B08_Section_J_Attachment_11_CLIN_Price_Sheet_updated_7_30_0003.pdf

PDF 136 KB Posted

Attached to
KNRI 257081¿ Knife River Indian Village National H
Solicitation number
140P2026R0086
Issued by

About this file

This document is a Contract Price Schedule for a federal construction solicitation issued by the National Park Service (NPS) Denver Service Center.

The solicitation (140P2026R0086) pertains to riverbank stabilization work at the Knife River Indian National Historic Site, specifically the Elbee Bend Bank project (PMIS: KNRI 257081). Offerors must submit a minimum of one Firm-Fixed-Price (FFP) offer that includes pricing for all base line items and option line items. The contract structure includes three base contract line items: (0010) Mobilization and Demobilization, (0020) River Embankment Stabilization, and (0030) Site Restoration. Two optional line items are available: (0040) Option A for Topsoil and Erosion work, and (0050) Option B for Temporary Access Road and Temporary River Crossing. Offerors must provide unit prices and total prices for lump-sum line items, with extended prices calculated based on quantity and unit price. All measurement and payment details are specified in project specifications Section 01 27 00. In case of pricing discrepancies, unit prices govern over extended prices, and summation errors are corrected by the stated total. All totals and extended prices must be rounded to whole dollars. Failure to complete the pricing schedule in full may render the proposal unacceptable.

View the file

Other files

File Type Posted
Sol_140P2026R0086_Amd_0006.pdf PDF
Attach_26_Amend_06_SF_1442_0006.pdf PDF
Attach_24_Amend_06_SF_30_140P2026R0086_0006.pdf PDF
Attach_25_Answers_to_Questions_Amendment_06_KNRI_0006.pdf PDF
Attach_23_Answers_to_Questions_Amendment_05_KNRI_0005.pdf PDF
Sol_140P2026R0086_Amd_0005.pdf PDF
Attach_22_Amend_05_SF_1442_0005.pdf PDF
Attach_21_Amend_05_SF_30_140P2026R0086_0005.pdf PDF
Sol_140P2026R0086_Amd_0004.pdf PDF
Attach_19_Answers_to_Questions_Amendment_04_KN_0004.pdf PDF
Attachment_19_KNIFE_RIVER_CONTROL_POINTS_0003.pdf PDF
Attachment_20__Sheet_4_Site_Survey_0003.pdf PDF
Sol_140P2026R0086_Amd_0003.pdf PDF
B08_Section_J_Attachment_16_KNRI_257081_Precon_SignIn_0003.pdf PDF
Attach_18_Answers_to_Questions_Amendment_03_KN_0003.pdf PDF
Amendment_02_Attach_19_Answers_to_Questions_0002.pdf PDF
Sol_140P2026R0086_Amd_0002.pdf PDF
Amendment_02_SF_1442_140P2026R0086_0002.pdf PDF
Amendment_01_B08_Section_J_Attachment_09_Solit_PSP_Vol_II_SubKPlan_0001.docx DOCX document
Sol_140P2026R0086_Amd_0001.pdf PDF
Amendment_01_Attach_17_Answers_to_Questions_Amendment_01_0001.pdf PDF
B08_Section_J_Attachment_14_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Section_J_Attachment_16_KNRI_257081_Precon_SignIn.pdf PDF
B08_Section_J_Attachment_02_KNRI257081_Specifications_Div31_32.pdf PDF
B08_Section_J_Attachment_15_KNRI_257081_QA_0003_(1).pdf PDF
B08_Section_J_Attachment_04_Appendix_A___Geological_Investigation_Field_Report_for_Knife_River.pdf PDF
B08_140P2026R0086_Solicitation.pdf PDF
B08_Section_J_Attachment_07_Appendix_D.pdf PDF
B08_Section_J_Attachment_13_SL2521_Permit.pdf PDF
Sol_140P2026R0086.pdf PDF
B08_Section_J_Attachment_12_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.docx DOCX document
B08_Section_J_Attachment_09_Solit_PSP_Vol_II_SubKPlan.docx DOCX document
B08_Section_J_Attachment_06_Appendix_C___Permit_Conditions_affecting_the_construction_process_for_Knife_River.pdf PDF
B08_Section_J_Attachment_01_KNRI257081_Specifications_Div01.pdf PDF
B08_Section_J_Attachment_08_Wage_Determination.pdf PDF
B08_Section_J_Attachment_05_Appendix_B_-_Geotechnical_Recommendations_Report_for_Knife_River.pdf PDF
B08_Section_J_Attachment_03_0_KNRI_Plan_Set_20250124_stamped.pdf PDF
B08_Section_J_Attachment_11_CLIN_Price_Sheet_-_Services.xlsx XLSX spreadsheet
B08_Section_J_Attachment_10_Solit_PSP_Vol_II_GenRefs.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date 06/17/2026

Solicitation No.

140P2026R0086

National Park Service (NPS) – Denver Service Center (DSC) KNRI 257081 – Riverbank Stabilization

Page

CONTRACT PRICE SCHEDULE

SOLICITATION NUMBER: 140P2026R0086

PARK - PMIS: KNRI 257081

PROJECT TITLE: Knife River Indian National Historic Site – Elbee Bend Bank

Offerors are required to submit, at a minimum, one (1) Firm-Fixed-Price (FFP) offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Please complete Attachment XX Contract Price Schedule (include this sentence if not using table below). Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals and extended prices to whole dollars.

CONTRACT LINE-

ITEM NUMBER (CLIN) CONTRACT LINE ITEM (CLI) TITLE QUANTITY UNIT OF

MEASURE

UNIT

PRICE

TOTAL

PRICE

0010 Mobilization and Demobilization 0020 River Embankment Stabilization 0030 Site Restoration TOTAL BASE PRICE (Contract Line-Item Number 1 through 3) ------------------------------------ 0040 OPTION A, Topsoil And Erosion

0050 OPTION B, Temporary Access Road and Temporary River Crossing

TOTAL PRICE FOR ALL OPTIONS (Contract Line-Item Numbers 0040 through 0050) -------------------- TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (CLIN 0010 through 0050) All measurement and payment information are included in the project specifications, Section 01 27 00.

File details come from the government source that posted it. Updated .