This document is a Frequently Asked Questions (FAQ) attachment to a Request for Quotations (RFQ) for telecommunications infrastructure work at Lake Roosevelt National Recreational Area (LARO). The solicitation number is 140P8326Q0042, and the project involves the installation, wiring, and replacement of telecommunications cable with fiber optic infrastructure. This is a 100% Small Business Set-Aside restricted to firms meeting the NAICS code 237130 (Power and Communication Line and Related Structures Construction) with a size standard of $45 million in average annual gross receipts over the past three years. The Government seeks offers between $150,000 and $200,000, though this is neither a ceiling nor a floor; offers outside this range may be considered if they represent best value.
A mandatory pre-proposal site visit is scheduled for June 24, 2026, at 1:30 PM Pacific Time at the Kettle Falls North District Office, with RSVP required to hal_hoversten@ios.doi.gov or nathan_krohn@nps.gov. Quotes must be submitted by email to hal_hoversten@ios.doi.gov by the deadline specified in Standard Form 1442 (deadline to be confirmed via SAM.gov), with questions due no later than June 25, 2026, at 3:00 PM ET. The contract will be firm-fixed-price subject to Davis-Bacon wage rate requirements, with an anticipated award in early July 2026 and a 120-day period of performance beginning after notice to proceed. All offerors must maintain active SAM.gov registration with current representations and certifications prior to submission. Required bonds include a performance bond at 100% of the offered price and liability insurance; bid bonds are not required. Prospective offerors must monitor SAM.gov for any amendments and download all solicitation attachments, which include a Statement of Work, drawings, photos, wage rates, and required forms.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| KF_Fiber_06242026_Site_Visit_Q_A_0002.pdf | ||
| Stevens_Co_Permit_For_Work_In_Right_of_Way_-_EDITABLE_0002.pdf | ||
| Sol_140P8326Q0042_Amd_0002.pdf | ||
| Sol_140P8326Q0042_Amd_0001.pdf | ||
| 06242026_Prebid_Site_Visit_Signin_Sheet_0001.pdf | ||
| Sol_140P8326Q0042.pdf | ||
| B08_Attachment_07_Price_Schedule_and_Forms_to_Submit_with_Quote.docx | DOCX document | |
| B08_KEY_PERSONNEL.docx | DOCX document | |
| B08_Relevant_Project_Experience_Questionnaire.docx | DOCX document | |
| A06_KF_Fiber_Route_Maps.pdf | ||
| Simplified_Construction_Attachment_2_Terms_Provisions_Clauses.docx | DOCX document | |
| WD_WA20260131_20260518.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation (RFQ) no. 140P8326Q0019 – Stabilize Stehekin Valley Road at 8 Mile North Cascades National Park (NOCA) Attachment 1, Frequently Asked Questions (FAQ)
Solicitation (RFQ) no. 140P8326Q0019 – Stabilize Stehekin Valley Road at 8 Mile North Cascades National Park (NOCA) Attachment 1, Frequently Asked Questions (FAQ)
Solicitation (RFQ) no. 140P8326Q0042 – Telecom Lines Replacement Lake Roosevelt National Recreational Area (LARO) Attachment 1, Frequently Asked Questions (FAQ)
1. This document reiterates and emphasizes information in the Request for Quote (RFQ) package and is provided solely for the convenience of prospective offerors.
Refer to the complete solicitation package for detailed requirements, which consists of the following documents:
· This document “FAQ” as Attachment 1
· Terms/Provisions/Clauses (FAR 15.204-1 Uniform Contract Format, Sections B – M) as Attachment 2
· Project Specifications (Statement of Work) as Attachment 3
· Photos as Attachment 4
· Drawings as Attachment 5
· Department of Labor Construction Wage Rates (Davis-Bacon Wage Rates) as Attachment 6
· Forms to Return with Quote as Attachment 7 NOTE: Attachment 7 is comprised of the following fill-in documents: Price Schedule, Relevant Experience, Technical Approach, and FAR Provisions 52.204-24. Complete all pages and return as part of the quotation.
· Technical Information/Past Performance Form as Attachment 8
2. Who can participate in this procurement?
This project is being solicited and will be awarded as a 100% Small Business Set-Aside in accordance with Federal Acquisition Regulation (FAR) Subpart 19.502-2. The NAICS code is 237130 – Power and Communication Line and Related Structures Construction with an associated small business size standard of $45 million average annual gross receipts for the past three years.
3. What is the estimated value?
AFFORDABILITY. The Government seeks offers with a total price between $150,000 and $200,000. Offerors should not interpret this figure as a ceiling (or as a floor) on offers; rather, this information is provided as a courtesy to prospective offerors. The Government may select an offer for award with a price below, at, or exceeding this figure if it finds that offer provides the best value and funds are available.
4. What type of contract will be issued?
All work will be performed under a single firm-fixed-price construction contract subject to the Construction Wage Rate Requirements in FAR Part 22.4.
5. Will there be a pre-proposal site visit? YES
SITE VISIT:
Yes, June 24, 2026 at 1:30 PM Pacific Time.
Please RSVP by email to hal_hoversten@ios.doi.gov / nathan_krohn@nps.gov Participants will meet at the Kettle Falls North District Office, 1368 Kettle Park Road, Kettle Falls, WA 99141
6. Project Period of Performance.
The anticipated Period of Performance (POP) for this project is 120 days after issuance of notice to proceed. The Government anticipates making an award early July 2026. The pre-construction conference will occur approximately one week after award. Notice to Proceed will be issued after the Government receives the required paperwork from the awardee that will be discussed as part of the conference. The awardee shall be required to commence work under this contract within 10 calendar days after the date the awardee receives the notice to proceed, prosecute the work diligently, and complete the entire work (including any last minute punch list requirements) ready for use not later than 120 days. The time stated for completion shall include final cleanup of the premises. The overall total POP of the contract includes time for invoicing via the IPP payment system.
7. What types of bonds and insurance will be required?
· NOT REQUIRED - Bid bond (FAR clause 52.228-1):
· REQUIRED - Performance bond (FAR clause 52.228-15) 100% of offered price
· REQUIRED -– Liability Insurance – Department of Interior (DIAR clause 1452.228-70)
· Contractors unfamiliar with Government contracts and bonds may find it useful to read Part 28 of the FAR (https://www.acquisition.gov/?q=/browse/far/52). Contractors should also be familiar with the U.S. Treasury listing of approved sureties, information can be located at https://www.fiscal.treasury.gov/fsreports/ref/suretyBnd/c570.html
8. System for Award Management (SAM) Registration Requirements
The System for Award Management (SAM) is an official U.S. Government database of entities wishing to do business with the federal Government. There is NO fee to register at this site. Prior to the solicitation closing date, all offerors must establish and/or maintain an active registration and complete the online representations and certifications at https://SAM.gov. Offerors shall have a current (not pending or expired status) SAM.gov registration upon submission of offer in order to be considered eligible for award. Small business may obtain assistance with SAM by contacting the Small Business Administration at https://www.sba.gov/local-assistance/federal-contracting-assistance or the Association of Procurement Technical Assistance Centers at https://www.aptac-us.org/find-a-ptac/?state=CA
9. Where and how do I submit my Proposal?
Quotes shall be submitted by email to hal_hoversten@ios.doi.gov . Hard copies of quotes will not be accepted. It is the Quoter’s responsibility to ensure quote submitted is fully received. Refer to Solicitation Attachment 2, Sections L-Instructions to Quoters, and Section M-Evaluation Factors, for full details on what to include in quote.
10. When is my quote due?
Unless changed by amendment, your quote is due by the date and time specified in Item 13 of the Standard Form 1442, Solicitation, Offer, and Award. Refer to FAR clause 52.215-1. If the quote due date is extended, the new due date and time will be stated in the associated amendment.
11. How will I know if the solicitation has changed?
Prospective quoters will be required to visit the SAM.gov website periodically to check for amendments and other changes to the solicitation documents; no other notifications will be sent. No hard copies of the solicitation will be mailed or issued. It is the responsibility of the offerors to monitor the SAM website to download all amendments and attachments which may also be issued against the solicitation prior to the solicitation’s closing date. The website address for SAM.gov is https://sam.gov/content/opportunities. Solicitation number is 140P8326Q0042.
12. How can I get more information?
· Read the full Request for Quote (RFQ) package first. If you have questions, send an e-mail message to the Contracting Officer at hal_hoversten@.ios.doi.gov .
· Questions about this RFQ shall be submitted no later than Thursday June 25, 2026 at 3:00 pm ET. Questions received after the due date/time may not be answered.
· Note: Amendment(s) to the solicitation answering any questions relative to these documents will be timely posted at the SAM.gov website (https://sam.gov/content/opportunities).