This document provides details for a federal solicitation seeking preservation and rehabilitation services. The solicitation number is 140P2021R0111 issued by the Department of the Interior National Park Service National Office. Services are required for the Carter G. Woodson Home and Adjacent Properties located in the District of Columbia. Responses are due by the date listed in the attached specifications file B08_RFP_Attach_1_-_Specifications__NACE_242190.pdf. The opportunity type is listed as a solicitation seeking preservation and rehabilitation services to restore the Carter G. Woodson Home and Adjacent Properties. Award date and pricing details are provided in the attached specifications file.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL CAPITOL PARKS - EAST
1538-1542 NINTH STREET, NW
WASHINGTON, DC
RESTORATION OF THE HISTORIC CARTER G. WOODSON
HOME AND ADJACENT PROPERTIES – PHASE 2
PMIS NO. 242190
PROJECT SPECIFICATIONS
Division 01 - 49
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
Final Construction Documents July 8, 2021
07/21/21
NACE 242190 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation for Historic Preservation Projects 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 57 19.11 Indoor Air Quality Management 01 57 19.12 Noise & Acoustics Management 01 57 23 Under-an-Acre Pollution Prevention 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 74 19B Standard Solid Waste Conversions 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training 01 91 14 Total Building Commissioning
DIVISION 02 – EXISTING CONDITIONS
02 08 00 Asbestos Abatement 02 25 00 Underpinning 02 41 19 Selective Demolition 02 83 00 Lead in Construction
DIVISION 03 – CONCRETE
03 33 00 Cast-in-Place Concrete
DIVISION 04 – MASONRY
04 20 00 Unit Masonry
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 05 31 00 Steel Decking 05 50 00 Metal Fabrications 05 51 13 Metal Pan Stairs 05 73 00 Decorative Metal Railings
NACE 242190 TOC-2
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 06 20 23 Interior Finish Carpentry 06 41 16 Plastic-Laminate-Clad Architectural Cabinets
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 14 16 Cold Fluid-Applied Waterproofing 07 21 00 Thermal Insulation 07 61 00 Sheet Metal Roofing and Wall Panels 07 72 00 Roof Accessories 07 84 13 Penetration Firestopping 07 84 43 Joint Firestopping 07 92 00 Joint Sealants
NACE 242190 TOC-3
VOLUME 2
DIVISION 08 – OPENINGS
08 01 13 Hollow Metal Doors and Frames 08 01 52.93 Historic Treatment of Wood Windows 08 14 16 Flush Wood Doors 08 31 13 Access Doors and Frames 08 71 00 Door Hardware 08 71 13 Automatic Door Operators 08 80 00 Glazing
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 09 23 00 Gypsum Plastering 09 23 01 Acoustical Plaster System 09 29 00 Gypsum Board 09 30 13 Ceramic Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 91 13 Exterior Painting 09 91 23 Interior Painting 09 93 00 Staining and Transparent Finishing
DIVISION 10 – SPECIALTIES
10 14 23.16 Room Identification Panel Signage 10 21 13.19 Plastic Toilet Compartments 10 28 00 Toilet, Bath, and Laundry Accessories 10 44 13 Fire Protection Cabinets 10 44 16 Fire Extinguishers
DIVISION 12 – FURNISHINGS
12 24 13 Roller Window Shades 12 36 61.16 Solid Surfacing Countertops 12 48 13 Entrance Floor Mats and Frames
DIVISION 14 – CONVEYING EQUIPMENT
14 21 23.16 Machine Room-Less Electric Traction Passenger Elevators 14 42 00 Wheelchair Lifts
DIVISION 21 – FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems
NACE 242190 TOC-4
DIVISION 22 - PLUMBING
22 05 16 Expansion Fittings and Loops for Plumbing Piping 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 22 05 18 Escutcheons for Plumbing Piping 22 05 19 Meters and Gages for Plumbing Piping 22 05 23 General-Duty Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 48.13 Vibration Controls for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 07 19 Plumbing Piping Insulation 22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties 22 11 23.21 Inline Domestic Water Pumps 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 42 13.13 Commercial Water Closets 22 42 13.16 Commercial Urinals 22 42 16.13 Commercial Lavatories 22 42 16.16 Commercial Sinks 22 47 13 Drinking Fountains
NACE 242190 TOC-5
VOLUME 3
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING
23 05 00 General Requirements for HVAC 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 48 Vibration Isolation and Seismic Restraints for Mechanical Components 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing Adjusting and Balancing for HVAC 23 07 13 Duct Insulation 23 07 19 HVAC Piping Insulation 23 09 23 Direct Digital Control (DDC) System for HVAC 23 09 93.11 Sequence of Operations for HVAC DDC 23 23 00 Refrigerant Piping 23 31 13 Metal Ducts 23 33 00 Air Duct Accessories 23 33 46 Flexible Ducts 23 34 16 Centrifugal HVAC Fans 23 37 13.13 Air Diffusers 23 81 26 Split System Air Conditioners 23 82 16.14 Electric-Resistance Air Coils 23 82 36 Finned-Tube Radiation Heaters 23 82 39.13 Electrical Cabinet Unit Heaters
DIVISION 26 - ELECTRICAL
26 05 19 Low Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceways and Boxes for Electrical Systems 26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 48 Seismic Controls for Electrical Systems 26 05 53 Identification for Electrical Systems 26 05 72 Overcurrent Protective Device Short-Circuit Study 26 05 73 Overcurrent Protective Device Coordination Study 26 05 74 Overcurrent Protective Device Arc-Flash Study 26 09 23 Distributed Digital Lighting Control System 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 13 Fuses 26 28 16 Enclosed Switches and Circuit Breakers 26 51 19 LED Interior Lighting 26 56 00 Exterior Lighting Appendix A Lighting Fixture Schedule Appendix B Standard Sequence of operations
NACE 242190 TOC-6
DIVISION 27 – COMMUNICATIONS
27 05 36 Cable Trays for Communications Systems 27 11 00 Communications Equipment Room Fittings 27 13 13 Communications Copper Backbone Cabling 27 15 13 Communications Copper Horizontal Cabling 27 15 33 Communications Coaxial Horizontal Cabling
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 15 00 Access Control 28 20 00 Video Surveillance 28 31 00 Intrusion Detection 28 46 21.11 Addressable Fire Alarm Systems
DIVISION 31 - EARTHWORK
31 10 00 Site Clearing 31 20 00 Earth Moving 31 50 00 Excavation Support and Protection
DIVISION 32 – SITE UTILITIES
32 17 13 Precast Concrete Parking Bumpers 32 17 23 Pavement Markings
DIVISION 33 – SITE UTILITIES
33 41 00 Site Storm Utility Drainage Piping DC Water Specs
NACE - 242190 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: 1538-42 9th Street NW Washington, DC.
B. The Work consists of the following:
1. The Work includes rehabilitation of adjacent structures 1540 & 1542 and sensitive modifications to the historic Carter G. Woodson home to allow full visitor access, the addition of interpretive media, and two office spaces. Work includes but is not limited to site work, interior reconstruction, renovation, modification and partial additions, HVAC, plumbing, fire protection and security systems, as well as electrical, AV, and lighting to support renovated spaces and exhibits.
2. Project is designed to comply with a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System, as specified in Division 01 Section "Sustainable Design Requirements."
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend of successful completion of preparatory work under this contract.
1. Carter Woodson exhibits: A separate contract will be awarded for production and installation of interpretive exhibits.
NACE - 242190 01 11 00 - 2
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Confine storage of materials to rear yard area of the property.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways, sidewalks, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. The building will be closed to the public during construction.
1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate
NACE - 242190 01 11 00 - 3
Government usage. Perform the Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
1.7 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 9:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Requires written approval from contracting officer
2. Early Morning Hours: work prior to 9:00 am must adhere to DC noise restrictions and have written approval from the contracting officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Maximum interruption time shall be 48 hours.
Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
NACE - 242190 01 11 00 - 4
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.10 ADDITIONAL REPORTS
A. A report entitled Limited Hazmat Survey Report has been prepared by Froehling & Robertson, Inc., dated August 1, 2012.
B. A report entitled Level-1 Pre-Acquisition Survey has been prepared by URS Group dated January 23, 2006.
C. A report entitled Level 2 Asbestos and Lead-Based Paint Survey has been prepared by URS Group dated February 24, 2006.
D. Copies of these reports are available to all plan holders with this package.
E. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
NACE - 242190 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
NACE - 242190 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
NACE - 242190 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their
NACE - 242190 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
NACE - 242190 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………9%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
NACE - 242190 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
NACE - 242190 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1: Building and Site Construction.
1. This item consists of the complete rehabilitation of the Carter G. Woodson Home and Adjacent Structures as indicated in the Contract Documents. The Work includes selective removals, protection of recently completed work throughout the site, general construction, and building systems construction. Coordination with and extension of recently completed work is required.
2. Measurement for payment will be per cent complete.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
NACE - 242190 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
1.2 DEFINITIONS
A. Authority Having Jurisdiction (AHJ):
A person who is responsible for enforcing the requirements of a code or standard, or for approving equipment, materials, an installation, or a procedure, related to structural fire management. This person is typically the National Park Service (NPS) Regional Structural Fire Manager (RSFM)
B. Construction Permits: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service (NPS). Examples of typical Contractor Provided Permits are:
NPDES Construction Permit (ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.
C. Government Furnished Permits: Permits that are obtained by NPS during the design process and provided to the contractor for compliance with the provisions through construction. These permits may address impacts to natural resources, construction, stormwater, etc.
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
NACE - 242190 01 31 00 - 2
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
NACE - 242190 01 31 00 - 3
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).
3. Number of Copies: Submit electronic copies only.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Contracting Officer (CO) will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.
NACE - 242190 01 31 00 - 4
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Preparation Format: AutoCad.dwg, operating in Microsoft Windows operating system, or as approved by the Contracting Officer.
3. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
4. Contracting Officer (CO) will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractors Commissioning Plan.
13. Historic Preservation Treatment Plan.
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
E. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
NACE - 242190 01 31 00 - 5
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.
CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
NACE - 242190 01 31 00 - 6
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.6 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period.
The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
NACE - 242190 01 31 00 - 7
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. NPS/DSC SharePoint Project website.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. Permit requirements.
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials.
26. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements.
NACE - 242190 01 31 00 - 8
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Sustainable design requirements
i. Review of mockups.
j. Possible conflicts.
k. Compatibility requirements.
l. Time schedules.
m. Weather limitations.
n. Manufacturer's written instructions.
o. Warranty requirements.
p. Compatibility of materials.
q. Acceptability of substrates.
r. Temporary facilities and controls.
s. Space and access limitations.
t. Regulations of agency(ies) with jurisdiction.
u. Testing and inspecting requirements.
v. Installation procedures.
w. Coordination with other work.
x. Required performance results.
y. Protection of adjacent work.
z. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
NACE - 242190 01 31 00 - 9
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan(WMP).
c. Implementation of the Indoor Air Quality (IAQ) Management Plan.
d. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).
e. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
f. Training for Contractor personnel in accordance with their position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Indoor Air Quality (IAQ) Management.
4. Noise & Acoustics Management.
5. Temporary Storm Water Pollution Prevention Environmental Management.
6. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Indoor Air Quality (IAQ) Management.
c. Noise & Acoustics Management.
d. Temporary Storm Water Pollution Prevention.
4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
1.9 PERMITS
A. General:
NACE - 242190 01 31 00 - 10
1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence.