the
Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a
Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
KNRI 257081 01 26 01 - 5
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense
Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenanc (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army
Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10%
Profit………......………9.5%
KNRI 257081 01 26 01 - 6
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS (NOT USED)
END OF SECTION 01 26 01
KNRI 257081 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
Knife River Indian Villages National Historic Site – PMIS 257081
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item. Provide all labor, materials, tools, equipment, services, and incidentals as necessary to perform the work as described in this section and in accordance with the Contract Documents and Drawings and to the satisfaction of NPS.
C. Conformance with the requirements of this section shall in no way relieve the Contractor from his/her responsibilities for compliance with laws, regulations, orders, and decrees, or responsibilities for public safety and convenience applicable to the Project, and the provisions of the Contract Documents.
D. Any estimated quantities of major elements of the work shown in the Drawings are approximate.
It is the Contractors responsibility to visit the project site prior to bid to identify existing conditions that will affect the work and determine the quantities of material required to complete the work.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall perform all work necessary to construct and deliver to NPS a complete Project conforming to the Contract Documents. Details not shown or provided in the Drawings and Specifications, but required for a complete and operational Project, shall be included in the Contract Price as approved by NPS.
3.2 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 0001 (CLIN 0001) Mobilization and Demobilization – CLIN 0001 shall include but not be limited to Mobilization and Demobilization, Clearing and Grubbing, Construction Surveying and Staking, As-built Survey.
1. This item consists of work pertaining to the Mobilization and Demobilization, to and from the site, as defined in the contract documents as well as clearing and grubbing, construction surveying and staking and as-built surveying.
2. Measurement for payment will be determined and paid according to the following schedule:
KNRI 257081 01 27 00 - 2
a. 50% of bid amount when at least 10% of the remainder of the Contract amount is complete.
b. 25% of bid amount when at least 50% of the remainder of the Contract amount is complete.
c. 25% of bid amount when at least 75% of revegetation or restoration (whichever occurs later) pay item is paid.
3. Payment will be made at the contract lump sum price.
4. The total amount bid shall not exceed 10% of the total bid amount.
B. Contract Line Item Number 0002 (CLIN 0002) River Embankment Stabilization – CLIN 0002 Shall include but not be limited to Silt Fence, Silt Curtain, Oil Boom, Temporary Rock Construction Entrances, Temporary Seeding, Temporary Tree Protection, Unclassified Excavation, Embankment Fill, Excess Fill Stored Onsite, Void-Filled Riprap and Bedding.
1. This item consists of all work pertaining to the items noted above and as shown in the contract documents.
2. Measurement for payment will be determined based on percent of construction complete.
3. Payment will be made at the contract lump sum price.
4. This price is full compensation for furnishing and placing materials required, including embankment and surfacing; excavation and stockpiling of excavated material; watering and compacting; furnishing, installing, and removing drainages structures; removal of access road and temporary river crossing; disposal of materials; and equipment, labor, tools, and incidentals
C. Contract Line Item Number 0003 (CLIN 0003) Site Restoration – CLIN 0003 shall include but not be limited to Permanent Access Road, Seeding and Restoration.
1. This item consists of work pertaining to installation of the Permanent Site Access Road, seeding and restoration as shown in the contract documents. Removal of the Temporary Site Access road and Temporary River Crossing shall also be included in this bid item.
2. Measurement for payment will be determined based on percent of construction complete.
3. Payment will be made at the contract lump sum price.
4. This price is full compensation for furnishing and placing materials required, including embankment and surfacing; excavation and hauling of excavated material; watering and compacting; furnishing, installing, and removing drainages structures; disposal of materials; and equipment, labor, tools, and incidentals.
D. Contract Line Item Number 0004 (CLIN 0004) BID ALTERNATE ITEM - TOPSOIL AND
EROSION CONTROL
1. This item consists of work pertaining to importing topsoil, movement and placement of imported and onsite topsoil, erosion control blanket and matting and mulching as shown in the Contract Documents.
2. Measurement for payment will be determined based on percent of construction complete.
3. Payment will be made at the contract lump sum price.
4. This price is full compensation for furnishing and placing materials required, including embankment and surfacing; excavation and hauling of excavated material; watering and compacting; disposal of materials; and equipment, labor, tools, and incidentals.
E. Contract Line Item Number 0005 (CLIN 0005) BID ALTERNATE ITEM - TEMPORARY
ACCESS ROAD AND TEMPORARY RIVER CROSSING
KNRI 257081 01 27 00 - 3
1. This item consists of work pertaining to installation of the Temporary Site Access Road, Temporary River Crossing, and culverts associated with the Temporary River Crossing as shown in the Contract Documents.
2. Measurement for payment will be determined based on percent of construction complete.
3. Payment will be made at the contract lump sum price.
4. This price is full compensation for furnishing and placing materials required, including embankment and surfacing; excavation and hauling of excavated material; watering and compacting; furnishing and installing drainage structures; disposal of materials; and equipment, labor, tools, and incidentals.
END OF SECTION 01 27 00
Price Schedule Supplement to Section 01 27 00 - Definition of Contract Line Items
Contract Line Item Contract Line Item Title1 Quanitity Unit of
Measurement Unit Price Subtotal
CLIN 0001 Mobilization and Demobilization 1 Lump Sum (LS)
CLIN 0002 River Embankment Stabilization 1 Lump Sum (LS)
CLIN 0003 Site Restoration 1 Lump Sum (LS)
CLIN 0004
Bid Alternate - Topsoil and Erosion Control 1 Lump Sum (LS)
CLIN 0005
Bid Alternate - Temporary Access Road and Temporary River Crossing 1 Lump Sum (LS)
1Refer to Section 01 27 00 for Complete Descriptions
Total Written Amount of Base Bid
Total Written Amount of Base Bid with Bid Alternates
Knife River Indian Villages National Historic Site - PMIS 257081
Total Base Bid $ (CLIN 0001-0003)
Total Base Bid with Bid Alternates $ (CLIN 0001-0005)
KNRI 257081 01 31 00 - 1
112723 PROJECT MANAGEMENT AND COORDINATION
Knife River Indian Villages National Historic Site – PMIS 257081
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction: An organization, agency, office, or individual that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document. Responsibility for enforcing the requirements of a code or standard, or for approving equipment, materials, an installation, or a procedure.
B. Construction Permits – Contractor Provided: Permits that will be applied for and obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service. Examples of typical Contractor Provided Permits are: National Pollutant Discharge Elimination System (NPDES) Construction Permit (ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.
C. Government Furnished (GF) Permits: Obtained by National Park Service (NPS), usually through the Architect/Engineer (A/E) or a consultant, during the design process (Predesign (PD) through Construction Documents (CD)) and are usually concerned with impacts to resources protected by federal law. However, GF permits can include other permits that are obtained for the convenience
KNRI 257081 01 31 00 - 2
of the Government during design. GF permits are "furnished" to the Contractor in the Request for Proposal (RFP) and as part of the final contract documents. The Contractor must comply with GF permit provisions. Examples of typical GF permits: Clean Water Act (CWA) 404 dredge and fill permit, CWA Water Quality Certification (often state administered), Highway Right-of-Way Permit, etc.
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Construction Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other Construction Contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Construction Contractor Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.4 SUBMITTALS
A. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
KNRI 257081 01 31 00 - 3
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Temporary Storm Water Pollution Prevention Plan (SWPPP)
11. Historic Preservation Treatment Plan (HPTP)
12. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
B. Provide items listed to Contracting Officer at least one week prior to Pre-Construction Conference, or as directed by Contracting Officer.
1. Failure to submit items may result in:
a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.
b. Work shall not commence until written Notice to Proceed has been issued and Certificates of Insurance and SF1413 documents are received for Construction Contractor and all Subcontractors.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract
Time or Contract Sum, Construction Contractor shall state impact in RFI.
8. Construction Contractor's signature
9. Requested date for response
KNRI 257081 01 31 00 - 4
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Construction Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MANAGEMENT AND COMMUNICATION SOFTWARE
A. Use to manage project communication and document sharing during contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Reminder and tracking functions
KNRI 257081 01 31 00 - 5
12. Archiving functions
13. Notification of submittal and RFI statuses and current responsible party
14. Permits and addendums
B. Some documents are not suitable to be shared using NPS project management and communication software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with project team as appropriate.
1.7 PROJECT RECORD DRAWINGS
A. A set of record drawings shall be kept current with all updates to the construction drawings that incorporate the results of RFIs and all as-built conditions.
B. Record drawings shall be available to the Contracting Officer for inspection at the time of month progress payment requests to ensure they are current and encompass the work completed to date.
C. Complete record drawings are required deliverable of this contract. See Section 01 77 00 Closeout Procedures for additional information on project record drawings.
1.8 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. NPS/DSC Project website
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
20. NPS Final Accessibility Inspection
21. Environmental requirements
22. Permit requirements
23. As-constructed drawings
24. Saturday, Sunday, holiday and night work.
25. Reference materials
KNRI 257081 01 31 00 - 6
26. Value engineering
27. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences:
1. Conduct a pre-construction conference for all major scopes of work. These activities shall include:
a. erosion and sediment control installation,
b. culvert installations, temporary river crossing and primary access road installation
(Temporary Access Road 1 as shown on the Drawings),
c. secondary access road work (Access Road 2 as shown on the Drawings),
d. embankment excavation and fill,
e. tension crack repair work,
f. riprap installation, and
g. seeding and restoration.
2. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
3. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
KNRI 257081 01 31 00 - 7
g. Submittals
h. Possible conflicts
i. Compatibility requirements
j. Time schedules
k. Weather limitations
l. Manufacturer's written instructions
m. Warranty requirements
n. Compatibility of materials
o. Acceptability of substrates
p. Temporary facilities and controls
q. Space and access limitations
r. Regulations of agency(ies) with jurisdiction
s. Testing and inspecting requirements
t. Installation procedures
u. Coordination with other work
v. Required performance results
w. Protection of adjacent work
x. Protection of construction and personnel
y. Discussion of risk identification and mitigation.
4. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
5. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
6. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.9 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of NPDES permit requirements & Storm Water Pollution Prevention
Plan (SWPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Training for Contractor personnel in accordance with position requirements.
f. Monitoring and documentation of environmental procedures.
KNRI 257081 01 31 00 - 8
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Temporary Storm Water Pollution Prevention Environmental Management
4. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to Project.
2. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Temporary Storm Water Pollution Prevention
3. Pollution Prevention (P2) practices: Submit evidence of P2 training, participation in P2 programs, and familiarity with P2 practices.
4. Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.
1.10 PERMITS
A. General:
1. Permits and Responsibilities: Construction Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Construction Contractor shall also be responsible for damages to persons or property that occur as a result of Construction Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Construction Contractor will not be considered an agent of the Government. Construction Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. CWA Section 404 Standard Individual Permit – United States Army Corps of Engineers - Northwestern Division, Omaha District, North Dakota Regulatory
2. CWA Section 401 Water Quality Certification - North Dakota Department of Environmental Quality, Water Quality Division
3. North Dakota Sovereign Lands Permit - North Dakota State Water Commission Office of the State Engineer
4. Floodplain Permit / No Rise Certification – North Dakota Department of Water Resources
KNRI 257081 01 31 00 - 9
C. Potential Permits: Permits listed below were identified during the design…
This is the start of the file's text. The full file is on GovTribe.